JSERC · Jharkhand State Electricity Regulatory Commission
Terms and Conditions for Intra-State Open Access Regulations, 2016
Jharkhand State Electricity Regulatory Commission (Terms and Conditions for Intra-State Open Access) Regulations, 2016
RegulationDated 28 Sep 2016Published in the Gazette 8 Dec 2016No.54 dated 28th September 2016
1 amendment to it is on Voltaic, dated 9 Feb 2021.
Summary
Summary written by software, from pages 1 to 35 of 44. Check the regulator's original before you rely on it.
The JSERC (Terms and Conditions for Intra-State Open Access) Regulations, 2016, notified on 28 September 2016 and published in the Jharkhand Gazette on 8 December 2016, create the framework for connectivity and open access on intra-State transmission and distribution systems in Jharkhand. They come into force on gazette publication and remain in force until 31 March 2020 unless reviewed or amended (p1).
Chapter I (pp1–6) sets out title, extent, definitions, and the requirement for the STU to form a Coordination Committee and frame detailed procedures and application formats for Commission approval. Chapter II (pp7–11) covers eligibility for connectivity and the separate application and processing routes to the intra-State transmission system (through STU) and distribution system (through distribution licensee), including interim fees, timelines, connection agreements, and testing/infirm power.
Chapter III (pp12–14) lays down general eligibility for open access, the 1 MW consumer threshold with captive exemption, protections for existing distribution licensees and existing open access users, and criteria for LTOA, MTOA and STOA. Chapter IV (pp15–26) classifies applications by system, location, duration and transaction type, and sets application procedure, interim fees, bank guarantee, timelines, consent requirements, treatment of defaulters, and allotment priority.
Chapter V (pp27–32) specifies transmission/distribution charges, scheduling and system operation charges, cross-subsidy and additional surcharges, standby power, imbalance charges, reactive energy charges, and parallel operation charges. Chapter VI (pp33–35) begins scheduling, metering and energy-loss provisions. Inter-state transactions are expressly routed through CERC regulations (pp18, 21).
Read with this
Amendments and corrections
Voltaic last read JSERC's website for final documents on 24 Nov 2026 (5 pages) and for drafts on 21 Nov 2026. A document JSERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of JSERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.