HERC · Haryana Electricity Regulatory Commission
Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation Regulations, 2019
Haryana Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement and related matters for Solar and Wind Generation) Regulations, 2019.
RegulationDated 29 Apr 2019No. 44/2019/HERC. dated The 29th April, 2019
Summary
Summary written by software. Check the regulator's original before you rely on it.
The document is HERC’s 2019 principal regulation for integrating solar and wind generation into Haryana’s intra-state grid through forecasting, scheduling and deviation settlement (p1–2). It opens with a Statement of Object and Reasons explaining SLDC’s section 32 mandate, ABT/DSM background, open access, FOIR recommendations and compatibility with inter-state accounting (p1–2). The operative text is made under sections 66, 86(1)(b), 86(1)(e) and 181 read with sections 32 and 33 of the Electricity Act, 2003 (p2).
Part A (pp2–5) sets commencement, definitions, objective and applicability. The regulation applies to wind and solar generators connected to Haryana’s intra-state transmission or distribution system, including pooling sub-stations and self-consumption or sale within or outside the state, subject to a combined installed capacity threshold of not less than 1 MW at a pooling sub-station or individual generator (p5). A Qualified Co-ordinating Agency (QCA) must be appointed and registered with SLDC.
Part B (pp5–9) is the Forecasting and Scheduling Code: day-ahead and week-ahead forecasts, intra-day revisions, telemetry and metering, QCA registration and duties, SLDC forecasting, and gaming treatment. Part C (pp9–11) contains commercial arrangements: deviation settlement for intra-state sales and self-consumption through absolute-error bands and the state deviation pool; separate treatment for inter-state and outside-Haryana transactions under the Annexure; and separate accounts for inter- and intra-state transactions. Part D (pp11–14) covers implementation: metering, weekly energy accounting, IT-enabled communication, deviation accounting and billing, payment security and interest for delay, curtailment intimation, and de-pooling. Part E (p14) provides practice directions and powers to amend, remove difficulties and relax. The Annexure (pp15–16) sets the framework for deviation charges for generators selling or consuming power outside Haryana, including PPA/APPC fixed rates and REC-based balancing of deemed RPO. The regulation is to be reviewed after two years (p5).
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read HERC's website for final documents on 24 Nov 2026 (2 pages). A document HERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of HERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.