Odisha Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) Regulations, 2022
Draft regulationDated 15 Oct 2022
Draft
A proposal, not law. Voltaic holds no final regulation made from this draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a public consultation package from the Odisha Electricity Regulatory Commission: a public notice (p1) and the revised draft of the OERC (Deviation Settlement Mechanism and Related Matters) Regulations, 2022 (pp2–13). The notice, dated 15 October 2022, says the draft is published under s.181(3) of the Electricity Act 2003 and invites objections and suggestions by 18.11.2022 at 5:00 p.m. It records that the earlier draft of 2 August 2021 had to be revised after CERC issued new Deviation Settlement Mechanism Regulations in March 2022, and that the final regulations will go to the official gazette after the Commission considers the responses.
The draft itself is a full principal regulation. Regulations 1–3 fix the short title, commencement on gazette notification, repeal of the OERC (Intra-State ABT) Regulation, the objective of holding grid users to schedule through a commercial mechanism, and the scope — sellers above 1 MW installed capacity scheduling through SLDC, buyers including distribution and deemed distribution licensees and consumers connected to the intra-state transmission system, with consumer deviation settlement routed to the Intra-State Open Access Regulations, 2020 (p2).
Regulation 4 (pp2–5) is the definitional spine, covering deviation, general versus WS sellers, available capacity, reference charge rate, area clearing price, the market contract types, time block, state entity and the State Power Committee. Regulation 5 requires adherence to schedule; Regulation 6 (pp5–6) sets participation pre-conditions — non-discriminatory treatment, information to SLDC, SLDC despatch instructions binding, connection agreements with the STU or distribution licensee, and 15-minute metering.
Regulation 7 (pp6–7) gives the formulas for computing deviation for general sellers, WS sellers and buyers. Regulation 8 sets the normal rate of deviation charges by reference to the higher of Day Ahead and Real Time Market clearing prices, with a fallback for missing prices and a future option to adopt ancillary service charges. Regulation 9 (pp7–10) is the charges table: slabs of over-injection and under-drawal with rate multipliers payable into the Deviation Pool Account, plus zero charges for infirm injection and normal rates for start-up power and shutdown auxiliaries.
Regulations 10–12 (pp10–12) establish the State Deviation Pool Account, its credits, charges, surplus use and shortfall recovery, the State Energy Account and consumer billing, third-party verification, an SLDC energy accounting procedure, payment timelines, late payment surcharge and Letter of Credit security. Regulation 13 creates the State Power Committee and lists its functions; Regulations 14–17 reserve the Commission's powers to relax, amend, remove difficulties and issue directions.
Read with this
Voltaic holds no final regulation made from this draft.
No other documents to read with it are on Voltaic.
Voltaic last read OERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (9 pages) and for drafts on 21 Nov 2026. A document OERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.