Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Commission's process manual for how the distribution licensee is to prepare, design, get approved, fund, implement and verify a demand side management (DSM) plan (p1). It sits beneath the State's DSM Regulations: the Regulations set out the activities and mandate the licensee to undertake them, while these General Guidelines describe the procedure to be followed (p1). No commencement date, validity period or control period is stated anywhere in the text.
Pages 1–3 lay the analytical foundations. Load research covers identifying target consumer segments, end uses and appliances and designing consumer surveys (sample size, selection criteria, questionnaire) (p1). Market research covers availability and penetration of efficient technologies, illustrated by a table of identified technologies that the text expressly calls illustrative and non-exhaustive (p2). A database development framework explains how data is built up from the State's Zones, Circles, Divisions and Sub-Divisions down to consumer category, feeder and sub-station, listing the data items to be compiled (p3). Potential assessment — whose section number is missing from the text — requires the licensee to develop a methodology for financially viable technical potential (p4).
Pages 4–7 cover goal and target setting (proposed by the licensee, finally set by the Commission), cost-effectiveness testing through three complementary tests that must be read together rather than individually, and DSM portfolio design (p4–5). The DSM fund and budget provisions permit recovery of justifiable DSM costs through ARR and tariff, prescribe year-wise budget submission with the MYT/ARR process, and allow pre-approved spending on awareness activities (p5–6); financing sources are then listed (p6).
Pages 7–9 enumerate what the DSM Plan document must contain, section by section: executive summary, introduction, status of the supply system, identification of sectors/segments/end-uses, identification of measures and technologies, funds requirement and financing, administration and management, and implementation.
Pages 9–12 cover submission to the Commission (at least one year before, or coincident with, business plans), DSM-CC review and Commission approval, project implementation and contracting, monitoring and reporting, evaluation, measurement and verification including third-party empanelment, dispute resolution, and a split of activities between the Commission and the licensee (p9–12).
Read with this
The regulation
- Dated 16 Mar 2012Punjab (Demand Side Management) Regulations, 2012
Amendments and corrections
- Dated 21 Jan 2013Corrigendum to Demand Side Management Consultation Committee, 2013
Procedures and orders made under it
Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.