Skip to content

HERC · Haryana Electricity Regulatory Commission

Conditions of Transmission Licence Regulations, 2008

Haryana Electricity Regulatory Commission (Conditions of Transmission Licence) Regulations, 2008

RegulationDated 31 Oct 2008Regulation No. HERC /18/2008 dated The 31st October, 2008

2 amendments to it are on Voltaic, the latest dated 14 Jun 2021.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on herc.org.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The HERC (Conditions of Transmission Licence) Regulations, 2008 (Regulation No. HERC/18/2008, notified 31 October 2008) lay down the conditions on which the Haryana Electricity Regulatory Commission grants and polices transmission licences in the state. Made under section 16 read with section 181 of the Electricity Act, 2003, they extend to the whole of Haryana and apply to licences issued under section 14 in accordance with HERC's Transmission & Distribution Licensing Regulation (HERC/09/2004) as well as to deemed licensees (p1). They take effect on Gazette publication; the Gazette date is not printed (p1).

The operative regulations (pp1-2) do little more than set title, commencement and application; adopt the definitions of the 2003 Act and, where consistent, the Haryana Electricity Reform Act 1997; provide that the licence conditions are those set out in Form-1; and reserve a power to remove difficulties.

The substance sits in Form-1 (pp2-30), a model transmission licence in five parts. Part I gives the terms — a short-title and definitions clause covering terms such as "area of activity", "major incident", "other business", "users" and "transmission system" (defined as EHV lines of 66 kV or higher) — and the term of the licence, which runs from the date stated in the granting order for the duration mentioned in the licence (pp2-5).

Part II, general conditions (pp6-18), covers compliance with the Act, grid codes and Commission directions; the section 39/40 duties of the STU and other licensees; prohibited activities and the prior-approval procedure; information and major-incident reporting; business plans; other business; investment planning and approval; accounting and audit on an April-March year; dispute resolution; licence fees; transfer or disposal of assets; and investigation and penalty.

Part III sets technical conditions — planning, security and operating standards, grid code review, non-discriminatory open access and connection, and cooperation with the STU and SLDC (pp19-24). Part IV governs tariff and the annual expected revenue requirement filing (pp25-26). Part V covers the STU carve-out, transition for deemed licensees, licensee powers, competition, interpretation and savings (pp27-29). Schedule-1 is the area-of-supply description, with a cantonment/defence no-objection requirement (p30).

Standard name
Licensing Regulations
Primary topics
Licensing and licence conditions, Grid operation and grid code, Transmission tariff

Read with this

Voltaic last read HERC's website for final documents on 24 Nov 2026 (2 pages). A document HERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of HERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on herc.org.in ↗

Report an issue with this document