This is the draft West Bengal Electricity Regulatory Commission (State Electricity Grid Code) Regulations, 2017 — the WBEGC or State Grid Code — which the Commission proposes to bring into force on gazette publication, superseding the 2007 State Grid Code and all its amendments (p5, p87). It extends to the whole State and applies to the STU, SLDC and every user connected to or using the intra-State transmission system (p14).
Chapter 1 (p5–17) sets the short title, extent and commencement, defines the code's vocabulary, routes persistent non-compliance through the Member Secretary of the State Power Committee to the Commission, leaves reactive energy charges to a separate order, allows exemptions only on petition, and gives interpretation rules. Chapter 2 (p18–26) allocates functions and linkages: SLDC as apex operator, ALDCs to be set up by every distribution licensee, the STU as planning and long/medium-term open access nodal agency, transmission licensees, generating companies, distribution licensees, the State Co-ordination Forum and the State Power Committee — its composition, secretariat, operationalisation timelines, functions and Metering Committee.
Chapter 3 (p27–35) is the System Planning Code: the STU's long-term transmission plan and annual updates, load forecasting duties on distribution licensees, planning criteria and contingency standards, distribution planning, planning data exchange, and implementation of the transmission plan. Chapter 4 (p36–51) is the Connectivity Conditions Code: connection and safety standards by reference to CEA regulations, the application and offer procedure, connection agreements, connection point demarcation, parameter variations, protection and fault clearance, metering classes, reactive compensation, communication and recording instruments, site responsibility schedules, single line diagrams and site common drawings, and conditionality of connectivity where a PPA is absent.
Chapter 5 (p52–68) is the Operating Code: operating policy, system security (governor operation, AVRs, protection coordination, frequency and voltage, under-frequency and df/dt load shedding, system protection schemes, must-run treatment of solar and wind), demand estimation, demand management, operational liaison, outage planning, recovery and black-start procedures, and event reporting. Chapter 6 (p69–85) is the Scheduling and Despatch Code: demarcation of responsibilities, merit order despatch, capacity declaration including the notional/actual declared capacity regime for coal shortage, the block-wise daily scheduling timetable and revision rules, wind and solar forecasting and scheduling, and reactive power and voltage control. Chapter 7 (p86–87) determines transmission loss, provides for annual SPC review of grid performance, and reserves powers to amend, remove difficulties and dispense with regulations.
Annexure-1 (p88–89) sets the complementary commercial mechanisms — capacity and energy charges, deviation settlement, transmission loss computation, State Energy Accounts, VAr charges and rounding. Annexure-2 (p90–91) works through the payment rules for reactive energy exchanges on beneficiary-owned interconnecting lines.
Read with this
Voltaic holds no final regulation made from this draft.
No other documents to read with it are on Voltaic.
Voltaic last read WBERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document WBERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.