MPERC · Madhya Pradesh Electricity Regulatory Commission
Terms and Conditions for Tariff Determination of Energy from Renewable Energy Sources (Revision-I) Regulations, 2024
Madhya Pradesh Electricity Regulatory Commission (Terms and Conditions for Tariff determination of energy from Renewable Energy Sources) (Revision- I) Regulations, 2024 {G-43(I) of 2024}
RegulationDated 2 Aug 2024No. 1790/MPERC/2024 dated 02/08/2024
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is MPERC's principal tariff regulation for renewable energy in Madhya Pradesh, notified on 02/08/2024 and running to 31 March 2027 (p1). It replaces the 2017 RE tariff regulations and sets out how the Commission determines generic tariffs, project-specific tariffs and adopts competitively bid tariffs. It extends to the whole State (p1).
Regulations 1–4 handle commencement, definitions and the eligibility split. Regulation 4.1 lists the technologies the Commission determines under Section 62 — including "Wind Power Project using new Wind Turbine generators with capacity less than 10 MW", small hydro up to and including 25 MW, biomass, bagasse cogeneration, "Solar PV and Solar Thermal Power Projects ... with capacity less than 5 MW", biogas, biomass gasifier, municipal solid waste, solar-wind hybrid below 10 MW and RE-with-storage (p5). Regulation 4.2 routes larger projects — wind of 10 MW and above, solar of 5 MW and above, hybrid of 10 MW and above — to adoption under Section 63 (p6), and Regulation 4.3 provides case-to-case project-specific tariff below the bidding thresholds (p7).
Chapter 1 (Regulations 5–12) states the principles: the control period, which technologies get a generic tariff (small hydro, biomass Rankine, bagasse cogeneration, biogas, MSW) versus project-specific tariff (solar PV and thermal, wind, biomass gasifier, hybrid, storage), the petition process and the forms and disclosures required, the single-part tariff structure and levelisation, the treatment of excess generation, and scheduling/despatch links to the 2021 cogen-and-RE regulations, the 2018 forecasting and DSM regulations and the MP Grid Code 2024 (p7–10).
Chapter 2 carries the common financial methodology: capital cost basis, debt-equity treatment, loan tenure and an SBI MCLR-linked interest rate, depreciation, return on equity, working capital, O&M escalation, rebate and late payment surcharge, CDM benefit sharing, and treatment of subsidy, cess, duties and water charges (p11–14).
Chapters 3–13 give technology-specific norms — small hydro (p15), biomass Rankine (p16–17), bagasse cogeneration (p18–19), biogas (p20), MSW (p21), solar PV (p22), solar thermal (p23), wind (p24), biomass gasifier (p25), wind-solar hybrid (p26) and RE with storage (p27). For several technologies the Commission determines capital cost, CUF/PLF, auxiliary consumption and O&M case by case, with the chapter fixing only a floor or ceiling; for others it sets normative values for the control period.
Chapter 14 (Regulations 88–92) permits deviation from the norms for bilaterally agreed tariffs, gives the Commission powers to amend, relax and remove difficulties, and repeals and saves the 2017 regulations (p28–29). Four petition forms follow (p30–36).
Read with this
No other documents to read with it are on Voltaic.
One more document belongs here and is not on Voltaic: a copy in another language.
Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of MPERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.