KERC · Karnataka Electricity Regulatory Commission
Licensing Regulations, 2004
Karnataka Electricity Regulatory Commission (Licensing) Regulations, 2004
RegulationDated 4 Nov 2004Published in the Gazette 2 Dec 2004No.D/01/3 dated 4th November 2004
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is KERC's principal licensing regulation, made under s.181 of the Electricity Act 2003 and notified in the Karnataka Gazette on 02.12.2004 (p1). It extends to the whole of Karnataka and comes into force from Gazette publication (p2). The Statement of Objects and Reasons (pp1-2) explains the gap it fills: deemed licensees need no new licence, but the Commission must prescribe the form and manner of application for everyone else, and issue licence conditions for the transmission company alongside those already issued for the ESCOMs.
Chapter I (pp2-3) gives the short title, commencement, extent and the defined terms, and applies the KERC (General and Conduct of Proceedings) Regulations, 2000 to proceedings under these regulations.
Chapter II (pp4-12) is the operational core. Regulations 3-4 carve out deemed licensees, co-operatives, rural generators/distributors and franchisee-type bodies, then set who must apply and what a licence application must contain. Regulations 5-16 lay out the full processing pipeline: receipt and acknowledgement, public inspection of the application, scrutiny, acceptance, newspaper advertisement of the application, amendment of the draft licence, objections and suggestions, defence-area no-objection certificates, local inquiries and hearings, approval or refusal of the draft licence, and notification of grant. Regulations 17-24 then cover the term and extension of a licence, deposit of maps and printed copies, annual accounts, model conditions of supply, the role of the annexed Forms in setting conditions of licence, and amendment of an existing licence.
Chapter III (pp13-14) sets out arbitration: adjudication of licensee/generator disputes by the Commission or by nominated arbitrators, nomination procedure, award procedure and cost.
Chapter IV (pp15-17) contains the miscellaneous powers — restrictions on acquiring, merging, assigning or transferring a utility or licence, fines and charges for violation, saving of inherent powers, power to remove difficulties, power to dispense with requirements, extension or abridgment of time, no invalidation for procedural failure, and enforcement of Commission orders by the Secretary.
Form 1 (pp18-19) is the prescribed licence application form.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read KERC's website for final documents on 24 Nov 2026 (3 pages) and for drafts on 23 Nov 2026. A document KERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of KERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.