HPERC · Himachal Pradesh Electricity Regulatory Commission
General Conditions of Transmission Licence Regulations, 2004
Himachal Pradesh Electricity Regulatory Commission (General Conditions of Transmission Licence) Regulations, 2004
RegulationDated 10 Jun 2004HPERC/381 dated 10th June, 2004
1 amendment to it is on Voltaic, dated 22 Feb 2005.
Summary
Summary written by software. Check the regulator's original before you rely on it.
Notification No. HPERC/381 dated Shimla, 10 June 2004 (p1) makes the Himachal Pradesh Electricity Regulatory Commission's standard conditions for transmission licences under s.16 read with s.181(2)(d) of the Electricity Act, 2003, in force from 10 June 2004 (p1).
Regulations 1–2 give the title, commencement and a long definition list (pp1–5) covering 'area of activity', 'licensed business', 'other business', 'intervening transmission facilities', 'transfer', 'users' and a transmission system defined as lines of 33 kV and above. Regulation 3 leaves the licence's term to the order granting it.
Regulations 4–5 set the licensee's compliance duties and permitted activities: non-discriminatory open access, no electricity trading or distribution business, restrictions on acquiring other utilities or generation interests, and conditions for carrying on 'other business' with ring-fenced accounts (pp5–7).
Regulations 6–9 cover accounts and financial reporting, information and incident reporting, business plans, investment approval and asset transfer, with Commission consent and post-facto approval in emergencies (pp7–15). Regulations 10–13 deal with licence fees and interest on default, grounds and procedure for revocation, amendment of licence conditions under s.18, and Commission arbitration of licensee disputes (pp15–17).
Regulations 14–17 require planning, security and operating standards, grid code compliance, connection and use-of-system arrangements, and filing of expected revenue calculations and tariff proposals (pp17–23). Regulations 18–22 apply the conditions to the State Transmission Utility with carve-outs, preserve waiver powers, extend them to deemed licensees, allow removal of difficulties for one year, and repeal earlier transmission licence conditions with savings (pp23–24).
Read with this
Amendments and corrections
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of HPERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.