NERC · Nagaland Electricity Regulatory Commission
Minimum Information to be Maintained by a Licensee or a Generating Company Regulations, 2012
The Nagaland Electricity Regulatory Commission (Minimum information to be maintained by a licensee or a generating company) Regulations, 2012
RegulationDated 15 Nov 2012NO.NERC/REGN/2012(A) dated the 15th Nov, '12
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Nagaland Electricity Regulatory Commission's principal regulation telling licensees and generating companies in the State exactly what records they must keep, how their accounts must be kept, and how an Investigating Authority appointed under section 128 of the Electricity Act will scrutinise them (p1). It applies to the whole of Nagaland and comes into force on gazette publication, a date the document does not print (p2).
Chapters 1–2 (p1–5) give the title, extent and commencement, and define the working vocabulary — Act, annual and accounting statements, licensed business versus other business, area of supply, auditor, licensee, generating company, 'integrated utility' (the Department of Power, Nagaland or its successor), RLDC and SLDC.
Chapter 3 (p6–9) sets general duties, plus specific duties for transmission licensees (efficient system operation, RLDC/SLDC directions, non-discriminatory open access, limits on unrelated business and a ban on trading) and for distribution licensees (develop the system, act as common carrier for open access, connect within a month of application, meet performance standards and compensate on failure). It also bars acquisition, merger, assignment or transfer of a licence without prior Commission approval.
Chapters 4–5 (p9–12) cover appointment of an Investigating Authority on complaint or suo moto, its reporting duties, its powers to appoint auditors and inspect records, the checks it must perform, its power to examine officers on oath, and the requirement that the licensee bear investigation costs, which rank ahead of other debts and are recoverable as arrears of revenue. The licensee must produce all books and records and cooperate.
Chapter 6 (p13–25) is the core: a lengthy schedule of the technical, operational, commercial, loss, incident, theft, accident and consumer information to be maintained at all times, cross-referenced to the Nagaland Grid Code and the Nagaland Electricity Supply Code, and detailed accounting rules — financial-year accounts, separate accounts for each business, allocation principles, consistency of allocation basis, voucher-level verifiability and annual auditor certification.
Chapter 7 (p25–29) is a 24-point self-verification list covering supply applications, tariff adherence, supply code, safety, metering, standards of performance and compensation, competition directives, power procurement and statutory notices.
Chapter 8 (p29) states the regulations are additional to, not in derogation of, the Act and rules, and allows the Commission to amend them suo moto.
Appendices 1–22 (p30–52) supply the mandatory formats: balance sheet, fixed assets, depreciation, current assets and liabilities, investments, loans, profit and loss account, fuel cost, power purchase cost, A&G, R&M and employee expenses, interest, income tax, return on equity, cash flow, operating parameters for thermal, hydel, transmission and distribution, and capex.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read NERC's website for final documents on 1 Oct 2026. A document NERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of NERC's website on 1 Oct 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.