OERC · Odisha Electricity Regulatory Commission
Compensation to Victims of Electrical Accidents Regulation, 2020
OERC (Compensation to Victims of Electrical Accidents) Regulation, 2020
RegulationDated 30 May 2020Published in the Gazette 14 Aug 2020No. OERC/Engg/2/2012/535 dated The 30th May, 2020
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Odisha Electricity Regulatory Commission made this regulation under s.181(2)(zp) of the Electricity Act 2003 to create a compensation scheme, independent of fault or civil suit, for victims of electrical accidents in the state. The notification (No. OERC/Engg/2/2012/535) is dated 30 May 2020 and was published in the Odisha Gazette on 14 August 2020, the date on which it came into force (p1).
Chapter I (p1–2) states the title, extends the regulation to the whole of Odisha, applies it to all generating companies and transmission and distribution licensees in their respective licensed areas, and defines the core terms — including 'electrical accident' as an undesired event caused by electric current injuring or killing persons, animals or birds, and 'beneficiary' and 'dependents'.
Chapter II (p2–4) sets safety standards: licensees must install, construct, maintain and operate their works so as to protect the public, animals and birds from electric shock, and must comply with the CEA (Measures relating to Safety and Electric Supply) Regulations. Regulation 4 makes licensees and generating companies liable to pay compensation whether or not there has been wrongful act, omission, rashness, neglect or default, unless the accident was primarily the result of an extraneous cause rather than a failure to meet safety standards. It excludes accidents arising from the victim's own irresponsible act, suicide or homicide, allows recovery of compensation from responsible employees after departmental inquiry, and permits pass-through in the Annual Revenue Requirement in deserving cases.
Chapter III (p4–5) fixes the quantum of compensation by category — loss of human life, disability bands certified by the Chief District Medical Officer/CMO, hospitalization duration, and loss of milch, draught and poultry animals/birds with per-household ceilings — and lets the Commission enhance the amounts by special order, subject to a floor tied to State and National Disaster Response Fund norms. Regulations 7–8 preserve other statutory, contractual and insurance rights, with credit given to amounts already paid.
Chapter IV (p5–7) prescribes the procedure: an occurrence report from the licensee's engineer to the Electrical Inspector and the MD/CEO/Head within 24 hours in Annexure-I format; an enquiry report by the Electrical Inspector within 30 days; claims on Annexure-II; payment or a reasoned order within 30 days of the enquiry report; appeal to the Secretary in charge of the Energy Department (decision final) within 45 days; monthly accident returns to the Commission by the 15th; and deemed contravention under ss.142 and 146.
Chapter V (p7–8) carries residuary provisions preserving other laws, the Commission's inherent powers, its power to issue practice directions, to amend the regulations, and to relax or dispense with clauses in specific cases. Annexures I and II (p9–10) are the reporting and claim forms.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read OERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (9 pages) and for drafts on 21 Nov 2026. A document OERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of OERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.