Delhi Electricity Regulatory Commission (Approval of Capital Investment Schemes for Distribution Licensees) Regulations, 2023

Draft regulationDated 22 Jun 2023No. F.17(316)/DERC/Engg./2022-23/7550

Draft

A proposal, not law. Voltaic holds no final regulation made from this draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on derc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Delhi Electricity Regulatory Commission has issued this draft principal regulation to control how distribution licensees in Delhi plan, seek approval for, and report capital investment. It is made under the Electricity Act 2003, sections 61 and 86 read with section 181, and applies to all distribution licensees, including deemed licensees, in the State of Delhi (p2). It comes into force on publication in the Official Gazette; the Gazette date is not printed (p2).

Regulation 3 sets out what may count as a capital investment scheme (p6–12): objectives, indicative categories, categories expressly excluded, special rules for metering, smart/prepaid meters, overhead-to-underground cable conversion and asset replacement, and separate treatment of Opex schemes. Regulation 4 creates the two-stage framework: in-principle approval before capex, then final approval of completed cost after assets are put to use (p12–13, p19). Schemes above 'Rupees 50 Lacs' are DPR Schemes requiring in-principle approval; below that they are Non-DPR Schemes, with exemptions for certain 11 kV/LT, grant-funded, emergency and unforeseen schemes (p12–13).

Regulations 5 and 6 prescribe the particulars an applicant must file for in-principle approval and for completed-cost approval, including technical and financial justification, cost-benefit analysis and completion certificates (p14–20). Regulation 7 requires a rolling three-year capital investment plan, updates and website publication, and says the plan is not itself an approval though provisional capitalisation may be allowed in ARR projections (p20–21). Regulations 8 to 10 set the Commission's prudence-check criteria for in-principle approval and for completed cost of both DPR and Non-DPR schemes, including disallowance or lower return on equity if benefits are not established (p21–27).

Regulations 11 to 15 deal with establishment overheads and road-restoration/right-of-way variations (p27), time and cost overrun treatment, including a delay-linked disallowance matrix for excess interest during construction and a 15% cost-overrun margin (p27–29), pre-requisites for capex schemes such as competitive bidding, related-party approvals and one-year initiation deadlines (p29–31), and the Standard Cost Data Book process (p31). Regulations 16 to 21 cover filing/publication, repeal of the earlier Guidelines for Approval of Capital Investment Schemes, and powers to relax, amend or remove difficulties (p32). Appendices give the application, approval, rolling-plan and non-DPR acknowledgement formats (p33–45).

Standard name
Capital Investment Approval
Primary topics
Capital cost and investment, Network planning and investment, Return, financing and working capital

Read with this

Voltaic holds no final regulation made from this draft.

Proposed changes (drafts with no final yet)

Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on derc.gov.in ↗

Report an issue with this document