OERC · Odisha Electricity Regulatory Commission
Terms and Conditions of Intra-State Open Access Regulations, 2020
OERC (Terms and Conditions of Intra-State Open Access) Regulations, 2020
RegulationDate not stated
Summary
Summary written by software, from pages 1 to 45 of 66. Check the regulator's original before you rely on it.
It applies to open access over the intra-State transmission and distribution systems in Odisha, including when those systems are used with the inter-State transmission system (p2).
Chapter 3's definitions (pp2–4) establish the Act, Commission/OERC, distribution and transmission licensees, STU, SLDC, nodal agency, open access customer, special energy meters and the three duration categories: long-term access (over 12 to 25 years), medium-term open access (over 3 months to 3 years) and short-term open access (up to 1 month). It also distinguishes 'allotted capacity' for long/medium-term customers from 'reserved capacity' for short-term customers, and defines imbalance and transmission system segment.
Chapter 2 (pp5–9) deals with connectivity. It allows consumers, generators and captive plants to seek connectivity under the OERC Distribution (Conditions of Supply) Code 2019 or Odisha Grid Code 2015, sets application procedures and non-refundable fees (with a 50% concession for RE generators), requires interconnection studies under CEA connectivity standards, provides for connection or tripartite agreements, and caps STU decision time at 60 days. Connectivity alone does not permit power interchange; testing and infirm power injection are allowed with SLDC permission before commercial operation.
Chapter 3 (pp10–11) sets eligibility and conditions for open access. Licensees, generating companies, captive plants and consumers may apply; consumers are eligible from 1 MW and above, with a lower route for captive users above 0.555 MW, and distribution franchisees may apply only as consumers. It excludes bankrupt applicants and those with more than two months' outstanding dues, requires special energy meters and (for 10 MW and above) RTUs, and says no augmentation shall be made solely to grant medium- or short-term open access.
Chapter 4 (pp12–37) is the application and approval code. It classifies applicants by system, location and duration; directs applications to the nodal agency; and contains Tables 1–3 setting the nodal agency, application fees, supporting documents, processing timelines, applicable charges and loss treatment for short-, medium- and long-term open access in different drawal/injection configurations. It then lays down procedures for long-term access (including bank guarantee, augmentation, agreements, extension and termination), medium-term open access (start-date limit, possible shorter grant, no renewal preference), and short-term open access (advance and day-ahead applications, formats ST-1 to ST-4, and electronic bidding when capacity is congested). It also provides for consents by STU/SLDC/distribution licensees with deemed consent for delay, summary rejection of defaulters, treatment of other eligible entities, and allotment priority, with distribution licensees highest.
Chapter 5 (pp39–43) sets out open access charges: transmission charges on an ATC/ALST formula; scheduling and system operation charges; wheeling charges on a wheeling-cost/ALSD formula; cross-subsidy surcharge using the National Tariff Policy formula; additional surcharge linked to stranded fixed costs; and standby charges for up to 42 days. Several charges are left to Commission orders or tariff orders; captive use and dedicated lines attract exemptions.
Chapter 6 (pp44–45) covers scheduling, metering, revision and losses: intra-State transactions are scheduled by SLDC under the State Grid Code, special energy meters are installed at the customer's cost with time-block metering, revisions follow IEGC/State Grid Code, and transmission and distribution losses are determined in tariff orders and payable in kind.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read OERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (9 pages) and for drafts on 21 Nov 2026. A document OERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of OERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.