Expected Revenue from Tariffs and Charges Regulations, 2010

Central Electricity Regulatory Commission (Procedures for calculating the expected revenue from tariffs and charges) Regulations, 2010

RegulationDated 12 Apr 2010No. L-1/9/2009/CERC dated 12.4.2010

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a CERC regulation, notified 12 April 2010 under s.62(5) read with s.178(2)(u) of the Electricity Act 2003, that creates a standing annual reporting procedure for the expected revenue a generating company or transmission licensee will earn from the tariffs and charges the Commission fixes for it (p1). It applies to every case where the Commission determines tariff other than for non-conventional energy sources (p1), and it supplements — expressly does not replace — the reporting already owed under the CERC (Terms and Conditions of Tariff) Regulations, 2009 (p3).

Chapter 2 is the operative core. Every applicant must file the prescribed formats annually, under affidavit, by 30 November, covering the previous, current and ensuing financial years (p3). Past-year and first-half figures must rest on audited or finalised accounts; second-half and ensuing-year figures may be provisional or estimated, certified on affidavit, with assets commissioned after 30 September reported within 90 days of commercial operation (p4). Generating companies forecast availability from fuel availability, maintenance and operating norms; transmission licensees estimate transmission, open-access and other charges (p4). The Commission may direct its own validation procedures (p4).

Chapter 3 removes the application fee, notwithstanding the CERC (Payment of Fee) Regulations, 2008, requires the filed information to be posted on the Commission's website, and gives the Commission power to relax any provision for recorded reasons (pp4–5).

Appendix-I (pp6–16) holds three indicative formats — Thermal, Hydro and Transmission — with instructions on supporting justification, electronic submission and the limited scope of the auditor's certification.

Primary topics
Tariff determination

Read with this

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of CERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗