The Tripura Electricity Regulatory Commission (Compliance Audit) Regulations, 2010 create the framework under which the Commission audits whether the entities it regulates are complying with the Electricity Act 2003, rules and regulations made under it, and the Commission's own orders and directions (p1). They apply in the State of Tripura and commence on publication in the Official Gazette — no Gazette date is printed anywhere in the document (p1).
Regulation 2 defines the Act and the "Regulated Entities" the regime covers: distribution licensees, generation companies, transmission licensees, electricity traders and State Load Despatch Centres (p1).
Regulation 3 lets the Commission conduct an audit at any time and governs how auditors are obtained: empanelment by order, appointment from the panel or fresh selection, and single-source selection in exceptional cases (p1–2). Before an audit begins, the Commission frames terms of reference setting out outputs and timeframes, and assigns the specific task by order (p2).
Regulation 4 sets independence and conduct requirements for consultants/auditors, including a five-year bar on holding office or any commercial interest in the audited entity, a duty of professional skill and care, and a written no-conflict declaration (p2–3).
Regulation 5 sets the cost mechanics: the Commission pays for the audit and recovers the expense from the regulated entity, which may then claim it through the annual revenue requirement, a tariff application, an approved trading-margin increase, or the SLDC annual budget (p3).
Regulation 6 is the methodology: inspection and investigation powers with reasonable advance written notice; the regulated entity's duty to produce books, registers and information; evidence collection through data requests, site visits, interviews and analysis including sampling; use of third-party complaints; the minimum contents of the audit report; a signed statement that the terms of reference were met and the report reflects the auditor's professional opinion; and supply of the report to the regulated entity (p3–5).
Regulation 7 allows the Commission to act on a report after giving the entity a reasonable opportunity to make a representation. Regulations 8–10 give the Commission power to remove difficulties, to amend the regulations, and to issue orders and practice directions for implementation (p5).
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read TERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document TERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of TERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.