Consolidated copyDated 23 Feb 2006Published in the Gazette 28 Feb 20061/1/KERC-2006/XI dated 23/02/2006
A consolidated copy of the Conditions of Licence for Existing Distribution Licensees Regulations, 2006, published by KSERC for reference. It may not include the latest amendments; read it with the amendments listed for the regulation.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the consolidated text of the KSERC (Conditions of Licence for Existing Distribution Licensees) Regulations, 2006 — the instrument through which the Kerala Commission fixes the general and special conditions attaching to the licences of distribution licensees already in business when the Electricity Act, 2003 took effect. Made under the proviso to s.16, it was notified on 23 February 2006 and published in the Kerala Gazette Extraordinary on 28 February 2006, and it applies to the State of Kerala (p1).
Chapter I (pp1–3) gives the short title, commencement from gazette publication, territorial application, definitions of 'Act' and 'Commission', and reproduces the Statement of Objects and Reasons explaining why deemed licensees under the provisos to s.14 need conditions specified by the Commission. It sets the procedure for amending a licence — Commission-initiated or on application, notices in two English and two Malayalam dailies, a 30-day objection window, Central Government consent where defence land is involved — and a power to remove difficulties (pp2–3).
The substance sits in Form I, made applicable by clause 3 (p2). Part I (pp3–6) defines the licence vocabulary: area of distribution, licensed business versus other business, major incident, operational control, use of system and the various standards. Part II (pp6–17) holds the general conditions — duty to develop and maintain an efficient distribution system, obligation to supply, non-discriminatory open access with default supply preserved, acts requiring prior Commission consent (acquisition, merger, assignment, sale outside the State), other-business and separate-account rules, subsidy controls, reporting including major-incident timelines and business plans, transfer or relinquishment of operational control, licence fee and dispute resolution. Part III (pp17–22) is technical: load forecasting, annual revenue requirement and tariff recovery only through approved tariffs, power procurement approval (deemed granted if the Commission does not decide within 90 days), investment planning and tendering, and compliance with the Grid Code, the Electricity Supply Code and the approved planning, operating and performance standards. Part IV (pp22–24) covers consumer complaints, consumer rights and information, use of system, competition, penalties, revocation and interpretation. Part V (pp24–25) carries the special conditions — the asset-value threshold for prior notice of relinquishment and the annual licence fee, with a concessional rate for KSEB Ltd.
Two amendments are footnoted: the First Amendment Regulations, 2009 (gazette 23.12.2009), which rewrote the fee-payment wording, and the Amendment Regulations, 2022 (gazette 04.07.2022, effective 01.04.2022), which added the KSEB Ltd concession.
Read with this
The regulation
Amendments and corrections
Other copies of these documents (1)
3 more documents belong here and are not on Voltaic: 3 copies in another language.
Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.