HPERC · Himachal Pradesh Electricity Regulatory Commission
Captive Generating Plant (CGP) Status Verification Procedure, Himachal Pradesh, 2021 — Draft
Procedure for verification of Captive Generating Plant (CGP) Status in the State of Himachal Pradesh
Draft procedureDated 24 Aug 2021HPERC-H(1)-34/2021 dated 24 August, 2021
Draft
A proposal, not law. Voltaic holds no final regulation made from this draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Himachal Pradesh Electricity Regulatory Commission issued this notification on 24 August 2021 (p1) carrying a draft Procedure for verifying captive generating plant (CGP) status in the state. It is a pre-publication draft: the Commission proposes to make the procedure and invites objections or suggestions within thirty days of publication in the Rajpatra, Himachal Pradesh, from which date the procedure would also apply (p1).
Clause 2 defines only what the procedure itself needs — Act, section, Verifying Authority — and defers to the Act and HPERC regulations for everything else (p1–2). Clause 3 reproduces in full section 9 of the Electricity Act, 2003 and rule 3 of the Electricity Rules, 2005, which carry the substantive ownership and consumption tests (p2–4). Clause 4 restates how those tests are to be applied: the ownership and consumption conditions, treatment of plants and users located outside Himachal Pradesh, and the variants for a single user, associations of persons, non-SPV companies, cooperative societies, partnership firms/LLPs and SPVs, including proportional-consumption and weighted-average shareholding rules (p4–6).
Clause 5 designates the State Load Despatch Centre as Verifying Authority and fixes its annual and monthly determination and reporting duties (p6). Clause 6 is the operational core: the ownership documents required from each form of ownership, the annual verification cycle, the change-intimation duty, and how captive consumption is computed, reported and metered, with a special first-year rule for open access (p6–10).
Later clauses cover when a plant ceases to qualify and how default is apportioned among shareholders (p10–11), metering including embedded CGPs (p11–12), recovery of cross-subsidy and additional surcharge through monthly billing, payment security instruments, refunds and interest (p12–14), and default in payment (p14). Annexures supply the owner's undertaking and the chartered-accountant certificate formats (p15–26).
Read with this
Voltaic holds no final regulation made from this draft.
No other documents to read with it are on Voltaic.
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.