Plot No-AH/5, Premises No. MAR16-III, Action Area- IA, New Town, Rajarhat, Kolkata – 700163
Tel.- 033 2962 3756, Fax – 033 2962 3757
Email – cp-wberc@gov.in, Website – www.wberc.gov.in
Dated: __/__/2020
The West Bengal Electricity Regulatory Commission (hereinafter referred as ‘WBERC’ or ‘the Commission’), in exercise of its power under section 181 and in compliance with the requirement of previous publication under sub-section (3) of section 181 of the Electricity Act, 2003, published the draft West Bengal Electricity Regulatory Commission (Recovery of Expenditure for Providing New Connections) (First Amendment) Regulations, 2020 (hereinafter referred as the “draft First Amendment 2020”) on its website and invited suggestions/objections/comments vide public notice No WBERC/Regulations-61/19-20/5341 dated 24.01.2020 published in 5 nos of leading newspapers on 25.01.2020. The last date of submission of comments was 10.02.2020.
The Commission in exercise of the powers conferred by sub-section (1) and clauses (zp) of sub-section (2) of section 181 read with section 46 of the Electricity Act, 2003 (36 of 2003) and all powers enabling it on that behalf had notified the West Bengal Electricity Regulatory Commission (Recovery of Expenditure for Providing New Connection) Regulations, 2013 vide notification no 53/WBERC on 2nd April 2013 (hereinafter referred to as the ‘Principal Regulations’).
Considering the Government of West Bengal’s initiative to promote ‘Ease of Doing Business’ and proposals from the Distribution Licensees for providing connections in a simpler and easier way through standard rate schedule (in Rs/ kW) upto 150 kW, the Commission finds it suitable to amend the Principal Regulations.
The Commission received suggestions/objections/comments from only CESC Limited within the specified time limit. The Commission, after detailed analysis and due consideration of the issues raised by the stakeholder on the draft First Amendment 2020, finalised the West Bengal Electricity Regulatory Commission (Recovery of Expenditure for Providing New Connections) (First Amendment) Regulations, 2020 (herein after referred as “First Amendment 2020”) for notification in the Kolkata Gazette Extraordinary. The proposed regulations, suggestions/objections/comments received from the various stakeholder and the rationale /decisions of the Commission thereon have been discussed in the succeeding paragraphs.
“1. Short Title, extent and commencement:
(i) These Regulations may be called the West Bengal Electricity Regulatory Commission (Recovery of Expenditure for Providing New Connections) (First Amendment) Regulations, 2020.
(ii) These extend to the whole of West Bengal.
(iii) These shall come into force on the date of their publication in the Official Gazette.”
4.2 Comments Received: No specific comments / suggestions received from the stakeholders.
4.3 Provision in First Amendment 2020: In absence of any comments/suggestions/objections from the stakeholders the draft regulation is retained.
“4.4 Notwithstanding anything to the contrary contained elsewhere in these Regulations, distribution licensee shall fix the rate of service connection in terms of Rs / kVA, for application at least upto 150 kVA of contract demand. For this purpose, distribution licensee(s) shall form a procedure under regulation 13.13 of Standard of Performance Regulations.”
Accordingly, CESC suggested to modify the draft as below:
4.4 Notwithstanding anything to the contrary contained elsewhere in these Regulations, distribution licensee shall fix the rate of service connection in terms of Rs / kVA or Rs / kW, for application (except Housing / Commercial / Industrial Complexes with multiple beneficiaries) at least upto 150 kVA of contract demand. For this purpose, distribution licensee(s) shall form a procedure under regulation 13.13 of Standard of Performance Regulations.
of the licensee regarding accessing the contract demand in case of bulk connections to Housing / Commercial / Industrial Complex with multiple beneficiaries requires for suitable procedure for providing connections in such cases. The regulation also specified formation of required procedure to provide connections under regulation 13.13 of the Standard of Performance Regulations. Thus at present it is found suitable to retain the proposed draft to this extent.
“4.4 Notwithstanding anything to the contrary contained elsewhere in these Regulations, distribution licensee shall fix the rate of service connection in terms of Rs / kVA or Rs / kW, for application at least upto 150 kVA of contract demand. For this purpose, distribution licensee(s) shall form a procedure under regulation 13.13 of Standard of Performance Regulations.”
Sd/-
(PULAK KUMAR TEWARI)
MEMBER
Sd/-
(DURGADAS GOSWAMI)
MEMBER
Sd/-
(SUTIRTHA BHATTACHARYA)
CHAIRPERSON
Dated: _____
27/02/2020