Specific Conditions of Distribution Licence (Gigaplex Estate IT & ITES SEZ, Airoli) Regulations, 2015

Maharashtra Electricity Regulatory Commission (Specific Conditions of Distribution Licence applicable to M/s. Gigaplex Estate Pvt. Ltd., for IT & ITES SEZ at Airoli Knowledge Park, TTC Industrial Area, Airoli, Dist. Thane) Regulations, 2015.

RegulationDated 17 Dec 2015No.MERC/TEC/Licence Conditions/GEPL/2015 dated 17th December 2015

2 amendments to it are on Voltaic, the latest dated 20 Sep 2018.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a project-specific MERC regulation that fixes the distribution licence conditions for a single licensee: M/s. Gigaplex Estate Pvt. Ltd. (GEPL), the developer-licensee of the IT & ITES SEZ at Airoli, Thane (p1). It is made under the Electricity Act 2003 licensing provisions and is deliberately narrow — rather than restating a full licence code, it sets a handful of site-specific conditions and deems them, together with MERC's General Conditions of Distribution Licence Regulations, 2006, to be GEPL's licence (p1).

Paragraphs 1–3 establish the title, extent and commencement, define the key terms (Act, Developer, Deemed Distribution Licensee, General Conditions, GEPL, SEZ Act, SEZ Rules), and state that these Specific Conditions plus the General Conditions govern GEPL's distribution and retail supply operations (p1). Commencement is tied to publication in the Official Gazette, whose date is not printed (p1).

Paragraph 4 defines the area of supply — the whole 11.74 hectares at Plot No. IT-5, as notified by the Government of India and delineated in the annexed map — and lays down what happens if the SEZ area later changes: GEPL must approach the Commission within 15 days of any notification or de-notification, and must keep supplying consumers in a de-notified area until alternative supply is arranged (p2).

Paragraphs 5–9 set the licence term (25 years running from the SEZ notification date of 11 June 2013), require public inspection of the licence, require 24-hour uninterrupted supply in the area, and reserve the Commission's powers to amend the regulations and to remove difficulties by order (p2). Schedule 1 is a map of the area of supply (p3).

Standard name
Licensing Regulations
Primary topics
Licensing and licence conditions

Read with this

Other copies of these documents (1)

7 more documents belong here and are not on Voltaic: 4 copies in another language and 3 drafts or notices on a draft not held as English text.

Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of MERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on merc.gov.in ↗

Report an issue with this document