SSERC · Sikkim State Electricity Regulatory Commission
Green Energy Open Access (GEOA) Regulations, 2023
Sikkim State Electricity Regulatory Commission (Terms and Conditions for Green Energy Open Access (GEOA) Regulations, 2023
RegulationDated 11 May 2023Published in the Gazette 17 May 2023No. 404/SSERC/2022-23/02 dated 11.05.2023
Summary
Summary written by software. Check the regulator's original before you rely on it.
The SSERC GEOA Regulations, 2023 create the framework for intra-State green energy open access in Sikkim. The notification (p1) is made under s.181(1)–(2) of the Electricity Act and applies to open access for electricity from renewable sources using the intra-State transmission and/or distribution system, including systems incidental to inter-State transmission (p1). It defines key roles and threshold terms, including ‘Consumer’ as a person with contract demand or sanctioned load of 100 kW or more, with captive consumers exempt from that load limit (p1–2), and defines renewable energy broadly to include hydro, pumped storage, storage charged from RE, green hydrogen/ammonia (p2).
Eligibility and categorisation: open access is long-term (5 years or more), medium-term (over one year to under five), or short-term (one year or less) (p2–3); eligible consumers include those at 100 kW and above and captive generators, with restrictions on changing RE quantum across twelve time blocks (p3). SLDC acts as State Nodal Agency, and applications go through the Central Nodal Agency portal (p3–4).
Procedure: detailed timelines sit in Schedule I (p4, p11–12), with processing fees, bank guarantee, deemed grant if the SNA does not respond in 15 working days, and cancellation for failure to sign a wheeling agreement or commission within twelve months (p4–6). Day-ahead GEOA has a separate timeline and fee (p6). Non-utilisation and surrender rules are specified (p6).
Charges: transmission, wheeling, cross-subsidy, standby, banking and other charges, plus monthly transaction and meter-reading fees; Schedule II gives formulas and methodologies (p7, p14–18). Banking is monthly, with no carry-forward and a 30% payment explanation (p7). Curtailment priority prefers GEOA over normal OA within categories (p7–8). Dispute resolution runs through SLDC then the Commission (p8). Metering, energy losses, grid code compliance, collection/disbursement, information system, reports, communication and Commission powers follow (p8–10).
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read SSERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 21 Nov 2026. A document SSERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of SSERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.