August 16, 2023
No. F-9 (34)/RG/UERC/2023/543: In exercise of the powers conferred under section 61(h), 86(1)(e) read with section 181 (zd) & (zp) of the Electricity Act, 2003, and all other powers enabling it in this behalf, and after previous publication, the Uttarakhand Electricity Regulatory Commission hereby makes the following regulations, namely:
Provided further that Regulations in Chapter 4 & 5 (except clause (B) & (C) of sub-
Regulation (1) of Regulation 27) of these Regulations shall not be applicable for generating stations commissioned prior to coming into effect of these Regulations and their existing tariffs shall continue to be applicable;
Provided also that clause (d) of sub-Regulation (3) of Regulation 11, 2nd & 3rd proviso of sub-Regulation 7 of Regulation 15 shall be applicable to such stations commissioned prior to coming into effect of these Regulations;
Provided that the tariff computation norms shall be in accordance with the Regulations prevalent during the year of commissioning of those stations;
Provided also that normative levelised tariff of 12 paise/unit, over and above the generic tariff for solar thermal/PV generating stations and normative levelized tariff of 5 paise/unit, over and above the generic tariff for Small Hydro Plants as specified in Regulation 16(1)(c) shall also be applicable to such stations commissioned prior to coming into effect of these Regulations;
Provided also that the Regulations other than those in Chapter 4 and 5 shall apply to other generating stations located in the State of Uttarakhand, which are based on Renewable Sources of Energy including non-fossil fuel based Co-generation and which transmit and/or supply electricity to any person other than the distribution licensee of the State utilizing State Transmission and/or Distribution System.
Provided that implementation of Canal Bank and Canal Top Solar Power Plants by the eligible government organisation shall be done through tariff based competitive bidding process. In such cases PPA for sale of power from these plants shall be signed with
distribution licensee at a tariff which shall be 8% higher than the tariff quoted by L-1 bidder, however, the tariff plus a margin of 8% shall not exceed the generic tariff determined by the Commission for the year of commissioning.
Provided further that in no case PPA for purchase of power by the distribution licensee shall be executed at a tariff exceeding the ceiling tariff as specified by the Commission in accordance with the regulations.
(1) Unless the context otherwise requires, the words used in these Regulations shall have the following meaning:
(i) "Act" means the Electricity Act, 2003 (36 of 2003);
(vi) "Biomass gasification" means a process of incomplete combustion of biomass resulting in production of combustible gases consisting of a mixture of Carbon monoxide (CO), Hydrogen (H2) and traces of Methane (CH4), which is called producer gas;
(vii) "Biogas" means a gas created when organic matter like crop residues, sewage and manure breaks down in an oxygen-free environment (ferments);
(viii) "Canal Bank Solar PV plants" means the Solar PV power plants installed on the banks of the canal.
(ix) "Canal Top Solar PV Plants" means the Solar PV power plants installed on the top of the canal.
(x) "Capacity Utilisation Factor (CUF)" shall mean the total energy sent out during the period expressed as a percentage of installed capacity reduced by the normative auxiliary consumption in that period.
$$CUF = \frac{ESO \times 10^7}{IC \times (100 - AUX) \times H} %$$
Where,
ESO-Energy Sent Out Ex-bus, i.e. at interconnection point, in MU during the period,
IC- Installed capacity in MW,
AUX - % Normative Auxiliary Consumption
H - Number of hours in the period
use" shall be construed accordingly.
Provided that in case of Small Hydro Plants the date of commissioning shall not be linked to achieving maximum continuous rating, nevertheless the generator will have to demonstrate the same within three years of commissioning.
The date of commissioning of Solar PV plant shall be considered as the date of first injection of power into the licensee's grid after completion of the project in all respect subsequent to compliance of initial three prerequisites, i.e.
Provided that minimum 75% Performance Ratio based on the rated installed capacity in kW or MW is demonstrated within Three months from the date of first injection of power into licensee's grid on compliance of aforesaid three pre-requisites.
due to conditions of grid or power system, beyond the control of the generating station resulting in spillage of renewable resources."
civil disturbance;
iii. Unavoidable accident, fire, explosion, radioactive contamination and toxic dangerous chemical contamination;
(xxvi) "Green Energy" means the electrical energy from renewable sources of energy including hydro and storage (if the storage uses renewable energy) or any other technology as may be notified by the Government of India from time to time and shall include any mechanism that utilizes green energy to replace fossil fuels including production of green hydrogen or green ammonia or any other source, as may be, determined by the Central Government.
(xxvii) "Grid interactive roof top solar PV plants (GRPV)/ Grid interactive small solar PV plants (GSPV)" means Solar PV plant installed on the rooftop of a building and includes plants installed on open contiguous land within the premises and connected to the grid under net metering arrangement having maximum capacity as specified under these Regulations.
(xxviii) "Group Net Metering" means an arrangement whereby surplus energy is generated and injected from a solar power plant through net meter and such surplus energy exported shall be adjusted in more than one electricity service connection(s) of the same consumer either at the same or different premise located within the same distribution licensee's area of supply;
(xxix) "Gross Calorific Value" or "GCV" in relation to a fuel used in generating station means the heat produced in kCal by complete combustion of one kilogram of solid fuel or one litre of liquid fuel or one standard cubic meter of gaseous fuel, as the case may be;
(xxx) "Gross Metering" means a mechanism whereby the total solar energy generated from GRPV/GSPV of a Prosumer and the total energy consumed by the Prosumer are accounted separately through metering arrangements and for the billing purpose, the total energy consumed by the Prosumer is accounted at the applicable retail tariff and total solar power generated is accounted for at feed-in-tariff determined by the Commission.
(xxxi) "Gross Station Heat Rate" or "GSHR" means the heat energy input in kCal required to generate one kWh of electrical energy at generator terminals of a thermal generating station;
(xxxii) "Hybrid Solar Thermal Power Plant" means the solar thermal power plant that uses other forms of energy input sources alongwith solar thermal energy for electricity generation, and wherein not less than 75% of electricity is generated from solar energy component.
(xxxiii) "Hybrid Wind Solar Power Plant" means the hybrid plant where Solar photovoltaic (PV) array coupled with a wind turbine and configured to operate at the same point of grid connection.
(xxxiv) "Indian Electricity Grid Code (IEGC)" means the Grid Code specified by the Central Electricity Regulatory Commission under clause (h) of sub-section (1) of section 79 of the Act;
(xxxv) "Infir Power" means electricity generated during trial runs prior to commercial operation of a unit of a generating station;
(xxxvi) "Installed Capacity" or "IC" means the summation of the name plate capacities of the units in the generating station or the capacity of the generating station (reckoned at the generator terminals);
(xxxvii) "Inter-connection Point" in respect of all the RE based generating stations, except GRPV/GSPV, shall mean interface point of line isolator on outgoing feeder on HV side of generator transformer in the switching yard of renewable energy generating facility with the transmission system or distribution system.
Provided that in respect of GRPV/GSPV, Inter-connection Point shall mean the interface of solar power generation facility under net metering arrangement with the network of licensee and shall normally be the point where export/import meter is installed to measure the energy transfer between the licensee and the eligible consumer/Prosumer.
(xxxviii) "MNRE" means the Ministry of New and Renewable Energy of the Government of India;
(xxxix) "Municipal solid waste" means and includes commercial and residential wastes generated in a municipal or notified areas in either solid or semi-solid form excluding industrial hazardous wastes but including treated bio-medical wastes;
(xi) "Net-metering" means a mechanism whereby solar energy exported by the GRPV/GSPV of a Prosumer is deducted from energy imported from the Grid in units (kWh) to arrive at the net imported or exported energy and the net energy import or export is billed or credited or carried-over by the distribution licensee on the basis of the applicable retail tariff by using a single bidirectional energy meter for net-metering at the point of supply.
(xli) "Net-meter" means an appropriate bi-directional energy meter capable of recording both import from the grid and export of electricity to the grid by the Solar Project
(xlii) "Non-fossil Fuel Based Co-generation" means the process in which more than one form of energy (such as steam and electricity) are produced in a sequential manner by use of biomass provided the project may qualify to be a co-generation project if it fulfills the eligibility criteria as specified in Regulation 4(2)(e).
(xliii) "Non-Peak Hour" means other than Peak hours as may be decided by the Commission from time to time.
(xliv) "Open Access" means the non-discriminatory provision for the use of transmission lines or distribution system or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with the regulations specified by the Appropriate Commission;
(xlv) "Open Access Regulations" means the Uttarakhand Electricity Regulatory Commission (Terms and Conditions of Intra-State Open Access) Regulations, 2015 as amended from time to time;
(xlvi) "Operation and Maintenance Expenses" or "O&M Expenses" means the expenditure incurred in operation and maintenance of the generating station or part thereof, including the expenditure on manpower, repairs, spares, consumables, insurance and overheads;
(xlvii) "Parallel Operation Charges" means charges determined by the Commission and to be recovered for cost of arranging the parallel operation from the concerned consumer of distribution licensee and/or transmission licensee, as the case may be, for availing the parallel operation.
(xlviii) "Peak Hours/Off Peak Hours" means particular hours of the day as may be decided by the Commission from time to time;
(xlix) "Performance Ratio" (PR) means the ratio of plant output versus installed plant capacity at any instance with respect to the radiation measured.
$$PR = \frac{\text{Measure output in kW}}{\text{Installed Plant capacity in kW}} \times \frac{1000 \text{ W/m}^2}{\text{Measured radiation intensity in W/m}^2}$$
(I) "Power Purchase Agreement" or "PPA" means a long term agreement between a generating company and a distribution licensee for supply of power on the terms and conditions specified therein and with the provision that the tariff for sale of power shall be as determined by the Commission from time to time;
(li) "Premises" means the land, building or infrastructure or part or combination thereof including the rooftops or/and elevated areas owned by the Eligible Consumer;
(lii) "Project/Plant" means a generating station and the evacuation system upto inter-connection point, as the case may be, and in case of a small hydro generating station includes all components of generating facility such as dam, intake water conductor system, power generating station and generating units of the scheme, as apportioned to power generation;
(liii) "Prosumer" means a person who consumes electricity from the grid and can also inject electricity into the grid of distribution licensee, using same point of supply.
(liv) "Refuse Derived Fuel" or RDF means segregated combustible fraction of solid waste other than chlorinated plastics in the form of pellets or fluff produced by drying, destoning, shredding, dehydrating, and compacting combustible components of solid waste that can be used as fuel;
(lv) "Renewable Energy" means grid quality electricity generated from renewable energy sources.
(lvi) "Renewable Energy Based Generating Stations and Non-fossil Fuel Based Co-generating Stations" means the power plants other than the conventional generating stations generating grid quality electricity from Renewable Energy Sources.
(lvii) "Renewable Energy Sources" means renewable sources such as small hydro, wind, solar including integration with combined cycle biomass, bio fuel co-generation, urban or municipal waste and other such sources as approved by MNRE.
(lviii) "Small Hydro Plant" means Hydro Power projects with station capacity/installed capacity upto and including 25 MW.
(lix) "Solar PV Plant (SPV)" means project designed for the supply of entire solar energy to distribution licensee and excludes Solar PV plants installed under Net-metering arrangement.
(lx) "Solar Thermal Power Project" means the project that uses sunlight for conversion into electricity through concentrated Solar Power Technology based on either line focus or point focus principle.
(lxi) "Saleable Energy" means the quantum of energy available for sale (ex-bus) after allowing for free energy, if any, to the home State;
(lxii) "State Grid Code" means the Uttarakhand Electricity Regulatory Commission (State Grid Code) Regulations, 2016 specified by Uttarakhand Electricity Regulatory Commission under clause (h) of sub-section (1) of section 86 of the Act;
(lxiii) "Tariff period" means the period for which tariff is to be determined by the Commission on the basis of norms specified under these Regulations;
(lxiv) "Third party owner" means a developer who generates solar energy from its plant established in the Premises of Eligible Consumer and who has entered into a lease/commercial agreement with such Eligible Consumer;
(lxv) "Useful Life" in relation to a unit of a generating station including evacuation system shall mean the following duration from the date of commercial operation (CoD) of such generation facility, namely:-
| (i) Wind energy power project | 25 years |
| (ii) Biomass power project including Municipal Solid Waste (MSW) and Refuse Derived Fuel (RDF) based power projects With rankine cycle technology. |
25 years |
| (iii) Non-fossil fuel cogeneration project | 25 years |
| (iv) Small Hydro Plant | 40 years |
| (v) Solar PV/Solar thermal/GRPV/GSPV / Canal bank/Canal top Solar PV plants. |
25 years |
| (vi) Biomass Gasifier based power project | 25 years |
(vii) Biogas based power project
25 years
Provided that where the operation of a plant was stopped due to a force majeure event, the life of the plant shall be extended by the period of such stoppage and, accordingly, the PPA shall be extended accordingly.
(lxvi) "Virtual Net Metering" means an arrangement whereby entire energy generated from Solar Energy based plant installed at Consumers premises or any other location is injected through Solar Energy Meter and the energy exported is adjusted in either one or more than one electricity service connection(s) of participating Consumer(s) located within the same Distribution Licensee's area of supply
(lxvii) "Year" means a financial year.
(2) Save as aforesaid and unless repugnant to the context or if the subject matter otherwise requires, words and expressions used in these regulations and not defined, but defined in the Electricity Act, 2003 or the UERC (State Grid Code) Regulations or the Commission's Regulations on determination of Tariff shall have the meanings assigned to them respectively in the Act or the State Grid Code or the Commission's Regulations as amended from time to time on determination of Tariff.
Topping cycle mode of co-generation - Any facility that uses non-fossil fuel input for the power generation and also utilizes the thermal energy generated for useful heat applications in other industrial activities simultaneously.
Provided that for the co-generation facility to qualify under topping cycle mode, the
sum of useful power output and one half the useful thermal output be greater than 45% of the facility's energy consumption, during season.
Explanation- For the purposes of this clause,
and configured to operate at the same point of grid connection.
(1) RE Based Generating Stations and Co-generating Stations shall indicate the capacity of its generating plant in the 'Detailed Project Report' (DPR) keeping in view the potential of electricity generation available from such source and its optimal utilization. It shall further be obliged to submit the DPR, progress of construction and details regarding commissioning of the generating plant or any other related information to the Commission in such form and manner as may be required by the Commission.
(2) The RE Based Generating Stations and Co-generating Stations shall:
(d) Submit audited annual accounts alongwith the copy of income tax returns filed on yearly basis to the Commission.
Provided that in case the generator is having more than one generating station in operation, it shall maintain and submit plant wise details of O&M expenses alongwith the audited accounts on yearly basis to the Commission.
(e) Shall establish a communication and data transfer system with State Load Dispatch Centre and Co-ordinate with State Load Dispatch Centre and the Regional Load Dispatch Center in respect to:
(i) Scheduling;
(ii) Exchange of data of quantity of electricity transmitted through the grid;
(iii) Real time grid operation and dispatch of electricity in accordance with IEGC and State Grid Code.
(3) The RE Based Generating Stations and Co-generating Stations shall abide by the grid discipline and install adequate protection equipment for safety of its system and human life. It shall not be entitled for any compensation in the event of grid failure or any interruptions or damage to the plant or its associated sub-station and transmission line on account of any occurrence in the grid.
(4) The RE Based Generating Stations and Co-generating Stations shall establish, operate and maintain generating station, the associated substation and dedicated transmission lines, if it exercises the option to establish the line. These shall be in accordance with:
(a) The technical standards for construction of electrical plants, electric lines and connectivity with the grid as specified by the Authority (section 73 (b) of the Electricity Act, 2003).
(b) Safety requirements for construction, operation and maintenance of electrical plants and electric lines as specified by the Authority (section 73 (c) of the Electricity Act, 2003).
(c) Grid standards for operation and maintenance of transmission lines as specified by Central Electricity Regulatory Commission/Central Electricity Authority or the State Transmission Utility (section 73 (d) of the Electricity Act, 2003).
(d) The conditions for installation of meters for supply of electricity as specified by the Authority or the State Transmission Utility (section 73 (e) of the Electricity Act, 2003).
(5) The RE Based Generating Stations and Co-generating Stations shall ensure the compliance of the 'IEGC', the State Grid Code and the Distribution Code as amended from time to time.
(6) The RE Based Generating Stations and Co-generating Stations shall ensure compliance of any general or specific direction issued and regulations made by the Commission for the generating companies.
(7) All Power Purchase Agreements (PPAs) signed by the generating stations existing on the date of notification of these regulations shall be amended in accordance with these regulations, if inconsistent with these Regulations, and such amended PPAs shall be valid for entire life of the RE Based Generating Stations and Co-generating Stations.
(8) The RE Based Generating Stations and Co-generating Stations shall coordinate with State Transmission Utility/Distribution Licensee for the purpose of planning and coordination relating to intra-state transmission/distribution system as provided under the Act.
(9) The RE Based Generating Stations and Co-generating Stations shall be under obligation to comply with the directions issued to it by the State Load Dispatch Centre failing which the plant shall be liable for appropriate action under the Electricity Act, 2003.
(10) The RE Based Generating Stations and Co-generating Stations shall pay fee and charges to the State Load Dispatch Centre as may be specified or directed by the Commission from time to time.
(11) In case of dispute with reference to quality of electricity or safe, secure and integrated operation of the grid or in relation to any direction issued by the State Load Dispatch Centre, the matter shall be referred to the Commission for adjudication.
distribution licensee intends to purchase power from such generator it shall sign the PPA within two months of offer made by the generating company. Otherwise, if the distribution licensee is not willing to purchase power from such generator it shall intimate the same to the generating company within one month of offer made by it.
Provided that where a GRPV/GSPV plant, is installed in the Premises, by a third party who intends to sell net energy (i.e. after adjustment of entire consumption of owner of the premise) to the distribution licensee, a tripartite agreement will have to be entered into amongst the third Party, the Eligible Consumer and such Distribution Licensee.
Provided further that the application for approval of PPA should be accompanied with an unconditional Technical Feasibility Report and the connectivity agreement signed with the Transmission/Distribution licensee shall form part of the PPA.
(1) Any consumer may elect to purchase green energy either upto a certain percentage of the consumption or its equivalent to 100% of its entire consumption and they may place a requisition for this with the distribution licensee, who shall procure such quantity of green energy and supply it and the consumer shall have the flexibility to give separate requisition for categories specified in Chapter-3 of these regulations.
(2) The consumer may purchase on a voluntary basis, more renewable energy, than he is obligated to do and for ease of implementation, this may be in steps of twenty five percent and going upto hundred percent.
(3) The tariff for the green energy shall be specified by the Commission in the Tariff Orders of Distribution Licensee which shall comprise of the average pooled power purchase cost of the renewable energy, cross-subsidy charges if any, and service charges covering the prudent cost of the distribution licensee for providing the green energy.
(4) Any requisition for green energy from a distribution licensee shall be for a minimum period of one year.
(5) The green energy purchased from distribution licensee or from Renewable Energy sources other than distribution licensee in excess of Renewable Purchase Obligation of the obligated entity shall be counted towards Renewable Purchase Obligation compliance of the distribution licensee.
(6) The accounting of renewable energy supplied at distribution level shall be on a monthly basis.
Provided that the 'open access' shall be allowed subject to the availability of surplus capacity in the State Transmission/Distribution System.
Provided that the captive power plants shall be required to pay Parallel Operation Charges to Distribution Licensee and/or Transmission Licensee, as the case may be, for utilization of grid support from Distribution Licensee and/or Transmission Licensee. The Commission shall specify the Parallel Operation Charges in its Tariff Orders for distribution licensee or transmission licensee, as the case may be, on annual basis.
Provided that levy of Open Access Charges on captive projects shall be governed by the relevant provisions of the Act and policies issued by Central/State Government from time to time.
| Year | Wind RPO | Hydro Purchase Obligation (HPO) | Other RPO | ||
|---|---|---|---|---|---|
| Solar RPO | Other than Solar | Total of Other RPO | |||
| 2023-24 | 1.60% | 0.66% | 5.00% | 19.81% | 24.81% |
| 2024-25 | 2.46% | 1.08% | 5.31% | 21.06% | 26.37% |
| 2025-26 | 3.36% | 1.48% | 5.68% | 22.49% | 28.17% |
| 2026-27 | 4.29% | 1.80% | 6.02% | 23.84% | 29.86% |
| 2027-28 | 5.23% | 2.15% | 6.33% | 25.10% | 31.43% |
| 2028-29 | 6.16% | 2.51% | 6.59% | 26.10% | 32.69% |
| 2029-30 | 6.94% | 2.82% | 6.77% | 26.80% | 33.57% |
Percentage RPO as stipulated above denotes Minimum Quantum of purchase from non-fossil fuel based co-generation and generation of electricity from renewable energy sources' as a percentage of total energy purchased from all sources/generated by the Obligated Entity during the year for own consumption.
Where, total energy purchased for different obligated entities shall be as under:
Provided that HPO obligation of the Distribution licensee may also be met out of the free power being provided to the State from HPPs (including PSPs and SHPs), commissioned after 8th March 2019 as per agreement at that point of time excluding the contribution towards LADE, if consumed within the Discom. Free Power (not that contributed for Local Area Development) shall be eligible for HPO benefit.
Provided that any shortfall remaining in achievement of Solar RPO category in a particular year can be met with excess energy consumed from eligible HPP (including PSPs and SHPs), commissioned after 8th March 2019 beyond 'HPO' for that year or with excess energy consumed from eligible 'Other than Solar RPO' under category of Other RPO for that year.
Provided further that any shortfall remaining in achievement of 'Other than Solar RPO' under 'Other RPO' category in a particular year can be met with either the excess energy consumed from Wind Power Plants, commissioned after 31st March 2022 beyond 'Wind RPO' for that year or with excess energy consumed from eligible HPPs (including PSPs and SHPs), commissioned after 8th March 2019 beyond 'HPO' for that year or with excess energy consumed from solar plants beyond 'Solar PRO' for that year or partly from all above three category..
Provided further that any shortfall in achievement of 'Wind RPO' in a particular year can be met with excess energy consumed from Hydro Power Plants, which is in excess of 'HPO' for that year and vice versa.
(2) For the purpose of this RPO framework, for every obligated entity, own consumption would mean gross energy consumed or purchased by the obligated entity from all sources for its own use or for the purpose of supply to its consumers within its area of supply, excluding any inter-se sale of electricity amongst the Licensees or outside consumers.
(3) Distribution licensee shall be eligible to utilise the gross Solar energy generated from the GRPV/GSPV of non-obligated entities for meeting its 'Solar RPO' compliance based on the gross energy generated meter reading of such GRPV/GSPV.
(4) The following percentage of total energy consumed shall be solar/wind energy alongwith/through storage.
| Financial Year | Storage (on Energy basis) |
|---|---|
| 2023-24 | 1.0% |
| 2024-25 | 1.5% |
| 2025-26 | 2.0% |
| 2026-27 | 2.5% |
| 2027-28 | 3.0% |
| 2028-29 | 3.5% |
| 2029-30 | 4.0% |
Provided that the option of seeking project specific tariff shall not be available to the following:
Provided further that if generating company does not give its option to the distribution licensee within above stipulated time, generic tariff shall be applicable based on the date of commissioning of the project or commissioning of the first unit, in case of multiple units.
(3) Project Specific Tariff, on case to case basis, shall be determined by the Commission in the following cases:
(b) Other hybrid projects include renewable-renewable or renewable-conventional sources, for which renewable technology is approved by MNRE;
(c) Projects having old plant and machinery or equipment;
(d) The RE generating company for meeting the expenditure on Renovation, Modernisation and Up-gradation (RMU) for the purpose of extension of life beyond the useful life of its RE based power plant shall make an application before the Commission for in-principle approval of the proposal alongwith a DPR giving complete scope, cost-benefit analysis, estimated life extension from a reference date, financial package, phasing of expenditure, schedule of completion and other details as required by the Commission and the Commission while fixing their tariffs, shall be guided by the tariff norms specified in the Regulations based on actual capital cost subsequent to the completion of the RMU activities and such other factors considered relevant by the Commission;
(e) Any other new renewable energy technologies approved by MNRE.
Provided that the Commission while determining the Project Specific Tariff shall be guided by the provisions of Chapter 4 & 5 of these Regulations for technologies specified therein.
Provided that the benchmark capital cost of Solar PV, Canal Bank & Canal Top Solar PV, Solar Thermal, Municipal Solid Waste based power projects, Refuse Derived Fuel based power projects and Grid interactive Roof Top and Small Solar PV projects may be reviewed annually by the Commission.
Provided further that the tariff determined as per these Regulations for the RE projects commissioned during the Control Period, shall continue to be applicable for the entire Tariff Period.
(1) The Tariff Period for Renewable Energy power projects shall be equal to Useful life of the Project as specified in Regulation 3(1)(lxiii) of these Regulations.
(2) Tariff period under these Regulations shall be considered from the date of commercial operation or commissioning of the renewable energy plant.
(3) The PPA shall be required to be executed with distribution licensee for the entire Tariff Period.
Provided that for Project Specific Tariff determination, the RE Based Generating Stations and Co-generating Stations shall submit the DPR and the break-up of Capital Cost items along with its petition.
Provided that the RE Based Generating Stations and Co-generating Stations shall be required to make a fresh application for determination of final tariff based on actual capital expenditure incurred up to the date of commercial operation or commissioning of the generating station within 18 months from the actual CoD.
(3) A petition for determination of project specific tariff shall be accompanied by such fee as specified in the UERC (Fee and Fines) Regulations, 2002, as amended from time to time, and shall be accompanied by:
(c) A Statement of all applicable terms and conditions and expected expenditure for the period for which tariff is to be determined;
(4) The proceedings for determination of tariff shall be in accordance with the UERC (Conduct of Business Regulations), 2014.
Provided that for renewable energy technologies having fuel cost component, like biomass/biogas/biomass gasifier power projects, Refuse derived fuel and non-fossil fuel based cogeneration, tariff with two components, namely fixed cost component and fuel cost component, shall be determined.
(2) The Tariff shall consist of the following fixed cost components:
(a) Return on equity;
(b) Interest on loan capital;
(c) Depreciation;
(d) Interest on working capital;
(e) Operation and maintenance expenses;
(3) The generic tariff is being determined separately for each kind of renewable source and for each type of renewable technology for which norms have been specified in these Regulations.
(4) The generic tariff is based on normative parameters as per the norms specified in these Regulations for each type of source and the year of commissioning of the plant. Tariff in respect of a RE Based Generating Stations and Co-generating Stations under these Regulations shall be applicable for the whole generating station.
Provided that the generic tariff for supply of electricity from the plant, having more than one unit commissioned during currency of different control period, shall be based on weighted average of the tariffs specified under different Regulations for the total capacity of the plant.
Provided that for renewable energy technologies having tariff (in Rs./kWh) with two components, for fixed cost component tariff may be determined on levelised basis considering the year of commissioning of the project while the fuel cost component shall be specified on year of operation basis.
Provided that where project specific tariff is being determined the revenue generated from infirm power shall be used to reduce the capital cost of the project after giving credit for cost of fuel consumed, wherever applicable;
Provided that any additional expenditure of capital nature which becomes necessary for restoration works only on account of damages caused by natural calamities (but not due to flooding of power house attributable to the negligence of the generating company), after prudence check by the Commission, shall be allowed as additional capitalisation after duly adjusting the proceeds from any insurance scheme for all the generating stations covered under these Regulations. For additional capital expenditure admitted, as above, appropriate adjustment in tariff shall be allowed for balance life of that project based on the norms given in Chapters 4 & 5 of the Regulations;
Provided that additional capitalisation on this account would only be allowed if appropriate and adequate insurance cover was available for the generating station at the time of occurrence of natural calamities referred to above. The generating company shall intimate the Commission and Distribution Licensee within seven days from the occurrence of any such force majeure event resulting into shut down of plant. The Commission may in such case direct the distribution licensee and State nodal agency to visit the damaged plant and assess the nature & type of damages and restoration works required in coordination with the generator/developer.
is connected).
Provided that if the delay is not attributable to the generating company and is due to uncontrollable factors, such expenditures may be allowed after due prudence check;
Provided further that where the delay is attributable to an agency or contractor or supplier engaged by the generating company, the liquidated damages recovered from such agency or contractor or supplier shall be kept in view while computing the capital cost.
(c) In case individual generating company opts to construct, at its own cost, the evacuation infrastructure from point of inter-connection to the nearest sub-station of transmission or distribution licensee to which the generating station is connected, it shall be allowed a normative levelised tariff of 7 paise/unit over and above the generic tariff determined at the point of inter-connection. However, in case of a solar generating company a normative levelised tariff of 14 paise/unit over and above the generic tariff determined at the point of inter-connection shall be allowed. The said normative tariff for evacuation infrastructure has been arrived at considering the cost of line and equipments specified under UERC (The Electricity Supply code, Release of New Connections and Related matters) Regulations, 2020 as per normative cost given below:
| (i) Upto 3MW, 11 kV S/C | - Rs. 8.00 lakh/km |
| (ii) Above 3MW and upto 13 MW, 33 kV S/C | - Rs. 12.50 lakh/km |
| (iii) Above 13 MW and upto 25 MW, 33 kV $2 \times S/C$ or DC | - Rs. 25.00 lakh/km |
Provided that in case more than one generating stations construct, at its own cost, a common evacuation infrastructure including pooling switching station, in accordance with Regulation 43 of these Regulations, for evacuation of power of their generation, then the above normative levelised tariff shall be apportioned among all such generating stations on the basis of their installed capacity.
Provided further that where the transmission line from inter-connection point to nearest sub-station is partly constructed by distribution licensee and partly by generating company, normative levelised tariff of 7 paisa/kWh or 14 paisa/kWh, as the case may be, shall be as per length of the line constructed by the generating company in proportion to the overall length of the line i.e. from inter-connection point to sub-station of the distribution/transmission licensee.
Provided that the distribution licensee will be required to exercise the option within one year from the date of commissioning of the generating station(s).
(a) For generic tariff debt-equity ratio shall be 70:30.
(b) For project specific tariff, the following provisions shall apply:
If the equity actually deployed is more than 30% of the capital cost, equity in excess of 30% shall be treated as normative loan:
Provided that where equity actually deployed is less than 30% of the capital cost, the actual equity shall be considered for determination of tariff;
Provided further that the equity invested in foreign currency shall be designated in Indian rupees on the date of each investment;
Provided further that it shall be assumed that the original repayments shall not be affected by this prepayment.
project cost.
Provided that for determination of project specific tariff, sale of electricity will be calculated based on the CUF envisaged in the approved DPR or the normative CUF specified for the relevant technology under Chapter 5, whichever is higher.
Provided that for determination of project specific tariff, CUF will be taken as the CUF envisaged in the approved DPR or the normative CUF specified for the relevant technology under Chapter 5, whichever is higher.
For payment of bills of the generating company through Letter of Credit or any other mode
within the specified period below, a rebate shall be allowed to the distribution licensee as follows:
| No. of days from the date of presentation of bill within which payment is credited in generating company account | Applicable Rebate (%) |
|---|---|
| Within 7 days | 1.65 |
| From 8 th day to 15 th day | 1.50 |
| From 16 th day to 23 rd day | 1.35 |
| From 24 th day to 30 th day | 1.25 |
Explanation: The number of days shall be counted consecutively without considering any holiday. However, in case the last day is official holiday, last day for the purpose of rebate shall be construed as the immediate succeeding working day.
In case the payment of bills is delayed beyond a period of 45 days from the date of billing, a late payment surcharge at the rate of 1.25% per month or part thereof shall be levied by the generating company.
Provided that the existing PPAs should be read as amended to be in conformity with the above sub-regulation 23 and 24 of these Regulations.
The Commission shall take into consideration any incentive or subsidy offered by the Central or State Government, including accelerated depreciation benefit if availed by the generating company, for the renewable energy power plants while determining the tariff under these Regulations.
Provided that only 75% of the capital subsidy for the financial year of commissioning as per applicable scheme of MNRE shall be considered for tariff determination.
Provided that the following principles shall be considered for ascertaining income tax benefit on account of accelerated depreciation, if availed, for the purpose of tariff determination:
Assessment of benefit shall be based on capital cost admitted, accelerated depreciation rate as per relevant provisions under Income Tax Act and corporate income tax rate.
Capitalisation of RE projects during second half of the fiscal year. Per unit benefit shall be derived on levelised basis at discount factor equivalent to Post Tax weighted average cost of capital.
(c) It shall be assumed that the generating company shall avail the benefit of accelerated depreciation and the onus of establishing, to the satisfaction of distribution licensee, that it is not entitled for this benefit shall be that of such generating company. The auditor's certificate in this regard shall be considered sufficient for this purpose.
Provided further that where Central Government or the State Government has notified any Generation Based Incentive Scheme for a particular kind of renewable technology such technology based generating stations shall be assumed to have availed the benefit of such a scheme and their tariffs shall automatically be treated as reduced by the amount of GBI per unit.
Tariff determined under these regulations shall be including direct taxes on income but exclusive of other taxes and duties as may be levied by the appropriate Government.
Provided that the taxes, duties and cess levied by the appropriate Government other than direct taxes shall be allowed as pass through on actual incurred basis.
(a) Till the actual CUF is less than or equal to annual CUF of 40%, tariffs would be payable at the levelised generic rates specified in the Regulations arrived at based on the normative CUF of 40%.
(b) For generation beyond annual CUF of 40%, following will apply:
(i) For generation beyond annual CUF of 40% but upto annual CUF of 45%, tariff shall be Rs. 1.50/kWh.
(ii) For generation beyond annual CUF of 45%, incentive shall be equal to the levelised generic rates specified in the Regulations at CUF of 45% reduced by Rs. 0.75 per kWh. Such reduction of Rs. 0.75/kWh shall be made from the subsequent monthly bills only till the actual annual CUF reaches 55%.
(iii) For generation beyond actual annual CUF of 55%, incentive shall be equal to the levelised generic rates specified in the Regulations at CUF of 45%.
B. For generators opting for project specific tariffs, the tariff for generation beyond the applicable CUF (i.e. the CUF envisaged in the approved DPR or the normative CUF
specified for the relevant technology under Chapter 5, whichever is higher), shall be allowed to be recovered at the project specific tariff approved by the Commission.
The annual CUF shall be calculated in accordance with the principles specified in Regulation 3(1)(viii) of the Regulations.
Since RE Sources are dependent on vagaries of nature and are of small capacities, the principle of merit order dispatch/purchase shall not be applicable to supply of power from such sources to the distribution licensee or local rural grids within the State, i.e. they shall be treated as must run stations.
| Project Size | Capital Cost (Rs. Lakh/MW) |
O&M Expenses for year of commissioning (Rs. Lakh/MW) |
Capacity Utilization Factor* (%) |
Auxiliary Consumption (%) |
|---|---|---|---|---|
| Upto 5 MW | 1150 | 59.43 | Generic Tariff- 40% Project Specific- 45% |
1% |
| > 5 MW & upto 15 MW | 1125 | 53.33 | ||
| > 15 MW & upto 25 MW | 1100 | 47.54 |
* for the recovery of Annual Fixed Charges.
NOTE: For the purpose of this Regulation, normative CUF is based on Energy Sent Out at interconnection point and for tariff purposes energy net of free power to the home State, if any, committed by the developer shall be factored. For generic tariff determination, home State share has been taken as 18% from 16th year onwards.
| Biomass Rankine Cycle Projects | Capital Cost for the year of commissioning of project (Rs. Lakh/MW) |
|---|---|
| Projects [other than rice straw and julfiora (plantation) based projects] with water cooled condenser | 559 |
| Projects [other than rice straw and julfiora (plantation) based projects] with air cooled condenser | 600 |
| For rice straw and julfiora (plantation) based projects with water cooled condenser | 611 |
| For rice straw and julfiora (plantation) based projects with air cooled condenser | 652 |
Normative O&M expenses for the first year of the Control period shall be Rs. 55.85 Lakh/MW. The Normative O&M expenses allowed for the year of commissioning shall be escalated at the rate of 5.72% per annum for subsequent years.
The Station Heat Rate of biomass power projects shall be
The normative auxiliary consumption shall be as follows:
Provided that for the biomass power projects commissioned on or before 31.03.2023, the use of fossil fuels to the extent of 15% in terms of calorific value on annual basis shall be allowed for the tariff period from the date of commissioning.
defaulting biomass power project shall continue to sell power to the distribution licensee and the rate during the financial year in which default occurred shall be the rate lower by Rs. 1.50/kWh of the applicable variable tariff specified by the Commission.
The Calorific Value of the biomass fuel used for the purpose of determination of tariff shall be at 3100 kCal/kg.
Biomass Fuel Price for the first year of the Control Period, i.e FY 2023-24 shall be taken as Rs. 3005/MT, unless specifically reviewed by the Commission. For each subsequent year of the Tariff Period, the normative escalation factor of 5% on previous year's fuel cost shall be applicable to determine the fuel cost for different years of the Tariff Period.
| Capital Cost | O&M Expenses for year of commissioning | Station Heat Rate | Calorific value of fuel | Auxiliary Consumption | Plant Load Factor |
|---|---|---|---|---|---|
| (Rs. Lakh/ MW) | (Rs. Lakh/MW) | (kCal / kWh) | (kCal/kg) | ||
| 492 | 29.52 | 3600 | 2250 | 8.5% | 45% |
Power Projects commissioned or to be commissioned on or after 01.04.2023 shall be as follows:
| Type of Project | Capital Cost (Rs. Lakh/MW) |
O&M Expenses for year of commissioning (Rs. Lakh/MW) |
Specific Fuel Consumption Kg/kWh |
Auxiliary Consumption |
Capacity Utilization Factor |
|---|---|---|---|---|---|
| Pine leaves based Biomass Gasifier projects |
625.00 | 132.00 | 1.50 | 10% | 85% |
| Other Biomass Gasifier Projects |
592 | 73.76 | 1.25 |
| Capital Cost (Rs. Lakh/MW) |
O&M Expenses for year of commissioning (Rs. Lakh/MW) |
Specific Fuel Consumption (kg/kWh) |
Auxiliary Consumption |
Capacity Utilization Factor |
|---|---|---|---|---|
| 1185 | 71.00 | 3.00 | 12% | 90% |
Norms for Solar Photovoltaic (PV) power project under these Regulations shall be applicable for grid connected PV systems that directly convert solar energy into electricity and exclusively installed for the purpose of sale of entire electricity to distribution licensee and are based on the technologies such as crystalline silicon or thin film etc. as may be approved by MNRE. The technology specific parameters for determination of generic tariffs for Solar PV Power Projects commissioned or to be commissioned on or after 01.04.2023 shall be as follows:
| Capital Cost (Rs. Lakh/MW) |
O&M Expenses for year of commissioning (Rs. Lakh/MW) |
Capacity Utilization Factor |
|---|---|---|
| 345.11 | 16.24 | 19 % |
Norms for canal bank Solar PV Power Plants and canal top Solar PV Power Plants under these Regulations shall be applicable for grid connected PV systems that directly convert solar energy into electricity and are based on the technology specific parameters for determination of generic tariffs for such power projects commissioned or to be commissioned on or after 01.04.2023 shall be as follows:
| Type Solar PV Plant | Capital Cost (Rs. Lakh/MW) |
O&M Expenses for year of commissioning (Rs. Lakh/MW) |
Capacity utilization Factor |
|---|---|---|---|
| Canal Bank Solar PV Plant |
400.00 | 16.24 | 19% |
| Canal Top Solar PV Plant | 425.00 |
Norms for Solar thermal power under these Regulations shall be applicable for Concentrated solar power (CSP) technologies viz. line focusing or point focusing, as may be approved by MNRE, and uses direct sunlight, concentrating it several times to reach higher energy densities and thus higher temperatures whereby the heat generated is used to operate a conventional power cycle to generate electricity. The technology specific parameters for determination of generic tariffs for Solar Thermal Power Projects commissioned or to be commissioned on or after
01.04.2023 shall be as below:
| Capital Cost (Rs. Lakh/MW) |
O&M Expenses for year of commissioning (Rs. Lakh/MW) |
Capacity Utilization Factor |
Auxiliary Consumption |
|---|---|---|---|
| 1200 | 22.14 | 23% | 10% |
| Project Size | Capital Cost (Rs. /kW) |
O&M Expenses for year of commissioning (Rs./kW) |
Capacity Utilization Factor |
|---|---|---|---|
| Upto 10 kW | 47691 | 2149 | 19 % |
| >10 kW & upto 100 kW | 43753 | 1912 | |
| >100 kW & upto 500 kW | 41276 | 1735 | |
| >500 kW and upto 1 MW | 40074 | 1624 |
Provided that the maximum GRPV/GSPV installed capacity at any Eligible Consumer's premises shall be upto a maximum of 100% of consumer's sanctioned load/contract demand;
Provided that in case of Domestic Consumer, such installed capacity of GRPV/GSPV shall be irrespective of consumer's sanctioned load/contract demand;
Provided, the maximum installed capacity of GRPV/GSPV at the premises of eligible consumer shall not be more than 1 MW.
Provided that such eligible consumer shall be exempted from payment of monthly minimum charges/monthly minimum consumption guarantee charges, if any, equivalent to the capacity of GRPV/GSPV installed at the premises;
Provided further that no open access charges including surcharges shall be leviable on such eligible consumers for the captive use of power.
| Capital Cost | O&M Expenses | Annual Mean Wind Power Density | Capacity Utilization |
|---|---|---|---|
| (Rs. Lakh/MW) | (Rs. Lakh/MW) | (W/m 2 ) | Factor |
| 515 | 12.55 | Upto 220 | 22% |
| 221-275 | 24% | ||
| 276-330 | 28% | ||
| 331-440 | 33% | ||
| >440 | 35% |
would be normally extended 10 km from the mast-point to all directions for uniform terrain and limited to appropriate distance in complex terrain with regard to complexity of the site. Based on such validation by NIWE, State Nodal Agency should certify zoning of the proposed wind farm complex.
| Project | Capital Cost | O&M Expenses for year of commissioning | Plant Load Factor | Auxiliary Consumption | Station Heat Rate | Calorific value |
|---|---|---|---|---|---|---|
| (Rs. Lakh/MW) | (Rs Lakh/MW) | kcal/kWh | kcal/kg | |||
| MSW | 1500 | 6% of the project cost for 1 st year and shall be escalated @ 5.72% per annum | 65% during stabilization & first year. 75% from second year onwards. |
15% | 4200 | - |
| RDF | 900 | 6% of the project cost for 1 st year and shall be escalated @ 5.72% per annum | 65% during stabilization & first year. 80% from second year onwards. |
15% | 4200 | 2500 |
The generic tariffs for the above-mentioned technologies are given in Annexure-I.
Provided that no Transmission and Wheeling Charges are payable for sale of electricity to distribution licensee or to local rural grid within the State;
Provided further that where a generating company proposes to supply electricity outside the State, such generating company, in addition to transmission/ wheeling charges specified above, shall have to bear the transmission/ wheeling charges determined by the Commission on case to case basis for the dedicated lines and substation of the transmission/ distribution licensee used only for evacuation of such power;
Provided further that where more than one generating company proposes to supply electricity outside the State over common dedicated transmission/ distribution system of transmission/ distribution licensee for evacuation of their power, such generating companies, in addition to transmission/ wheeling charges specified above, shall have to bear the full transmission/ wheeling charges determined by the Commission on case to case basis for such dedicated lines and substation of the transmission/ distribution licensee used only for evacuation of such power on pro-rata basis of installed capacity.
Provided further that no losses shall be adjusted in kind for sale of electricity to distribution licensees within the State or to local rural grid.
Provided further that where more than one RE based Generating Stations having cumulative installed capacity less than 25 MW are located in a cluster/ area and for the purpose of evacuation, these generating stations agree to pool their generation at a common pooling switching station to be constructed by them at their own cost and further beyond such pooling switching station, the Distribution Licensee shall provide connectivity at its nearest sub-station. They may further mutually agree to provide connectivity at appropriate
voltage level subject to technical feasibility and technical standards for construction of electricity lines and connectivity with the grid as may be specified by CEA. However, such generating stations shall be eligible for additional levelised tariff as specified under Regulation 16(1)(c) of these Regulations, only if they construct the line from pooling sub-station to the nearest sub-station at their own costs.
Provided that any RE based Generating Station having capacity upto 25 MW is willing to connect and evacuate power through 132 kV & above transmission system, it may do so subject to consent of the Transmission Licensee.
Provided further that where more than one RE based Generating Stations having cumulative installed capacity more than 25 MW are located in a cluster/area and for the purpose of evacuation, these generating stations agree to pool their generation at a common pooling switching station to be constructed by them at their own cost and further beyond such pooling switching station, the Transmission Licensee shall provide connectivity at its nearest sub-station. They may further mutually agree to provide connectivity at appropriate voltage level subject to technical feasibility and technical standards for construction of electricity lines and connectivity with the grid as may be specified by CEA. However, such generating stations shall be eligible for additional levelised tariff as specified under Regulation 16(1)(c) of these Regulations, only if they construct the line from pooling sub-station to the nearest sub-station at their own costs.
Provided that such Generating Stations may also get the work of construction of the power evacuation system carried out by State transmission/distribution licensee;
Provided further that the land for extending the bay shall be provided by the owner of the transmission or distribution sub-station, as the case may be, free of cost.
For sale to person other than the Distribution Licensees or to Local Rural Grid principles of optimum scheduling and dispatch as per IEGC and State Grid Code scheme shall apply and for this purpose RE based Generating Stations shall be required to pay such fee to the SLDC as specified under UERC (Terms and Conditions of Intra-State Open Access) Regulations, 2015.
the Net exchange.
Provided that Check Meter and related equipments can be procured by such plant owner. However, the cost of Check Meter shall be refunded by the licensee to such plant owner. The cost of the check meter to be refunded would be, lower of the following:
Generating Station shall provide ABT compatible Special Energy Meters at the point of interconnection complying with the Regulation on installation of meters specified by CEA.
The State Load Dispatch Centre shall carry out scheduling and accounting of energy sent out by the generators and the same shall be communicated to the utilities interacting with the grid as per the scheme framed by SLDC in pursuance of the provisions of IEGC, State Grid Code and Open Access Regulations. Billing for open access transactions shall be done in accordance with the Open Access Regulations.
Provided that in case of sale to the distribution licensee of the area, the power purchase agreement may provide for joint meter reading and in such cases, energy accounting and billing shall be done by the generating station in coordination with the concerned distribution licensee.
Provided that in case electricity generated from the plant is being exclusively sold to the State Distribution Licensee, the electricity (in kWh) procured by the Generating Station from the State Distribution Licensee to meet its requirement of his own use or for startup power, will be adjusted from the electricity sold to the Distribution Licensee on month to month basis. The Distribution Licensee shall make the payment for net energy sold to it by the Generating Company, i.e. difference of the total energy injected into the grid and energy drawn from the grid by the Generating Company.
In case the energy supplied by the distribution licensee is more than the energy injected by the generating company, the net energy (in kWh) thereof shall be charged as per the tariff determined by the Commission for temporary supply under appropriate "Rate Schedule of tariff" for Industrial Consumers considering maximum demand during the month as the contracted demand for that month. The Fixed/Demand charges for that month shall be payable for the number of days during which such supply is drawn.
Provided further that in case electricity generated from the plant is sold to third party other than the Distribution Licensee, then such purchase of electricity by the generating company from the distribution licensee, shall be charged as per the tariff determined by the Commission for temporary supply under appropriate "Rate Schedule of tariff" for Industrial Consumers considering maximum demand during the month as the contracted demand for that month. The Fixed/Demand charges for that month shall be payable for the number of days during which such supply is drawn.
(1) The Generating Stations shall be allowed to bank power within a period of one calendar month, for the purpose of withdrawal of the banked power in the event of emergency or shut down or maintenance of the plant, subject to following conditions:
(h) The banked power remaining unutilized on the expiry of the financial year would be treated as sale and the financial settlement shall be made at the tariff determined by the Commission in its Tariff Order for the year during which the power was banked or at the generic tariff specified by the Commission in case of a Non-fossil fuel based Co-generating Stations. No banking charges shall be deducted from such unutilized banked energy.
(i) Banking charges shall be adjusted in kind @ 8% of the energy banked.
(j) In case of a Non-fossil fuel based Co-generating Stations, which is not a captive generating plant, the facility of banking shall apply only if it has a PPA with the distribution licensee in the State.
(k) The energy banked during non-peak hours (TOD slots) shall be permitted to be drawn during non-peak hours (TOD slots) by only paying the banking charges and from non-peak hours (TOD slot) to peak hours (TOD slot) by paying charges in kind @ equivalent to % of difference between the Peak hours energy charge rate and Normal hours energy charge rate (as defined in the respective Tariff Orders issued by the Commission) of the energy banked in addition to the above banking charges specified under these regulations.
(Applicable only in case of Small Hydro Generating Plants & Solar PV Plants & Solar Thermal Projects excluding Solar power plants installed under net metering arrangement)
Provided that the following shall not count towards Deemed Generation:
(i) The loss of generation at the Station on account of aforesaid factor(s) but attributed to the Force Majeure event(s);
(ii) The loss of generation at the Station due to the interruptions/outages attributed to the aforesaid factor(s) during the period in which the total duration of such outages/interruptions, other than that excluded under above, is within the limit of:
48 hours in a month in case of small hydro project, and
12 hours in a month in case of solar PV and Solar Thermal Project.
Provided that for working out the ceiling of 12 Hrs. in a month for Solar PV and Solar Thermal Projects, the interruptions/outages occurring during 18.00 hours in the evening to 6.00 hours in the morning shall not be counted;
The distribution licensee shall be required to maintain the voltages at the point of interconnection with the project within the limits stipulated hereunder, with reference to declared voltage:
Any loss in generation due to variations in the voltage beyond the limits specified above shall be reckoned as deemed generation provided such loss of generation results in reduction of more than 25% of capacity output.
(iii) The generation loss towards the Deemed Generation (in MWh) in accordance with sub-Regulation (ii) above, if any, during the month shall be considered as the summation of the product of number of hours the variations in voltage beyond the specified limit existed and the Generation lost (in MW) due to the variation in the voltage beyond the specified limit. The Generation lost (in MW) would be the difference between the following:
Provided that if such variation in voltage continues for the entire month, generation (in MW) before such variation in voltage occurrence would be treated as the "Actual Generation".
(b) The generation achieved during the period when variation in voltages took place.
(3) The distribution licensee shall pay for the saleable deemed generation, on annual basis, for Small Hydro projects and Solar PV and Solar Thermal projects worked out on the basis of the deemed generation on the above lines, at the generic/project specific tariffs as applicable in accordance with the applicable RE Regulations. The settlement of payment towards deemed generation charges shall be carried out within 3 months of the completion of the financial year.
Provided that any charges paid by the distribution licensee towards deemed generation shall not be allowed as an expense to be pass through in tariffs. The distribution licensee will have to bear such charges;
Provided further that the deemed generation conditions stipulated above shall be applicable only on those Small Hydro projects and Solar PV and Solar Thermal projects who have signed a long term PPA with the distribution licensee;
Provided also that the deemed generation conditions shall be applicable only on the Small Hydro projects and Solar PV and Solar Thermal projects where the evacuation line is connected to 11 kV or higher voltage Grid Sub-station.
Commission to make such orders as may be necessary to meet the ends of justice.
If any difficulty arises in giving effect to these regulations, the Commission may, of its own motion or otherwise, by an order and after giving a reasonable opportunity to those likely to be affected by such order, make such provisions, not inconsistent with these regulations, as may appear to be necessary for removing the difficulty.
The Commission, for reasons to be recorded in writing, may vary any of the provisions of these regulations on its own motion or on an application made before it by an interested person.
The Commission may, at any time add, vary, alter, modify or amend any provision of these Regulations.
| Particulars | Upto 5 MW | Above 5 MW & upto 15 MW | Above 15 MW & upto 25 MW |
|---|---|---|---|
| Gross Tariff (CUF@ 40%) | 7.96 | 7.54 | 7.14 |
| Gross Tariff (CUF @ 45%) | 7.07 | 6.70 | 6.35 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 6.67 |
| Less: Acc. Dep. Benefit | 0.24 |
| Net Tariff | 6.43 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 4.05 |
| Less: Acc. Dep. Benefit | 0.13 |
| Net Tariff | 3.91 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.54 | 4.77 | 5.01 | 5.26 | 5.52 | 5.79 | 6.08 | 6.39 | 6.71 | 7.04 | 7.40 | 7.76 | 8.15 | 8.56 | 8.99 | 9.44 | 9.91 | 10.41 | 10.93 | 11.47 | 12.05 | 12.65 | 13.28 | 13.94 | 14.64 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 3.17 |
| Less: Acc. Dep. Benefit | 0.10 |
| Net Tariff | 3.07 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.36 | 4.58 | 4.81 | 5.05 | 5.30 | 5.56 | 5.84 | 6.13 | 6.44 | 6.76 | 7.10 | 7.46 | 7.83 | 8.22 | 8.63 | 9.06 | 9.52 | 9.99 | 10.49 | 11.02 | 11.57 | 12.14 | 12.75 | 13.39 | 14.05 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 4.72 |
| Less: Acc. Dep. Benefit | 0.08 |
| Net Tariff | 4.63 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.17 | 4.38 | 4.60 | 4.83 | 5.07 | 5.33 | 5.59 | 5.87 | 6.17 | 6.47 | 6.80 | 7.14 | 7.50 | 7.87 | 8.26 | 8.68 | 9.11 | 9.57 | 10.04 | 10.55 | 11.07 | 11.63 | 12.21 | 12.82 | 13.45 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 3.06 |
| Less: Acc. Dep. Benefit | 0.08 |
| Net Tariff | 2.98 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.17 | 4.38 | 4.60 | 4.83 | 5.07 | 5.33 | 5.59 | 5.87 | 6.17 | 6.47 | 6.80 | 7.14 | 7.50 | 7.87 | 8.26 | 8.68 | 9.11 | 9.57 | 10.04 | 10.55 | 11.07 | 11.63 | 12.21 | 12.82 | 13.46 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 4.22 |
| Less: Acc. Dep. Benefit | 0.15 |
| Net Tariff | 4.07 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 5.77 | 6.06 | 6.36 | 6.68 | 7.02 | 7.37 | 7.73 | 8.12 | 8.53 | 8.95 | 9.40 | 9.87 | 10.36 | 10.88 | 11.43 | 12.00 | 12.60 | 13.23 | 13.89 | 14.58 | 15.31 | 16.08 | 16.89 | 17.73 | 18.61 |
| Particular | Canal bank Solar PV Power Plants |
Canal top Solar PV Power Plants |
|---|---|---|
| (Rs./kWh) | ||
| Gross Tariff | 5.13 | 5.36 |
| Less: Acc. Dep. Benefit | 0.21 | 0.22 |
| Net Tariff | 4.92 | 5.13 |
| Particular | Solar PV Projects | Solar Thermal Projects |
|---|---|---|
| (Rs./kWh) | ||
| Gross Tariff | 4.64 | 14.34 |
| Less: Acc. Dep. Benefit | 0.18 | 0.63 |
| Net Tariff | 4.46 | 13.70 |
| Particular | Upto 10 kW Approved |
Above 10 kW to 100 kW Approved |
Above 100 kW to 500 kW Approved |
Above 500 kW below 1 MW Approved |
|---|---|---|---|---|
| Levelled Tariff considering nil Subsidy | ||||
| Gross Tariff | 6.29 | 5.71 | 5.33 | 5.11 |
| Less: Acc Dep Benefit | 0.25 | 0.23 | 0.22 | 0.21 |
| Net Tariff | 6.04 | 5.49 | 5.11 | 4.90 |
| Levelled Tariff considering 20% Subsidy | ||||
| Gross Tariff | 5.77 | 5.24 | 4.88 | 4.68 |
| Less: Acc Dep Benefit | 0.22 | 0.20 | 0.19 | 0.19 |
| Net Tariff | 5.55 | 5.03 | 4.69 | 4.49 |
| Levelled Tariff considering 30% Subsidy | ||||
| Gross Tariff | 5.51 | 5.00 | 4.65 | 4.46 |
| Less: Acc Dep Benefit | 0.21 | 0.19 | 0.18 | 0.17 |
| Net Tariff | 5.30 | 4.81 | 4.47 | 4.29 |
| Levelled Tariff considering 40% Subsidy | ||||
| Gross Tariff | 5.25 | 4.76 | 4.43 | 4.24 |
| Less: Acc Dep Benefit | 0.19 | 0.18 | 0.17 | 0.16 |
| Net Tariff | 5.05 | 4.58 | 4.26 | 4.08 |
| Levelled Tariff considering 70% Subsidy | ||||
| Gross Tariff | 4.47 | 4.05 | 3.76 | 3.59 |
| Less: Acc Dep Benefit | 0.14 | 0.13 | 0.13 | 0.12 |
| Net Tariff | 4.33 | 3.92 | 3.63 | 3.47 |
| Levelled Tariff considering 80% Subsidy | ||||
| Gross Tariff | 4.23 | 3.83 | 3.55 | 3.39 |
| Less: Acc Dep Benefit | 0.13 | 0.12 | 0.11 | 0.11 |
| Net Tariff | 4.11 | 3.71 | 3.44 | 3.29 |
| Levelled Tariff considering 90% Subsidy | ||||
| Gross Tariff | 4.04 | 3.65 | 3.38 | 3.23 |
| Less: Acc Dep Benefit | 0.10 | 0.10 | 0.09 | 0.09 |
| Net Tariff | 3.93 | 3.56 | 3.29 | 3.14 |
| Particular | Rate of Fixed Charges (Rs./kWh) | ||||
|---|---|---|---|---|---|
| Zone 1 | Zone 2 | Zone 3 | Zone 4 | Zone 5 | |
| Gross Tariff | 5.20 | 4.47 | 4.09 | 3.47 | 3.27 |
| Less: Acc. Dep. Benefit | 0.36 | 0.33 | 0.28 | 0.24 | 0.22 |
| Net Tariff | 4.85 | 4.14 | 3.81 | 3.23 | 3.05 |
A. Projects [other than rice straw and julfiora (plantation) based projects] with water cooled condenser based on Travelling grate boilers.
| Particular | Rate of Fixed Charges(Rs./kWh) |
|---|---|
| Gross Tariff | 2.97 |
| Less: Acc. Dep. Benefit | 0.08 |
| Net Tariff | 2.90 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023- 24 (Rs./kWh) |
4.44 | 4.67 | 4.90 | 5.14 | 5.40 | 5.67 | 5.95 | 6.25 | 6.56 | 6.89 | 7.24 | 7.60 | 7.98 | 8.38 | 8.80 | 9.24 | 9.70 | 10.18 | 10.69 | 11.23 | 11.79 | 12.38 | 13.00 | 13.65 | 14.33 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 2.97 |
| Less: Acc. Dep. Benefit | 0.08 |
| Net Tariff | 2.89 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.44 | 4.67 | 4.90 | 5.14 | 5.40 | 5.67 | 5.95 | 6.25 | 6.56 | 6.89 | 7.24 | 7.60 | 7.98 | 8.38 | 8.80 | 9.24 | 9.70 | 10.18 | 10.69 | 11.23 | 11.79 | 12.38 | 13.00 | 13.65 | 14.33 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 3.14 |
| Less: Acc. Dep. Benefit | 0.09 |
| Net Tariff | 3.06 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.03 | 4.86 | 5.10 | 5.36 | 5.62 | 5.90 | 6.20 | 6.51 | 6.84 | 7.18 | 7.54 | 7.91 | 8.31 | 8.72 | 9.16 | 9.62 | 10.10 | 10.60 | 11.13 | 11.69 | 12.28 | 12.89 | 13.53 | 14.21 | 14.92 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 3.14 |
| Less: Acc. Dep. Benefit | 0.09 |
| Net Tariff | 3.05 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.54 | 4.77 | 5.01 | 5.26 | 5.52 | 5.80 | 6.09 | 6.39 | 6.71 | 7.05 | 7.40 | 7.77 | 8.16 | 8.57 | 9.00 | 9.45 | 9.92 | 10.41 | 10.94 | 11.48 | 12.06 | 12.66 | 13.29 | 13.96 | 14.65 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 3.10 |
| Less: Acc. Dep. Benefit | 0.08 |
| Net Tariff | 3.01 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.52 | 4.75 | 4.99 | 5.24 | 5.50 | 5.77 | 6.06 | 6.37 | 6.68 | 7.02 | 7.37 | 7.74 | 8.12 | 8.53 | 8.96 | 9.40 | 9.87 | 10.37 | 10.89 | 11.43 | 12.00 | 12.60 | 13.23 | 13.89 | 14.59 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 3.09 |
| Less: Acc. Dep. Benefit | 0.08 |
| Net Tariff | 3.01 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.52 | 4.75 | 4.99 | 5.24 | 5.50 | 5.77 | 6.06 | 6.37 | 6.68 | 7.02 | 7.37 | 7.74 | 8.12 | 8.53 | 8.96 | 9.40 | 9.87 | 10.37 | 10.89 | 11.43 | 12.00 | 12.60 | 13.23 | 13.89 | 14.59 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 3.27 |
| Less: Acc. Dep. Benefit | 0.09 |
| Net Tariff | 3.17 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.54 | 4.77 | 5.01 | 5.26 | 5.52 | 5.80 | 6.09 | 6.39 | 6.71 | 7.05 | 7.40 | 7.77 | 8.16 | 8.57 | 9.00 | 9.45 | 9.92 | 10.41 | 10.94 | 11.48 | 12.06 | 12.66 | 13.29 | 13.96 | 14.65 |
| Particular | Rate of Fixed Charges (Rs./kWh) |
|---|---|
| Gross Tariff | 3.26 |
| Less: Acc. Dep. Benefit | 0.09 |
| Net Tariff | 3.17 |
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Variable Charges for 1 st year as FY 2023-24 (Rs./kWh) | 4.54 | 4.77 | 5.01 | 5.26 | 5.52 | 5.80 | 6.09 | 6.39 | 6.71 | 7.05 | 7.40 | 7.77 | 8.16 | 8.57 | 9.00 | 9.45 | 9.92 | 10.41 | 10.94 | 11.48 | 12.06 | 12.66 | 13.29 | 13.96 | 14.65 |
Form-1.1: Form Template for (Wind Power or Small Hydro Project or Solar PV/Thermal)
| Sl. No. | Assumption Head | Sub-Head | Sub-Head(2) | Unit | Values |
|---|---|---|---|---|---|
| 1 | Power Generation | Capacity | Installed Power Generation Capacity Capacity utilization Factor Commercial Operation date Useful Life |
MW % MM/YYYY Years |
|
| 2 | Project Cost | Capital Cost/MW | Normative Capital Cost Capital Cost Capital subsidy, if any Net Capital Cost |
Rs. Lakh/MW Rs. Lakh Rs. Lakh Rs. Lakh |
|
| 3 | Financial Assumptions | Debt: Equity | Tariff Period Debt Equity Total Debt Amount Total Equity Amount |
Years % % Rs. Lakh Rs. Lakh |
|
| Debt Component | Loan Amount Moratorium Period Repayment Period (incl'd Moratorium) Interest Rate |
Rs. Lakh Years Years % |
|||
| Equity Component | Equity Amount Return on Equity for first 10 years Return on equity 11 th Year onwards Discount rate |
Rs. Lakh % p.a. % p.a. % |
|||
| Depreciation | Depreciation Rate for first 12 years Depreciation Rate 13 years onwards Generation based incentives, if any |
% % RS L.p.a. |
|||
| Incentives | Period for GRI | years | |||
| 4 | Operation & Maintenance | Normative O&M Expenses O&M Expenses per annum Escalation factor for O&M expenses |
Rs. Lakh/MW Rs. Lakh % |
||
| 5 | Working Capital | O&M expenses Maintenance Spare Receivables Interest on working capital |
% of O&M expenses) | Months % Months %p.a. |
Form - 2.1: Form Template for (Biomass Power, municipal solid waste, refuse derived fuel or Non-fossil fuel based Cogen) Parameter Assumptions
| Sl.No. | Assumption Head | Sub-Head | Sub-Head (2) | Unit | Values |
|---|---|---|---|---|---|
| 1 | Power Generation | Capacity | Installed Power Generation Capacity Auxiliary Consumption factor PLF (during stabilization upto 6 months) PLF (during 1 st year after stabilization) PLF (2 nd yr onwards) Commercial Operation Date Useful Life |
MW % % % % mm/yyyy Years |
|
| 2 | Project Cost | Capital Cost/MW | Normative Capital Cost Capital Cost Capital subsidy, if any Net Capital Cost |
Rs. Lakh/MW Rs. Lakh Rs. Lakh Rs. Lakh |
|
| 3 | Financial Assumptions | Debt/Equity | Tariff Period Debt Equity Total Debt Amount Total Equity Amount |
Years % % Rs. Lakh Rs. Lakh |
|
| Debt Component | Loan Amount Moratorium Period Repayment Period (incl'd Moratorium) Interest Rate |
Rs. Lakh Year Year % |
|||
| Equity Component | Equity Amount Return on Equity for first 10 years Return on Equity 11 th year onwards Discount Rate |
Rs. Lakh %p.a. %p.a. % |
|||
| Depreciation | Depreciation Rate for first 12 years Depreciation Rate 13 years onwards Generation Based Incentives, if any Period for GBI |
% % Rs. L p.a. years |
|||
| 4 | Operation & Maintenance | Incentives | |||
| Normative O&M expense O&M expense per annum Escalation factor for O&M expense |
Rs. Lakh/MW Rs. Lakh % |
||||
| 5 | Working Capital | O&M expense Maintenance Spare Receivables Biomass stock Interest on working capital |
(% of O&M expenses) | Months % Months Months % p.a. |
|
| 6 | Fuel related assumptions | Station Heat Rate Fuel types & mix |
During stabilization Post stabilization Biomass fuel type-1 Biomass fuel type-2 Municipal Solid Waste fuel Refuse Derived Fuel Fossil fuel (coal) GCV of Biomass fuel type-1 GCV of Biomass fuel type-2 GCV of fossil fuel (coal) Biomass Price (fuel type-1):yr-1 Biomass Price (fuel type-2):yr-1 Fossil fuel price (coal) : yr-1 Fuel price escalation factor |
Kcal/kWh Kcal/kWh % % % % % tCal/kg tCal/kg tCal/kg Rs./MT Rs./MT Rs./MT % p.a. |
Form 1.2 Form Template for (Biomass Power, municipal solid waste, refuse derived fuel or Non-fossil fuel based Cogen: Determination of Tariff Components)
| Unit Generation | Unit | Year | |||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | ||||||
| Installed Capacity | MW | ||||||||||||||||||||||||||||||||||||||||||||
| Net Generation | MU |
| Unit Generation | Unit | Year | |||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | ||||||
| O&M Expenses | Rs. Lakh | ||||||||||||||||||||||||||||||||||||||||||||
| Depreciation | Rs. Lakh | ||||||||||||||||||||||||||||||||||||||||||||
| Interest on term loan | Rs. Lakh | ||||||||||||||||||||||||||||||||||||||||||||
| Interest on working Capital | Rs. Lakh | ||||||||||||||||||||||||||||||||||||||||||||
| Return on Equity | Rs. Lakh | ||||||||||||||||||||||||||||||||||||||||||||
| Total Fixed Cost | Rs. Lakh |
| Per Unit Tariff Components | Unit | Year | |||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | ||||||
| PU O&M Expenses | Rs./kWh | ||||||||||||||||||||||||||||||||||||||||||||
| PU Depreciation | Rs./kWh | ||||||||||||||||||||||||||||||||||||||||||||
| PU Interest on term loan | Rs./kWh | ||||||||||||||||||||||||||||||||||||||||||||
| PU Interest on working Capital | Rs./kWh | ||||||||||||||||||||||||||||||||||||||||||||
| PU Return on Equity | Rs./kWh | ||||||||||||||||||||||||||||||||||||||||||||
| Total Fixed PU Components | Rs./kWh |
| Levelised Tariff | Unit | Year | |||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | ||||||
| Discount Factor | |||||||||||||||||||||||||||||||||||||||||||||
| Discount Tariff Components | Rs./kWh | ||||||||||||||||||||||||||||||||||||||||||||
| Levelised Tariff | Rs./kWh |
| Year | ||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Unit Generation | Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | |
| Installed Capacity | MW | |||||||||||||||||||||||||||||||||||||||||
| Net Generation | MU |
| Year | ||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Tariff Components (Fixed charge) | Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | |
| O&M Expenses | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Depreciation | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Interest on term loan | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Interest on working Capital | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Return on Equity | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Total Fixed Cost | Rs. Lakh |
| Year | ||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Tariff Components (Variable charge) | Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | |
| Biomass fuel type-1 | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Biomass fuel type-2 | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Municipal Solid Waste | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Refuse Derived Fuel | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Fossil fuel (coal) | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Sub-total (Fuel Costs) | Rs. Lakh | |||||||||||||||||||||||||||||||||||||||||
| Fuel cost allocable to power | % | |||||||||||||||||||||||||||||||||||||||||
| Total Fuel Cost | Rs. Lakh |
| Year | ||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Per Unit Tariff (Components) | Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | |
| PU & O&M Expenses | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| PU Depreciation | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| PU Interest on term loan | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| PU Interest on working Capital | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| PU Return on Equity | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| PU Total Fixed Components (Fixed) | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| PU Total Fixed Components (Variable) | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| PU Total Fixed Components (Total) | Rs./kWh |
| Year | ||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Levelised Tariff | Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | |
| Discount Factors | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| Discount Tariff Components (fixed) | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| Discount Tariff Components (variable) | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| Discount Tariff Components (total) | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| Levelised Tariff (fixed) | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| Levelised Tariff (variable) | Rs./kWh | |||||||||||||||||||||||||||||||||||||||||
| Levelised Tariff (total) | Rs./kWh |
By Order of the Commission,
NEERAJ SATI,
Secretary,
Uttarakhand Electricity Regulatory Commission.
पी०एस०यू० (आर०ई०) 34 हिन्दी गजट/317-भाग 1-क 2023 (कम्प्यूटर/रीजियो)।
मुद्रक एवम् प्रकाशक-अपर निदेशक, राजकीय मुद्रणालय, उत्तराखण्ड, रुड़की।
भाग 1-क
उत्तराखण्ड गजट, 28 अगस्त, 2023 ई० (गजटपद 04, 1945 राक रागद)