The Licence Conditions of TP Southern Odisha Distribution Limited (TPSODL)
RegulationDated 26 Mar 2021In force from 1 Jan 2021OERC/Engg./1/2021/408 dated 26.03.2021
Summary
Summary written by software, from pages 1 to 31 of 41. Check the regulator's original before you rely on it.
This is OERC's order of 26 March 2021 that rewrites the licence conditions of the former SOUTHCO distribution utility and hands them to TP Southern Odisha Distribution Limited (TPSODL). Pages 1–4 give the history: SOUTHCO's 1999 licence and its 2006 conditions (p1); revocation of the licence in 2015 and appointment of an Administrator, upheld by APTEL and the Supreme Court (p1); the 2020 competitive sale process under s.20 that selected Tata Power (TPCL) and led to TPSODL's incorporation on 25.12.2020 as the SPV, held 51% by TPCL and 49% by GRIDCO (p2). The Vesting Order of 28.12.2020 fixed 01.01.2021 as the date the utility and licence transferred (p2), and this order is the promised amendment of the licence conditions within 90 days of that date (p3). It directs the licensee to publish the conditions on its website and in one English and two Odia dailies (p3–4), and provides that any conflict with the Vesting Order or the RFP documents goes to the Commission, whose decision is final (p4).
Pages 5–31 carry the licence conditions themselves. Part I (pp6–11) gives the short title, the area of supply — the City, Berhampur, Aska, Bhanjanagar, Jeypore and Rayagada circles — the definitions, and the 25-year term running from 1 January 2021, with no exclusivity in the area of supply. Part II (pp12 onward) sets out the general conditions for distribution licensees, adapted from Appendix 4A of the OERC (Conduct of Business) Regulations: compliance with law and despatch-centre directions, the licensee's functions and power procurement (including the obligation to buy from GRIDCO), franchisees, open access, trading without a separate licence, affiliate transactions, accounts and financial reporting, major incident reporting, the investment approval regime, transfer of assets and charges, licence fees, suspension and revocation, amendment procedure, dispute resolution, grid and distribution codes, consumer service obligations, and system and performance standards.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read OERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (9 pages) and for drafts on 21 Nov 2026. A document OERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of OERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.