The Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, its Compliance and Implementation of Renewable Energy Certificate Framework) Regulations, 2016 — notification No. MERC/Tariff/Regulation/2016/01743, signed 30 March 2016 — build the State's RPO regime and tie it to the central renewable energy certificate framework. They extend to the whole of Maharashtra and take effect from publication in the Official Gazette (p15).
Regulations 1–2 give the short title, extent and commencement and define the working vocabulary: obligated entity, captive user, open access consumer, certificate, floor and forbearance price, inter-connection point, preferential tariff, renewable energy sources and the State Agency, MEDA (p15–17).
Part A (Reg 3) frames the scope: promoting cogeneration and RE generation and fixing a procurement percentage against a distribution licensee's total consumption (p17).
Part B is the operative core. Regulation 4 lists eligible RE sources and the capacity and metering conditions for eligible generation; Reg 5 identifies who is obligated, keyed to captive plant size and open-access contract demand; Reg 6 fixes the four-year operating period; Reg 7 prescribes year-wise solar, non-solar and composite targets, a mini/micro hydro carve-out, a tolerance band and a lighter composite-only duty for smaller entities; Reg 8 makes CERC-issued certificates the compliance instrument, with solar and non-solar ring-fenced; Regs 9–11 assign the State Agency's monitoring and reporting role and the filing duties of distribution licensees, captive users and open access consumers; Reg 12 sets RPO regulatory charges for shortfalls; Reg 13 creates a Monitoring Committee under the Grid Co-ordination Committee (p18–23).
Part C (Reg 14) lets RE projects commissioned in the operating period choose between the State RE tariff route and the REC route, and locks the choice for the tariff period or PPA. Part D (Regs 15–19) covers grid connectivity cost-sharing and the Commission's powers to relax provisions, issue orders and practice directions, amend, and remove difficulties (p23–24).
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of MERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.