Net Metering/Bi-Directional Metering & Connectivity for Solar PV Projects 2016 — Amendment, 2022

Amendment to the Order on Net Metering/Bi-Directional Metering & their Connectivity with respect to Solar PV Projects 2016 (as amended upto 17.01.2018)

OrderDated 5 May 2022No. OERC-Engg. 02/2022/468 dated 05.05.2022

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on orierc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Odisha Electricity Regulatory Commission's amendment order No. OERC-Engg. 02/2022/468 dated 05.05.2022 (p1), which amends the Commission's 2016 Order on Net Metering/Bi-Directional Metering and their connectivity with respect to Solar PV Projects, itself last amended up to 17.01.2018. The order renames the consolidated instrument to add Gross Metering, Group Net Metering and Virtual Net Metering (p1).

The preamble (p1) gives the reasons: stakeholders raised group and virtual net metering; DERC issued guidelines on both in 2019; MNRE wrote on 30.01.2022 asking SERCs to facilitate them; Odisha consumers proposed group metering; and the Ministry of Power notification of 28.06.2021 under the Electricity (Rights of Consumers) Rules, 2020 capped a prosumer's net metering capacity at 500 kW or the sanctioned load, whichever is lower.

The operative amendments follow. The preamble's Clause 1(vi)(c) is replaced to set the net metering capacity ceiling and to keep it within 75% of transformer capacity (p1). Four new definitions are inserted after Clause 2(c) — net metering, gross metering, group net metering and virtual net metering — the last two expressly covering Battery Energy Storage Systems charged through a renewable energy system (p1–2). The definition of Prosumer is replaced (p2), and existing Clause 2(d) and 2(f) are renumbered as 2(h) and 2(j).

A new Clause 15 (p2) creates the group and virtual net metering framework: virtual net metering is confined to Domestic and Specified Public Purpose consumers under the OERC Distribution (Conditions of Supply) Code, 2019, and to Government/local authority offices, and the installed capacity under either framework must be not less than 5 kW and not more than 500 kW. Existing Clauses 15 and 16 are renumbered as 16 and 17. The amendment takes effect prospectively from the date of its notification (p2).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Gross metering

Voltaic last read OERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (9 pages) and for drafts on 21 Nov 2026. A document OERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on orierc.org ↗

Report an issue with this document