F-201, Nirman Bhawan, New Delhi
Dated the 10th June, 2025
This is in continuation to the Ministry of Power Orders No. 23/12/2016 R&R dated 23.11.2021, 30.11.2021, 01.12.2022, 06.12.2022 and Order No.12/07/2023-RCM dated 29.05.2023 & 09.06.2023 regarding the waiver of Inter-State Transmission (ISTS) Charges on transmission of the electricity generated from Renewable Energy (RE) sources, Energy Storage Systems (ESS) and Green Hydrogen/ Green Ammonia.
a) ISTS charges waiver for Hydro PSP Projects for which the construction work has been awarded on or before 30th June 2028 shall be 100%.
b) ISTS charges waiver for co-located Battery Energy Storage System (BESS) Projects commissioned on or before 30th June, 2028 shall be 100%, if the power from such BESS projects is consumed outside of the state, where such BESS project is commissioned.
Provided that a BESS project shall be considered as co-located, if the BESS and RE projects are connected at the same ISTS sub-station.
c) There will not be any ISTS charges waiver for Hydro PSP Projects, for which the construction work awarded after 30th June, 2028 and for co-located BESS commissioned after 30th June, 2028.
d) For BESS projects which are not co-located, the ISTS charges waiver shall be as per the extant orders issued by the Ministry of Power and CERC Regulations.
10/6/25
(Sunil Kumar Sharma)
Director (RCM, NRE)
Tel: 011-2306 2914
To:
Secretary, Central Electricity Regulatory Commission, New Delhi
Copy to:
Copy for information to: