Summary written by software. Check the regulator's original before you rely on it.
The JSERC (Demand Side Management) Regulations, 2010 are a principal state regulation, notified in the Jharkhand Gazette on 16 September 2010 (p1) and coming into force from that notification (p2). They apply to every distribution licensee in the State within its own area of supply (p2) and set up a process by which the Commission steers demand side management without itself prescribing programme-level detail.
Chapter I (pp2–3) gives the title, extent and commencement and fixes the vocabulary used later — baseline data, DSM, DSM resource acquisition, energy service company, cost effectiveness index, evaluation/measurement/verification and monitoring. Chapter II (pp3–5) puts objective-setting and target-setting with the Commission, requires each licensee to assess the technical potential for DSM one year before every MYT control period (first assessment within six months of notification), and provides for Commission guidelines on load research, implementation, cost effectiveness, monitoring, eligibility, target and funding methodology and database development — guidelines expressly not a precondition to the first DSM plan.
Chapter III (pp5–6) requires a DSM Cell in each licensee within three months. Chapter IV (pp6–10) is the operative core: load and market research and baseline development; a perspective DSM plan (first plan within one year, running to the end of the ongoing MYT control period) plus rolling annual plans; Commission review and approval of the plan; a programme document and prior Commission approval for each programme; mechanisms to recover net incremental cost through tariff; and monitoring, reporting and third-party evaluation, measurement and verification.
Chapters V–VII (p10) require six-monthly progress reports and a programme completion report within one month of completion, allow the Commission to grant incentives, and reserve to the Commission powers of amendment, difficulty removal, practice directions and dispute resolution.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read JSERC's website for final documents on 24 Nov 2026 (5 pages) and for drafts on 21 Nov 2026. A document JSERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of JSERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.