Skip to content

BERC · Bihar Electricity Regulatory Commission

Consumer Grievance Redressal Forum, Electricity Ombudsman and Consumer Advocacy Regulations, 2017 — First Amendment, 2019

Regulatory Commission (Consumer Grievance Redressal Forum, Electricity Ombudsman and (First Amendment) Regulations, 2019

AmendmentDated 30 Oct 2019Published in the Gazette 4 Nov 2019BERC SMP-19/2019/05 dated The 30th October, 2019

Amends the Consumer Grievance Redressal Forum, Electricity Ombudsman and Consumer Advocacy Regulations, 2017.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on berc.co.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Bihar Electricity Regulatory Commission's First Amendment to its 2017 Consumer Grievance Redressal Forum, Electricity Ombudsman and Consumer Advocacy Regulations was notified on 30 October 2019 and carried in the Bihar Gazette (Extraordinary) of 4 November 2019 (p1). It applies to every distribution licensee in the State of Bihar within its licensed area and comes into force on gazette notification (p1).

The operative text is one amending clause substituting five provisions of the 2017 Regulations. Two substitutions rework who may sit on the Forum: the First Member, who chairs it, must come from a judicial, administrative or licensee-engineering background with a minimum period of experience, with preference for judicial or quasi-judicial work and electricity-regulatory familiarity (p2); the Third Member must be an independent consumer representative drawn from a registered society, NGO or consumer organisation, or a person of standing, and must not have been employed by the distribution licensee for a specified period beforehand (p2). A further clause fixes maximum and minimum ages for both posts (p2). Another replaces the remuneration provision — the Chairperson's pay is left to the licensee with Commission approval, while the Independent Member's per-sitting fee is set out inclusive of travel allowance (p2). The final substitution restates the right of a complainant, the licensee or any other party to appear in person or through an authorised representative (p3). A construction clause makes these Regulations subordinate to the licensees' standards of performance and the Commission's Electricity Supply Code where they conflict (p1–2).

Standard name
CGRF and Ombudsman
Primary topics
Consumer grievance redressal (CGRF)

Read with this

Voltaic last read BERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document BERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on berc.co.in ↗

Report an issue with this document