JSERC · Jharkhand State Electricity Regulatory Commission
Small Hydro Power Projects Tariff Regulations, 2016
Jharkhand State Electricity Regulatory Commission (Determination of Tariff for procurement of power from Small Hydro Power Projects) Regulation, 2016
RegulationDated 28 Sep 2016Published in the Gazette 8 Dec 2016No. 58 dated 28th September 2016
1 amendment to it is on Voltaic, dated 31 Dec 2020.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Commission issues this regulation under ss.61, 62(1) and 86(1) of the Electricity Act 2003 to govern how tariff is determined for power procured from small hydro projects in Jharkhand (p1). It applies to small hydro generating stations of installed capacity between 1 and 25 MW located in the state (p4), runs from Gazette publication until 31 March 2020, and its control period ends on the same date (p1, p5).
Chapter A2 defines the vocabulary used throughout — plant, capital cost, control period, useful life, interconnection point, force majeure and so on (pp2–4). Chapter A3 sets the scope: tariff may be a generic tariff determined on norms, or a project-specific tariff sought by petition with Forms 1.1/1.2, a detailed project report and a subsidy statement; a tariff already discovered through s.63 bidding is to be adopted instead (pp4–5).
Chapter A4 (pp6–12) is the core. It prescribes a levellised cost-plus tariff design discounted at post-tax WACC, makes tariffs firm subject to a closed list of review triggers (water cess, revision of the free-power pass-through limit, change in capital subsidy policy, revision of minimum downstream flow, and force majeure additions), then sets the components: normative capital cost by project size band with a WPI-linked indexation formula for steel and electrical machinery (pp7–9); capacity utilisation factor, plant life, debt-equity ratio, loan term and interest benchmark, depreciation approach, O&M escalation, working capital and interest, return on equity, and auxiliary consumption (pp9–12); closing with a consolidated cost-parameter table (pp11–12).
Chapter A5 (pp13–16) handles the commercial interface: transmission/wheeling charges and losses on the open-access basis, must-run treatment for projects of 10 MW and above, metering and billing per the open access regulations, Grid Code and CEA metering rules, the payment/settlement mechanism with late payment surcharge and rebates, third-party sale rights on default, start-up and shutdown power drawal, evacuation connectivity, treatment of central/state incentives and accelerated depreciation, taxes as a pass-through, industrial-policy benefits, single-window clearance and the tariff period. Chapters A6–A8 reserve the Commission's powers to remove difficulties, amend and act notwithstanding these regulations (p16).
Appendix Forms 1.1 and 1.2 are the data templates a petitioner uses to compute and present tariff (pp18–21).
Read with this
Amendments and corrections
Voltaic last read JSERC's website for final documents on 24 Nov 2026 (5 pages) and for drafts on 21 Nov 2026. A document JSERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of JSERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.