AERC · Assam Electricity Regulatory Commission

Procurement of Electricity from Rooftop PV & Small Solar Power Generation Programme (RPSSGP) Category 1 Projects Regulations, 2010

Assam Electricity Regulatory Commission (Procurement of Electricity from Projects / Schemes covered under 'Rooftop PV & Small Solar Power Generation Programme' (RPSSGP) - Category 1 Projects under Jawaharlal Nehru National Solar Mission) Regulations, 2010

RegulationDated 31 Oct 2010No. AERC.22/2010/ dated The 31st October, 2010

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on aerc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Assam Electricity Regulatory Commission's notification of 31 October 2010 (No. AERC.22/2010) makes a regulation with a deliberately narrow purpose: to satisfy the MNRE condition that a State have its own tariff framework in place before projects from that State can join the Rooftop PV & Small Solar Power Generation Programme (RPSSGP) under the Jawaharlal Nehru National Solar Mission (p1, p3).

Regulation 2 sets out the JNNSM as background, reproducing the Mission's capacity, off-grid, solar-thermal and rural-lighting targets (p1–2). Regulation 3 defines the scope: it distinguishes Category 1 projects (connected at HT below 33 kV) from Category 2 LT projects, notes that MNRE's guidelines cover only Category 1, and reproduces the key features of RPSSGP — the MoU chain among generator, distribution licensee and IREDA as Programme Administrator, the levelised tariff tenure, monthly certificates of power purchased, and the generation-based incentive flow from IREDA to the distribution licensee (p2–3). It states expressly that the regulations exist only to fulfil the MNRE requirement, and that other solar and renewable projects continue under AERC's 2009 Cogeneration and Renewable Sources regulations (p3).

Regulation 4 is the operative part: it fixes a control/review period, a tariff period running from commercial operation, an annual review of benchmark capital cost, a conditional carry-forward of the generic tariff into the following year, and, for RPSSGP projects, adopts the CERC-determined levelised tariff (including CERC's annual tariffs) as the applicable Assam tariff, with a base rate that escalates annually for later projects but stays constant for a given project (p3–4). Regulation 5 requires compliance with the MNRE guidelines' procedural formalities and technical requirements (p4).

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff, Tariff determination, Power procurement and PPAs

Read with this

No other documents to read with it are on Voltaic.

Voltaic last read AERC's website for final documents on 30 Sep 2026. A document AERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of AERC's website on 30 Sep 2026, Voltaic holds no later regulation that replaces this one.