Registered No. WB/SC247 No.WB(PartI)/2007/SAR62 The Calcutta Gazette Extraordinary Published by Authority CAITRA 14] WEDNESDAY, APRIL 04, 2007 SAKA 1929
No. 34/WBERC Dated: 04.04.2007
In exercise of the powers conferred by subsection (1) and clause (zp) of subsection (2) of section 181 read with clause (h) of subsection (1) of section 86 of the Electricity Act, 2003 (36 of 2003) and all powers enabling it on that behalf and in supersession of the Notification No. 26/WBERC dated 12th January 2006 published in the Kolkata Gazette, Extraordinary on 16th January 2006, the West Bengal Electricity Regulatory Commission (WBERC) hereby makes the following Regulations.
I. These Regulations may be called the West Bengal Electricity Regulatory Commission (State Electricity Grid Code) Regulations, 2007 or in short WBEGC.
II. These Regulations shall come into force on the date of their publication in the official gazette unless otherwise stated in these Regulations and shall be concurrent within the area of jurisdiction of the West Bengal Electricity Regulatory Commission.
(xlii) “REF Relays” means Restricted Earth Fault Relay;
(xliii) “Regional Grid” means the entire synchronously connected ‘Regional Grid’ specified in the Grid Code and concerned to the territorial jurisdiction for which RLDC has been established;
(xliv) “Regulations” means the Regulations made under the Act;
(xlv) “RLDC” means Regional Load Despatch Centre concerned to the territorial jurisdiction under which State is being considered in accordance with subsection (1) of section 27 of the Act;
(xlvi) “RPC” means Regional Power Committee concerned to the Region under which State is being considered in accordance with the resolutions under clause (55) of section 2 of the Act;
(xlvii) “Rules” means the Rules made under the ‘Act’ by the State Government;
(xlviii) “ROR” means Run of the River;
(xlix) “Safety Regulations” means Regulations framed by Authority under section 53 of the Act or Indian Electricity Rules, 1956;
(l) “SLCF” or “State Level Coordination Forum” means a committee constituted by the Commission through modification with one member each from licensees and generating companies having installed capacity above 1000 MW connected to the STS where the convener and Chairman of the forum will be notified by the Commission during constitution of the forum;
(li) “SLDC” means SLDC as specified in Tariff Regulations;
(lii) “Spinning Reserve” means reserve margin of part loaded generating capacity that is synchronized to the State Grid and is ready to provide increased generation at short notice pursuant to despatch instruction or instantaneously in response to a frequency drop;
(liii) “Standing Committee” for transmission planning means a committee constituted by the CEA to discuss, review and finalize the proposals for ISTS and associated IntraState Transmission Systems;
(liv) “STS” or “State Transmission System” is consisting of IntraState Transmission System of the State comprising of transmission lines of owners of dedicated transmission lines, STU and Transmission Licensees in State grid;
(lv) “STU” or “State Transmission Utility” means STU as specified in Tariff Regulations;
(lvi) “State” means State of West Bengal;
(lvii) “State Government” means Government of West Bengal;
(lviii) “State Grid” to be mean the entire synchronously connected grid of power system of the State including the State Transmission System along with the connected grid of the Distribution Licensee with embedded generating stations, if any;
(lix) “Static VAR Compensator” or “SVC” means an electronically controlled facility designed for the purpose of generating or absorbing reactive power;
(lx) “Tariff Regulations” means the Regulations framed by the Commission under section 61 of the Act;
(lxi) “Transmission Licensee” means Transmission Licensee as specified in Tariff Regulations;
(lxii) “Transmission System” mean the transmission system as specified in the Tariff Regulations;
(lxiii) “User” means a person / agency using the IntraState Transmission System;
(lxiv) “VAR” means Reactive Power;
(lxv) WBSEB means WBSEB as specified in Tariff Regulations;
Words and expression used and not defined in any of the Regulations shall have the meanings as defined in the Act.
These Regulations are applicable to SLDC, ALDC and all the entities connected to the State Grid and under the purview of WBERC. In case of any inconsistency between the Grid Code and State Grid Code, the provision of Grid Code shall prevail.
In case of any inconsistency between Grid Standard and State Grid Code, the provision of Grid Standard shall prevail.
West Bengal’s State Power Sector is remarkable, due to presence and operation of multiple agencies and licensees in the State. At present ISGS like National Thermal Power Corporation (NTPC), National HydroPower Corporation (NHPC), Power Grid Corporation of India Limited (PGCIL) as CTU, STU, West Bengal Power Development Corporation Limited (WBPDCL), Licensees like WBSEB, CESC Limited (CESC), The Durgapur Projects Limited (DPL), DPSC Limited (DPSC) and Damodar Valley Corporation (DVC) are functioning in the State. In West Bengal SLDC monitors grid operations of the State grid and RLDC is monitoring the grid operation of the Regional Grid in accordance with Grid Code and as per agreed matter in the RPC in pursuance to subsection (4) of section 29 of the Act.
2/27/2017
The WBEGC lays down
The functions of STU, SLDC, entities and consumers shall be consistent with the provisions of the Act. As relevant to State Grid Code, their functions shall be as follows:
The SLDC shall be the apex body in the STS operation to ensure integrated operation of the State Grid in the following manner:
A distribution Licensee shall inform the STU and the SLDC about the contracts entered into for importing/exporting power from/to different sources and shall assist and co-ordinate with the SLDC in real time operation, control of the system and drawal/injection of reactive power from/to the STU. Distribution licensee shall also assist/follow instruction of the SLDC in scheduling its exchange from/to the STU.
Every transmission licensee or owner of a dedicated transmission line of the State grid shall comply with such technical standards of operation and maintenance of transmission line, as applicable to the Intra-State Transmission System, in accordance with this WBEGC, Grid Standards and Grid Code.
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
Untitled Document
( a) It shall maintain and operate the part of the ST which are licensed to transmission licensee and comply with directions of SLD C.
( b) It shall provide nondiscriminatory open access in pursuance to open access to its transmission system subject to availability of adequate transmission facilities for use by any licensee or generating company or open access customer on payment of the charges as determined by the Commission.
( v) Generating Station:
The generating stations connected to the STU and evacuating their generation through the STU, shall inform the STU and the SLD C about the contracts entered into with different parties for exporting power along with its schedule. They should follow the instruction of the SLD C and assist the SLD C in the real time operation and control of the system and scheduling of generation.
( vi) Free Governor Action:
( a) All units of generating stations having capacity above 50 MW shall keep their governor under free governor operations as per WBEGC with effect from the date to be separately notified by the Commission.
( b) If any entity seeks an exemption from the above requirement, it shall file a petition justifying the same in advance to the Commission, which may, at its sole discretion, allow the same.
( c) The gas turbines / CCGT and nuclear power stations shall be exempted from regulations 4.2.5, 4.2.6, 4.2.7 and 4.2.8 till the Commission reviews the situation.
In accordance with clause (b) of subsection (2) of section 39 of the Electricity Act 2003, the STU shall discharge all functions of planning and coordination relating to STS with CTU, State Government, CEA, RPC and other related organizations, who shall utilize the STS for evacuation or injection or drawal of power.
Power Supply Planning starts with a forecast of anticipated future load requirements of both demand and energy covering a particular period of time. The primary responsibility of load forecasting rests with the distribution licensees, who shall follow the respective perspective plans as per Tariff Regulations. The overall peak and energy demand projections for such forecasts shall take into account the growth trend of the last five years with due importance and weightage being given to growth in sale of electricity for different classes of consumers in the said period. The proposed services for connected load of 1 MW and above shall also be separately considered for two categories viz. firm load in pipeline where investment in infrastructure has already taken place, and infirm load where investment decision is in the planning stage. This input shall be obtained from the distribution licensee(s) concerned. Details for firm load including the degree of firmness in terms of financial tie up and different agreement signing may be recorded for proper assessment of the possibility of additions of the demand in the system. Consideration of infirm load for overall load forecast shall be based on the past experience of maturity rate for last five years of such forecasted infirm load into reality. The load forecast shall be consolidated transmission sub station wise (132 kV and above). The periodicity of the survey shall preferably synchronize with the studies conducted by CEA. The STU may conduct the load survey at shorter intervals of time if the trend of growth rate shows an increase in two consecutive years. The distribution entities shall furnish the required data to the STU as required by the STU. The STU shall integrate the load forecasts and determine a relatively longterm (10 years) load forecast for the State. The resulting overall load forecast including its spatial distribution should be one of the basis for expansion of generation and transmission and distribution system. The planning process shall consider an extended study period of 10 years beyond the base period of 10 years. This load forecast along with a note on such forecasting methodology may be submitted to the Commission for approval before any planning on the basis of such forecast.
This load forecast along with demand growth trend of different Districts and Municipal Corporations are to be provided in the Website of the STU.
The technical component of transmission and distribution losses shall be estimated based on sample studies, measurements, load flow studies etc. The STU shall work out on the basis of projected loads and losses of the system, the net energy requirement and peak load requirement at generation end. The installed capacity, peak availability, surplus or deficit both in demand and in availability of energy at the State level shall also be worked out by the STU. The demand forecasts as per Regulation 2.2.1 shall be used to determine the capacity of generation, transmission and distribution systems and energy forecast along with the load duration curve shall be used to determine the type of generation facilities required. The generation criteria based on operational parameter as per Tariff Regulations shall be applied for arriving at the additional generation capacity requirement. While calculating the availability for existing units, the trend of generation shall be considered and for projects under construction, 80% availability shall be considered. For any proposed hydrogenerating station, generating capacity shall be considered on a case specific basis after considering the results of requisite detailed investigation studies.
The STU shall workout the requirement of additional transmission capacity after taking into account, the existing capacity, future requirement of power evacuation from new power generating projects inclusive of CPPs, power generating projects under construction in State, and share allocation of the State from ISGS. Any supply from generating stations of temporary nature shall not be considered. In addition, the power procurement plan of different distribution licensee of the State pursuant to the Tariff Regulations and power to be wheeled by different Open Access Customers in LongTerm Open Access as per Open Access Regulations shall also be taken into account for the purpose of overall planning. Consumers having open access of 1 MW and above
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
2/27/2017 under ShortTerm Open Access shall also be contacted to assess their likely demand from the State Grid and degree of firmness of such demand to meet its regular supply as consumer on expiry of such ShortTerm Open Access or backup or standby power as specified in Open Access Regulations. Information from such consumer having open access shall be collected in writing by the Distribution Licensee with whose distribution system the premises of consumer is connected when the Distribution Licensee prepares its perspective plan in pursuance of regulation 2.5.5 of Tariff Regulations. In the case of absence of any response from such a consumer, it shall be treated that such a consumer has no requirement of back up or standby power or any power against regular supply in consumer mode on expiry of the terms of open access during the period of perspective plan for which information is sought for. Such future demand for standby or backup power or regular supply for such consumer having open access shall only be taken into consideration for the forecast demand only after execution of agreement between the licensee and such consumer. The STU shall also identify suitable locations near which big substation required to be installed. Regarding transmission corridor availability, the norms as per Tariff Regulations shall be considered and for adequate redundancy for secure and stable grid operation of the STS, 30% extra capacity is to be created than the required capacity.
The STU shall carry out planning process from time to time as per the requirement for identification of major IntraState Transmission System, which shall fit in with the perspective plan developed by State Government. While planning, the following shall be considered in addition to the data of authentic nature collected from and in consultation with various generating stations, licensees, State Government, etc.
The plan shall indicate and include a chapter on proposed STS scheme open for private investment by the STU, based on which the entrepreneurs can formulate primary investment decisions.
The planning report shall indicate the action taken to fulfill the additional requirements and actual progress made on new schemes. These reports will be available to any interested party for making investment decision / connection to the STS.
As voltage management plays an important role in the STS, special attention shall be accorded to planning of VAR compensation in the network so that voltage instability does not occur and line can transfer designed power with designed operating voltage range.
Based on the load forecast and the additional generation required for 10 years period the STU shall develop a longterm plan for STS considering generation capacity addition programme and expansion in distribution system.
Medium Term Planning: A 5 year rolling plan shall also be finalized by the STU every year for requirement arising out of expansion of the STS, generation and distribution systems to meet the future demand and to ensure quality supply to consumers. The rolling plan shall take into account the previous years’ achievements.
The planning criteria are based on the security philosophy on which the STS is planned. The guidelines in general are detailed for distribution, transmission and generation are to be as follow:
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 6/30
Untitled Document
v) Voltage in the distribution system shall be controlled and maintained at statutory levels. Voltages at the consumer terminals shall be maintained as specified in the Safety Regulations.
vi) The level of harmonics generated by consumer’s equipment is to be controlled as per the limits specified in the grid connectivity standards specified by CEA.
vii) Voltage flickers caused by consumers’ loads shall have to be controlled within the permissible limits as per Grid Standards.
i) The permissible voltage excursions for transmission and sub transmission system during the steady state operation is + 5% for 400 KV and 220 KV level and + 10% for 132 KV and below. This limit may be exceeded only during the outages of 400 KV lines and in such cases, use of dynamic VAR source may be considered if necessary.
ii) The standard fault rating of switchgear at 132 KV is 31.5 KA and at 220 KV and 400 KV is 40 KA.
iii) The capacity of any single sub station shall not normally exceed 1000 MVA for 400 KV, 500 MVA for 220 KV and 250 MVA for 132 KV.
iv) Size and number of EHT/HT transformers in a substation of a transmission system shall be planned in such a way that in the event of outage of any single unit, the remaining unit(s) would still supply the load for 80% time of the day.
v) The line loading limits shall be based on the thermal / surge impedance loading depending on the line sections and VAR support provided.
a) The general policies are as given below:
i) As a general rule, the STS shall be capable of withstanding and be secured against the following contingency outages without necessitating load shedding (except for radial line) or rescheduling of generation during steady conditions in operation:
ii) The above contingencies shall be considered assuming a precontingency system depletion (planned outage) of another 220 KV D/C line or 400 KV S/C line in another corridor and not emanating from the same substation & during the period other than the peak.
iii) All the generating units of a generating station may operate within their reactive capability curves and the network voltage profile shall also be maintained within voltage limits specified.
b) The STS shall be capable of withstanding the loss of the most severe single system infeed transmission or generation.
c) Any one of these events defined above shall not cause:
d) In all substations (132 KV and above), at least two transformers shall be provided.
e) The STU shall carry out planning studies for reactive power compensation of generating stations under WBERC purview including reactive power compensation required at their switchyard.
The system shall be designed to maintain synchronism and system integrity under the following disturbances:
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
2/27/2017 Untitled Document
i) Outage of one of the largest size generating unit. For this the generating companies should get clearance from STU regarding the choice of unit size if the capacity of unit exceeds 500 MW.
ii) A single line to ground fault on a 400 KV line, single pole opening of the faulted phase (5 cycles) with unsuccessful reclosure (dead time 1 sec) followed by three pole opening (5 cycles) of the faulted line.
iii) A permanent three phase fault with duration of 8 cycles in 220 KV and 132 KV systems assuming three poles opening.
Connectivity conditions specify the minimum technical and design criteria which shall be complied with by any agency connected to, or seeking connection to the STS to transmit electrical energy either way from/to the STS. The STU shall ensure compliance by any agency with the above criteria as a pre-requisite for the establishment of an agreed connection.
Prior to an agency being connected to the STS, all necessary conditions outlined in the WBEGC and other Regulations specified by CEA in addition to other mutually agreed requirements to be complied with, must be fulfilled by the agency. Any agency seeking to establish new or modified arrangement of connection to STS for use of it, shall submit an application on specified format to the STU along with the following details:
The STU shall normally make a formal offer to the agency within one month from the date of receipt of all details along with the proposed changes, if any. The offer shall stipulate and take into account any works required for the extension or reinforcement of the transmission system to satisfy the requirements of the connection application and for obtaining statutory clearances, way leaves as necessary. The agency shall give its consent and submit to STU within a fortnight thereafter.
Final decisions on applications for connections to STU network shall be provided by the STU within 45 days from the date of submission of consent to it by the agency.
If the nature and complexity of the proposal is such that the specified time limit for making the offer is not adequate, the STU shall make a preliminary offer within the specified time limit indicating the extent of further time required with the consent of the WBERC for more detailed examination of the issues.
The STU shall make a revised offer, upon request by any User, if necessitated by changes in data earlier furnished by the User.
All offers (other than preliminary offers) including revised offers shall remain valid for 60 days of issue of the offer. In the event of the offer becoming invalid or not being accepted by any User within the validity period, no further action shall be taken by the STU on the connection applications. In the offer, details of the requirements and procedures for connection to the STS and the resulting Connection Agreement with the agency shall be set out.
Upon compliance, STU shall notify the agency that it can be connected to the STS. However in case of the existing connections between STS network and entities, the WBERC may allow at its discretion relaxation up to one year in respect of connection agreements and the present agreements/ present practice as followed may continue in order to avoid the whole process of re-negotiation with the existing entities.
Prior to providing any connectivity to a consumer with the STS, the licensee shall take approval of the STU and the SLDC after meeting all technical and commercial requirements of the STU and the SLDC.
A connection agreement shall include (but may not be limited to), as appropriate, within its terms and conditions, the following:
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 8/30
2/27/2017 Untitled Document
v) the metering arrangements;
vi) the general procedure, guidelines, etc. on protection and telemetry;
vii) the procedures necessary for site access, site operational activities and maintenance standard for equipment of Licensee at the premises of the User and vice-versa;
viii) commitments to provide data requirement as per Annexure - I.
(i) For Generating Station, the switchyard voltage of connection point may be 400 / 220 / 132 KV or as agreed with the Licensee with whose network the connection is to be effected. Unless specifically agreed with the Licensee with whose network the connection to be effected, the connection point shall be the outgoing feeder gantry of generating station switchyard. All the terminals, communication, protection and metering equipment owned by the generating company within the perimeter of its site shall be maintained by it. From the outgoing feeder gantry onwards, all electrical equipment shall be maintained by the Licensee or the owner of the dedicated transmission lines with whose network the connection is to be effected.
(ii) For Distribution Licensee, the voltage of connection point may be as agreed with Generating Station or the Licensee with whose network the connection is to be effected but the same cannot be below 6 KV. The connection point shall be the outgoing feeder gantry of Generating Station switchyard or the sub-station in case of the Licensee. However, in case of connection with dedicated transmission lines, it may be the point as agreed by the Distribution Licensee and the owner of the dedicated transmission line. All the terminal, communication, protection and metering equipment within the premises of the sub-station shall be maintained by owner of the substation. From the outgoing feeder gantry onwards, all electrical equipment shall be maintained by the respective distribution entity.
(iii) For the ISTS of the Regional Grid, the connection point, protection scheme, metering scheme, metering point and the voltage shall be in accordance with the mutual agreement between owners of two connecting systems, until and unless they are specified by CEA in its Regulations under the Act.
(iv) For CPPs and EHT/HT Consumers, voltage may be 220/132/66/33 KV or as agreed with Licensee with whose network the connection is to be effected. Sub-stations, owned by CPPs and EHT / HT Consumers, shall be maintained by them or as mentioned in the connection agreement. The connection point shall be the feeder gantry on their premises in case of EHT / HT consumers and at Licensee’s gantry in case of CPPs.
Instantaneous values of system frequency of the State grid and voltage are subject to variation from their nominal value as provided in these regulations. All agencies shall ensure that their plants and apparatuses requiring service from / to the STS are of such design and construction that satisfactory operation shall not be prevented by such variation.
Rated frequency of the system shall be 50.0 Hz and shall normally be controlled within the limits as specified in Grid Code.
The variation of voltage may not be more than the voltage range specified in the IE Rules as may be specified by CEA in its Regulations under the Act. The agency engaged in sub-transmission and distribution shall not depend upon the STS for reactive support when connected. To avoid need of exchange of reactive power to/from the STS, the agency shall estimate and provide the required reactive compensation in its sub-transmission and distribution network for maintaining a cumulative power factor of 0.85, to 0.95 in order to meet its full reactive power requirement, unless specifically agreed to with the STU.
i) All EHV outdoor switchyard equipment shall comply with standard of Bureau of Indian Standards (BIS) / International Electro Technical Commission (IEC) / prevailing code of practice.
ii) All equipment shall be designed, manufactured and tested and certified in accordance with the quality assurance requirements as per IEC / BIS standards.
iii) Each connection between an agency and STS shall be controlled by a circuit breaker capable of interrupting, at the connection point, the short circuit as advised by the STU in the specific connection agreement.
i) The total fault clearance time, for faults on agency's equipment directly connected to STS and for faults on STS connected to agency's equipment, from fault inception to the circuit breaker arc extinction, shall not be more than –
a) 100 milli seconds (ms) for 400 KV;
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 9/30
Untitled Document
b) 160 milli seconds (ms) for 220 KV & 132 KV;
c) 160/400 milli seconds (1st /2nd Zone).
i) Protection systems are required to be provided by all entities connected to the STS and as specified by STU. These are required to isolate the faulty equipments and protect the other components against all types of faults, internal / external to them, within the specified fault clearance time with reliability, selectivity and sensitivity. Protective relay settings shall not be altered, or protection bypassed and / or disconnected, without consultation and agreement of all the affected users. If protection is bypassed and / or disconnected by agreement, then the cause must be rectified and protection shall be restored to normal condition as quickly as possible. If agreement is not reached, the electrical equipment, in question, shall be removed from service forthwith in a case where it affects the security of the system. Relay setting coordination shall be done by STU. The STU shall arrange periodic meetings of the entities to discuss coordination of protection. The STU shall investigate into any malfunctioning of protection or other unsatisfactory protection issues. The concerned Licensees shall take prompt action to correct any protection malfunction or issue as discussed and agreed to in these periodical meetings.
In case of installation of any device, which necessitates modification / replacement of existing protection relays / scheme in the network, such modification / replacement shall be carried out by owner of respective part of the network. All agencies connected to STS shall provide protection systems as specified in the connection agreement. Relay setting coordination shall be done at State level by STU.
ii) Generating units and generating stations requirement:
iii) Transmission Line Requirements:
Every EHT line taking off from a generating station or a substation shall have distance protection and back up protection as mentioned below. The STU shall notify users of any changes in its policy on protection from time to time.
(b) 220 kV Line:
(c) 132 kV Lines:
For cable feeders cable differential / suitable fast protection to be used.
(d) General:
(iv) Distribution Line Requirements:
All 33KV and 11/6 kV lines at connection points shall be provided with a minimum of over current and earth fault protection with or without directional features as given below:
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
2/27/2017
Directional time lag over current and earth fault relays;
For long feeders or transformer feeders, the relays should incorporate a high set instantaneous element.
All windings of auto transformers and power transformers of EHV class shall be protected by differential relays and REF relays. In addition there shall be back up time lag over current and earth fault protection. For parallel operation such back up protection shall have directional feature. For protection against heavy short circuits, the over current relays should incorporate a high set instantaneous element. In addition to electrical protection, gas operated relays, winding temperature protection and oil temperature protection shall be provided. For transformers of HV class, differential protection shall be provided for 10 MVA and above along with back up time lag over current and earth fault protection (with directional feature for parallel operations). Transformers 2.5 MVA and above and less than 10 MVA shall be protected by time lag over current, earth fault and instantaneous REF relays. In addition, all transformers 2.5 MVA and above shall be provided with gas-operated relays, winding temperature and oil temperature protection.
All users shall provide suitable bus bar protection for substation bus bars in all 400 kV, 220 kV and 132 kV class substations or generating stations. Adequate precautions shall be taken and protection shall be provided against lightning and fire hazards to all apparatus of the users conforming to relevant Indian Standard Specification and / or provisions as specified in Safety Regulations.
i) The agency who has to provide, operate and maintain the metering arrangements at various locations shall be specified by the STU in the connection agreement.
The commercial metering is designed to ensure the following:
(a) MW, MWH and MVARH flow are to be measured at interconnection points, power transformer locations, distribution substation end and consumption by HT / EHT consumers. The information are to be provided in the specified formats. Each metering point associated with determination of energy exported or imported shall be provided with both main and check meter or as per the agreement between the STU and the entities. Minimum standards of accuracy of such meter shall be of class 0.2 or as specified by the STU. All current transformers and voltage transformers used in conjunction with commercial (tariff) metering shall conform to the relevant BIS or standard of IEC. These shall be of accuracy class having better accuracy than 0.5 and of suitable rating to cater to the meter and lead wire burden. Voltage supply to the metering shall be assured with necessary voltage selection schemes. Voltage failure relays shall be provided which shall initiate alarms on loss of one or more phases of the voltage supply to any meter. Meters shall be tested and calibrated by a neutral agency in a frequency as specified by CEA or in absence of such at least once in a year or such as mutually agreed between the STU and the entities according to the guidelines in the standards / supplier's recommendations. Records of meter calibration test shall be maintained for future reference.
(b) Wherever a meter becomes defective, consumption recorded by the check meter shall be referred for a mutually agreed period. The details of malfunctioning along with date, time and other data including load survey data shall be retrieved from the main meter. The exact nature of malfunctioning shall be brought out after analyzing the data so retrieved and the consumption / losses recorded by the main meter shall be assessed accordingly.
(c) If the main as well as the check metering systems become defective, the assessment of energy consumption for the outage period shall be done by the concerned parties on mutually agreed basis.
(d) A procedure shall be drawn up between the STU and the entities covering summation, collection, processing tariff meter readings at various connection sites. This may be revised from time to time as needed.
(e) The ownership and responsibility of maintaining and testing of meters shall be mutually agreed between the entities and the STU.
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
2/27/2017 Untitled Document
(f) Any disputes relating to inter-entity metering between the STU / Transmission Licensee and Generating Company / Distributing Licensee / Open Access Users / Transmission Licensee shall be settled in accordance with the procedures stipulated under relevant Power Purchase Agreement / Connection Agreement as the case may be. In case of unresolved dispute, the matter may be referred to WBERC for adjudication and reference for arbitrations.
(a) The Generating Company shall install operational metering to STU's specification so as to provide operational information for both real time and recording purposes in relation to each generating unit at each power station in respect of bus voltage frequency, MW, MVAR and any other additional data as required by STU.
(b) All current transformers and voltage transformers used in conjunction with operational metering shall conform to the relevant standards and shall have accuracy better than accuracy class 0.5 and of suitable ratings to cater to the meter and lead wire burden.
(c) Meters shall be calibrated so as to achieve overall accuracy of operational metering in the limits as specified by the STU.
(d) Records of calibration shall be maintained for reference and shall be made available to the STU on request.
(e) Generating companies shall furnish recorded data of all electric measurements and events recorded by the operational metering to the SLDC as requested by them.
(f) The STU shall be responsible to formulate the metering procedure and implement it with other users.
Users shall provide the STU with data for this section as specified in the formats under Annexure – II.
The following communication facilities as relevant and applicable to the user shall be decided and finalized at the initial stage and incorporated in the Connectivity Agreement:
(a) Audio Communication:
Reliable and efficient audio communication system shall be provided to the SLDC / ALDC to facilitate supervision / control / direction of the State Grid under both normal and abnormal operating conditions.
(b) Data Communication:
Real time telemetered data through Supervisory Control And Data Acquisition System (SCADA) or Data Acquisition System (DAS) and off-line data for State Grid such as flow, voltage, States of switches, transformer taps, etc. through suitable and reliable data communication facilities so as to facilitate efficient and uninterrupted data exchange with SLDC / ALDC under both normal and abnormal operating conditions.
(c) Data Entry Terminals:
Data entry facilities as advised by SLDC for exchange of information between SLDC and entities.
Recording instruments such as DAS / Disturbance Recorder / Event Logger / Fault Locator (including time synchronization equipment) shall be provided in the STS for recording of dynamic performance of the STS. Agencies shall provide all the requisite recording instruments as specified in the connection agreement according to the agreed time schedule.
3.7.1 Reactive power compensation and / or other facilities, should be provided by the STU or Transmission Licensees, etc. For agencies engaged in distributing electricity reactive power compensation shall be provided as far as possible in the low voltage systems close to the load points, thereby avoiding the need for exchange of reactive power to / from STS and to maintain STS voltage within the specified range.
3.7.2 Fixed line reactors may be provided to control temporary over voltage within the limits as set out in connection agreements.
3.7.3 The addition of reactive compensation to be provided by the agency (including generating station) shall be indicated by the STU in the Connection Agreement for implementation on the basis of planning studies.
The STU, the users, and the entities shall be responsible for safety as indicated in Site Responsibility Schedules for each connection point.
i) A Site Responsibility Schedule shall be produced by the parties as agreed in the connection agreement detailing the ownership, control, maintenance and operational responsibilities of each, before execution of the project or connection including safety responsibilities. For connection to the STS, a
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 12/30
2/27/2017 schedule shall be prepared by the agency pursuant to the relevant connection agreement which shall mention, for each item of plant and apparatus at the connection point, the following:
ii) The format, principles and basic procedures to be used in the preparation of Site Responsibility Schedules shall be formulated by the STU in line with the Regulation specified by the CEA for technical standards for connection to grid and shall be provided to each agency / entities for compliance.
iii) All agencies connected to or planning to connect to the STS shall ensure providing of Remote Transmitting Unit (RTU) and other communication equipments, as specified by the SLDC, for sending realtime data to the SLDC at least before date of commercial operation of the generating stations or substation / line being connected to the STS.
i) Single Line Diagram shall be furnished to the SLDC for each connection point with transmission licensee by the connected agencies in concurrence with Transmission Licensee. These diagrams shall include all HV connected equipment and the connections to all external circuits and incorporate numbering, nomenclature and labelling, etc., The diagram shall provide an accurate record of the layout and circuit connections, rating, numbering and nomenclature of HV apparatus and related plant.
ii) Whenever any equipment is proposed to be changed, the concerned agency shall intimate the desired changes to the Licensee with whom he is connected and to the SLDC. When the changes are implemented, changed Single Line Diagram shall be circulated by the agency to the SLDC and the STU.
i) Site Common Drawing shall be prepared for each connection point and shall include site layout, electrical layout details of protection and common services drawings. The detailed drawings for the portion each of the agencies concerned at each connection point shall be prepared individually and exchanged between agencies and STU.
ii) The detailed drawings for the portion of the agencies and the STU at each connection point shall be prepared individually and copies shall be handed over to other party and the STU.
iii) If any change in the drawing is found necessary, either by agencies or the STU, the details shall be exchanged between agency and the STU as soon as possible.
The connection agreement shall also indicate the procedures necessary for site access, site operational activities and maintenance standards for the STU equipment at the premises of the users and vice versa.
The STU shall submit annually to WBERC by 30th September each year a schedule of transmission assets, which constitute the State grid as on 31st March of that year indicating ownership on which the SLDC has operational control and responsibility.
4.1.1 An integrated operation of the State grid is aimed at achievement of overall operational economy and reliability of the State Grid.
4.1.2 Overall real time operation of the State grid shall be supervised by the SLDC. The roles of the SLDC and the STU shall be in accordance with WBEGC.
4.1.3 Such Distribution Licensee shall establish at least one ALDC to monitor grid operation of its distribution system and to make coordination with the SLDC.
4.1.4 All State entities shall comply with the operation guidelines specified hereinafter and coordinate with each other, for deriving maximum benefits from the integrated operation and for equitable sharing of obligations.
4.1.5 A set of detailed internal operating procedures for the State Grid shall be developed and maintained by the SLDC in consultation with the entities and the same shall be consistent with WBEGC.
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 13/30
Untitled Document
The control rooms of the SLDC, ALDC, generating stations, and EHV substations and any other control centers of all the entities shall be manned round the clock by qualified personnel with adequate training.
All entities in the State grid shall endeavor to operate their respective State Grids and generating stations in synchronism with each other at all times, such that the entire State grid operates as one synchronized system.
(i) No part of the State grid shall be deliberately isolated from the rest of the State Grid, except -
(ii) Such isolation due to any of the above mentioned causes under (i) shall be followed by complete restoration of synchronized grid as soon as the conditions again permit. The restoration process shall be supervised by the SLDC, as per operating procedures separately formulated.
No important element of the State grid shall be deliberately opened or removed from service at any time, except when specifically instructed by the SLDC or with specific and prior clearance of the SLDC. The list of such important grid elements on which the above stipulations apply shall be prepared and be available at the SLDC. If any opening / removal of any important element of the grid under an emergency situation as mentioned in 4.2.2 (i) & (ii) takes place, the same shall be communicated to the SLDC at the earliest possible time after the event.
Any tripping, whether manual or automatic, of any of the above elements of State grid shall be precisely intimated by the concerned entities to the SLDC as soon as possible, preferably within ten minutes of the event. The reason (to the extent determined) and the likely time of restoration shall also be intimated. All reasonable attempts shall be made for the elements' restoration as soon as possible. Similarly any incident of outage significantly affecting the system of any agency will be intimated to the agency by SLDC within the above time.
All generating units, which are synchronized with the grid, irrespective of their ownership, type and size, shall have their governors in normal operation at all times. If any generator of over 50 MW rating is required to be operated without its governor in normal operation, the SLDC shall be immediately advised about the reason and duration of such operation. All governors shall have a droop between 3% and 6%.
Facilities available with load limiters, Automatic Turbine Run up System (ATRS), turbine supervisory control, coordinated control system, etc., shall not be used to suppress the normal governor action. No dead bands and / or time delays shall be deliberately introduced.
All generating units, operating at or up to 100% at their MCR shall normally be capable of (and shall not in any way be prevented from) instantaneously picking up five percent (5%) extra load as soon as possible but preferably within five (5) minutes when frequency falls due to a system contingency. However, for existing generating units (generating units of COD up to 31.12.2005), these should be within the technical limits stipulated by the manufacturer. The generating units operating at above 100% of their effective MCR shall not be prevented from going at least up to 105% of their effective MCR when frequency falls suddenly. After an increase in generation as above, a generating unit may slide back to the original level at a rate of about 1% per minute, in case continued operation at the increased level is not sustainable. Any generating unit (synchronized with the State grid) of over fifty (50) MW size, not complying with the above requirement, shall be kept in operation only after obtaining the permission of the SLDC. However, the entity can make up the corresponding shortfall in spinning reserve by maintaining an extra spinning reserve on the other generating units of the entity.
The recommended rate for changing the governor setting, i.e. supplementary control for increasing or decreasing the generation sent out for all generating units, irrespective of their types and sizes, would be 1% per minute or as per manufacturer's limits. However, if frequency falls below 49.5 Hz, all partly loaded generating units shall pick up additional load at a faster rate, according to their respective capability.
Except under an emergency, or when there is need to prevent an imminent damage to personnel and equipment, no entity shall suddenly reduce its generating unit output by more than 100 MW without prior intimation to and consent of the SLDC, particularly when frequency is falling or is below 49.0 Hz. Similarly, no entity shall cause sudden increase in its load by more than 100 MW without prior intimation to and consent of the SLDC.
All generating units shall normally have their AVRs in operation, with appropriate settings. In particular, if a generating unit above 50 MW size is required to be operated without its AVR in service, the SLDC shall be immediately intimated about the reason and duration, and its permission obtained. Power System Stabilizer (PSS) in AVRs of generating units (wherever provided), shall be got properly tuned by the respective generating unit owner as per plan prepared for the purpose by the SLCF from time to time. The STU will be allowed to carry out checking of PSS and further tuning it, wherever considered necessary.
Provision of protections and relay settings shall be coordinated periodically throughout the State grid, as per a plan to be separately finalized by the STU in coordination with all entities and RPC.
All entities shall ensure that the grid frequency always remains within the 49.0 - 50.5 Hz band.
All entities shall provide automatic under-frequency load shedding in their respective systems, to arrest frequency decline that could result in a collapse / disintegration of the grid, as per the plan separately finalized by the SLCF, and shall ensure its effective application to prevent cascaded tripping of generating units in case of any contingency. All entities shall ensure that the under-frequency load shedding / islanding schemes are functional and no under-frequency relay is by-passed or removed without prior consent of the SLDC.
All entities shall also facilitate identification, installation and commission of system protection schemes (including inter-tripping and run-back) in the State’s State Grid to protect against situations such as voltage collapse and cascading. Such schemes would be finalized by the concerned SLCF forum, and shall be kept in service. The SLDC shall be promptly informed in case any of these is taken out of service.
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
2/27/2017 Untitled Document
Procedures shall be developed to recover from partial / total collapse of the grid and periodically updated in accordance with the regulation 4.8. These procedures shall be followed by all the entities to ensure consistent, reliable and quick restoration for which the SLDC shall coordinate with all entities.
Each entity shall provide adequate and reliable communication facility internally and with the SLDC and with other entities, if required, to ensure exchange of data / information necessary to maintain reliability and security of the grid. Wherever possible, redundancy and alternate path shall be maintained for communication along important routes, e.g. SLDCs to ALDCs and / or generating stations.
The entities shall furnish on request information / data including disturbance recorder / sequential event recorder output etc., to the SLDC for purpose of analysis of any grid disturbance / event. No State entity shall block any data/ information required by the SLDC for maintaining reliability and security of the grid and for analysis of an event.
All entities shall make all possible efforts to ensure that the grid voltage always remains within the following operating range as specified for different equipment.
| Nominal Voltage in (kV rms) | Maximum | Minimum |
|---|---|---|
| 400 | 420 | 380 |
| 220 | 231 | 209 |
| 132 | 145 | 119 |
| 66 | 72 | 60 |
The SLDC shall develop methodologies / mechanisms for daily / weekly / monthly / yearly demand estimation (MW, MVAR and MWh) mainly based on the data furnished by the Distribution Licensees for operational purposes. The data for the estimation shall also include load shedding, power cuts etc. The SLDC shall also maintain historical database for demand estimation, which shall also take into account weather forecast appropriately. The demand estimates are to enable the SLDC to conduct system studies for operational planning purposes. While the demand estimates for operational purposes is to be done on a daily, weekly, monthly basis initially, as deemed fit by the SLDC and within one year, appropriate mechanism and facilities at the SLDC shall be created at the earliest to facilitate online estimation for daily operational use.
The entities shall endeavor to restrict their net drawal from the grid to within their respective drawal schedules whenever the system frequency is below 49.5 Hz. When the frequency falls below 49.0 Hz., requisite load shedding (manual) shall be carried out to curtail the over drawal. Such load shedding and also automatic UFR operation shall be pre planned for each level of under frequency as per the guidelines as specified in Regulations of the Commission or stipulated in any of the Commission’s order, if any and where applicable.
Further, in the case of certain contingencies and / or threat to system security, the SLDC may direct the sub stations/distribution licensee to decrease its drawal by a certain quantum. Such directions shall immediately be acted upon.
Each entity shall make such arrangements that will enable manual demand disconnection to take place, as instructed by the SLDC under normal and / or contingent conditions.
The measures taken to reduce the entities' drawal from the State grid shall not be withdrawn as long as the frequency / voltage remains at a low level, unless specifically permitted by the SLDC / ALDC. If required, necessary rescheduling of drawal for the entities shall be done by SLDC.
In the case of shortage of power availability with respect to demand, the ALDC shall resort to shedding the load of different feeders on economic principle till the Commission specifies any policy in this matter through notification.
i) The SLDC / ALDC will monitor, regulate and submit report to the Commission as per order under section 23 of the Act.
ii) In the case of shortage of supply, the Commission in consultation with the SLDC / ALDC, may impose restriction on any consumer or class of consumers or any feeder in drawal of power, including zero drawal, for any time / duration of the day for a period as may be decided by the Commission.
A weekly report shall be submitted by the SLDC to the Commission, the STU, licensees and generating companies of the State and shall cover the performance of the State grid for the previous week. The weekly report shall contain the following:
(i) Frequency profile: Maximum and Minimum frequency recorded daily on 15 minutes time block basis and also average frequency during peak, off-peak and normal period;
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 15/30
Untitled Document
(ii) Voltage profile: The Voltage profile of 132 KV and above substations;
(iii) Major Generation and Transmission outages;
(iv) Transmission constraints;
(v) Daily demand profile consisting of:
(vi) Daily Generation Performance Status:
Generating station wise daily schedule for availability declared, actual generation, non-drawal by the system (if any), reason for non-drawal, reason for less generation;
(vii) Instances of persistent / significant non-compliance of WBEGC;
(viii) Monthly load duration curve with date;
(ix) Demand and load for the days of month of maximum demand and minimum demand.
The SLDC shall also prepare a quarterly report, which shall bring out the system constraints, reasons for not meeting the requirements, if any, of security standards and quality of service, along with details of various actions taken by different agencies, and the agencies responsible for causing the constraints. The convenor of the SLCF shall arrange adding of the monthly meeting of the Forum(s).
Exchange of information, in relation to operations and / or events on the total State Grid, which have had or will have an effect on the State Grid or Inter State links or the system of an entity, is extremely important for the purpose of maintaining stability of the State Grid.
The operational liaison generally relates to notifying of what is expected to happen or what has happened and does not relate to the reasons of the same. The operational liaison function is a mandatory built-in hierarchical function of the SLDC and entities, to facilitate quick transfer of information to operational staff. It will correlate the required inputs for optimization of decision-making and actions.
(i) Operations and events on the State grid:
Before any operation is carried out on the State Grid, the SLDC shall inform each entity, whose system may, or will, experience an operational effect, and give details of the operation to be carried out. Immediately following an event in the State Grid, the SLDC shall inform each entity, whose system may, or will, experience an operational effect following the event and give details of what has happened in the event but not the reasons why.
(ii) Operations and events on an entity's system:
Before any Operation is carried out on an entity system, the entity shall inform the SLDC, in case the State grid may, or will, experience an operational effect, and give details of the operation to be carried out. Immediately following an event on an entity system, the entity shall inform the SLDC, in case the State grid may, or will, experience an operational effect following the event, and give details of what has happened in the event but not the reasons why.
The procedure for preparation of outage schedules for the elements of the State Grid in a coordinated and optimal manner keeping in view the State Grid operating conditions and the balance of generation and demand in optimal level, requires following activities.
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
2/27/2017 Untitled Document
(iv) Optimization of the transmission outages of the elements of the State grid without adversely affecting the grid operation taking into account the generation outage schedule, outages of constituent systems and expected level of maintenance of system security standards on such transmission outages.
(i) The STU, generating companies and the distribution licensees with generation shall provide the SLDC with their respective proposed outage programs in writing for the next financial year by 1st August each year. These shall contain identification of each generating unit / line / interconnecting transformer, the preferred date for each outage and its duration and where there is flexibility, the earliest start date and latest finishing date.
(ii) The SLDC shall then come out with a draft outage programme for the next financial year by 15th November each year for the State grid taking into account the available resources in an optimal manner and the need to maintain security standards. This will be done after carrying out necessary system studies and, if necessary, the outage programmes shall be rescheduled. Adequate balance between generation and load shall be ensured while finalizing outage programme.
(iii) The SLDC shall inform the RPC Secretariat of its proposed outages in writing by 30th November for each financial year.
(iv) The RPC secretariat shall then come out with an outage programme for the next financial year for the Regional Grid as per Grid Code.
(v) The SLDC shall interact with all users as may be necessary to review and optimize the outage plan, agree to any changes and produce an acceptable coordinated generation and transmission outage plan.
(vi) The SLDC shall release the finally agreed outage plan in the SLCF, which takes into account of regional and user requirements, to all users by 1st March each year.
(vii) The SLDC shall review the final outage plan quarterly in consultation with the RLDC and the users, who shall be informed by the SLDC of any proposed changes. Users’ requests for additional outages will be considered by the SLDC and accommodated to the extent possible. The SLDC shall inform users promptly of any changes that affect them.
(viii) In case of emergency in the system viz., loss of generation, break down of transmission line affecting the system, grid disturbance, system isolation, the SLDC, may conduct studies again before clearance of the planned outage.
(ix) The SLDC is authorized to defer the planned outage in case of any of the following:
(x) Each entity shall obtain the final approval from the SLDC prior to availing an outage.
The RLDC and the SLDC shall coordinate with each other to determine the extent of the problem in case there is any contingency crisis arising out of a total or a partial blackout of the State Grid or the Regional Grid. The SLDC shall advise all users of the situation and follow the strategy as outlined below for restoration.
Users’ employees’ persons authorized for operation and control shall be available at Users’ end for communication and acceptance of all operational communications throughout the contingency. Communication channels shall be restricted, as far as possible, to operational communications only till normalcy is restored.
The SLDC shall instruct all relevant generating stations with black start capability to commence their preplanned Black Start Procedure. The SLDC may require the CPPs to extend startup power supply to generating stations as may be feasible.
The SLDC shall prepare the STS for restoration by creating discrete power islands with no interconnection. Close coordination with concerned entities shall be maintained during such restoration process. Generating stations, to whom start up power supply is made available, shall sequence their start up to match their auxiliary power demand with supply available.
Generating stations shall inform the SLDC as generating units become available to take load, in order that the licensee may assess the MW demand, which the generating unit is likely to pick up on circuit breaker closure.
The SLDC shall coordinate with generating stations and distribution licensees to:
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
2/27/2017 ( ii) extend islands by adding more generating units and more demand in a coordinated manner maintaining load generations balance;
( iii) synchronize islands to form a larger, more stable island.
The SLDC shall, taking into account sites where system synchronizers are available, gradually extend the synchronization until all demand is restored.
The SLDC shall utilize any regional or Inter-State assistance available, if appropriate, at any time to assist in the above process.
During recovery, priority of withdrawal of restriction on power drawal shall be as per policy of 4.4.3.
During the restoration process following regional blackout conditions, normal standards of voltage and frequency shall not apply.
A list of essential loads and priority of restoration shall be prepared by each entity in line with regulation 4.4.3.
Distribution Licensees with essential loads shall separately identify non-essential components of such loads, which may be kept off during System contingencies. Distribution Licensees shall draw up an appropriate schedule with corresponding load blocks in each case. The non-essential loads can be put on only when system normalcy is restored, as advised by the SLDC.
All users shall pay special attention in carrying out the procedures so that secondary collapse due to undue haste or inappropriate loading is avoided.
Despite the urgency of the situation, careful, prompt and complete logging of all operations and operational messages shall be ensured by all users to facilitate subsequent investigation into the incident and the efficiency of the restoration process. Such investigation shall be conducted promptly after the incident.
Typical examples of reportable incidents that could affect the grid are the following:
(i) All reportable incidents occurring in lines and equipment of 33 kV and above at grid sub-stations and generating stations shall promptly be reported orally / message by the user whose equipment has experienced the incident to any other significantly affected Users and to SLDC.
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
2/27/2017 Untitled Document
(ii) Depending on the nature of incidence, the SLDC may ask for a preliminary as well as detailed written report, which shall be submitted within 48 hours in case of preliminary report and in case of detailed report it shall be submitted within 7 days.
(iii) In the case of an event occurring in EHV system and generating equipment which was initially reported by a constituent, the constituent shall give a written report within a week.
(iv) The SLDC may call for a report from any user on any reportable incident affecting other users and the entity in case the same is not reported by such user whose equipment might have been the source of the reportable incident.
(v) The above shall not relieve any user from the obligation to report events in accordance with Safety Regulations.
(vi) The format of such a report shall be as agreed at the SLCF and approved by the Commission, but will typically contain the following information:
Date:......... Time:…......
Following a major failure, the licensee and other users shall cooperate to inquire and establish the cause of such failure and produce appropriate recommendations. Licensee/users shall report the major failure to the Commission immediately for information and shall submit the enquiry report to the Commission within 2 (two) months of the incident.
Reporting of accidents shall be in accordance with the Section 161 of Electricity Act, 2003. In both fatal and nonfatal accidents, the report shall be sent to the Electrical Inspector in the prescribed form and to such other authorities as the State Government may, by general or special order, direct.
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 19/30
2/27/2017 Untitled Document
Procedures to be adopted after introduction of intraState ABT for scheduling of injection by beneficiaries including all generating agencies connected with the STS, injected share of ISGS and scheduling of drawal by all licensees connected to the STS of the State on a daily basis are dealt with herein.
The general methodology for scheduling and calculating availability and capacity index shall be as under:
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 20/30
Untitled Document
(vii) While giving requisition of drawal, the licensee or beneficiary shall also show block-wise projected demand under normal conditions along with reasons of restriction in drawal, if any, and its quantum. This requisition shall be given as per format in Annexure - IV. This requisition shall also indicate separately quantum of power to be supplied to persons, other than beneficiaries under long-term and short-term power selling agreement and also short-term sale of incidental surplus power after meeting fully the demand of the area of supply.
(viii) In case of any entity, the requisition of drawal / injection schedule shall be submitted by their respective ALDC on behalf of them. While submitting such requisition or schedule it shall take into consider the requirement of other entities as explained in item (ix) below. Such Intra-State ABT scheduling shall be applicable to all the entities as specified in the regulation 5.1.2 of Tariff Regulations.
(ix) All other entities on whom these Regulations are applicable shall give their drawal requisitions along with the source of supply against such drawals and corresponding injection schedules from such sources as applicable. For this purpose, formats of Annexure - IIII and Annexure - IV shall be used. These entities shall submit their above drawal requisition / injection schedule to the ALDC or SLDC, on whose area of supply their drawals or injections are taking place. In case of such submission to the ALDC, the ALDC shall reflect the drawal requisition and injection schedule in its corresponding drawal requisition and injection schedule to be submitted to the SLDC.
(x) The drawal requisition of a beneficiary or a licensee or a pumped storage hydro-generating station shall show its drawal from those generating stations and licensee only with whom there is power purchase agreement and drawal against each such generating stations and licensee shall be shown separately.
(xi) Based on the requisitions given by the beneficiaries and different entities and taking into account technical limitations on varying the generation and transmission system constraints, if any, the availability of central sector allocation / share, the relevant issues like open access and trading of power, etc. in the regional schedule, the SLDC shall prepare the economically optimal injection schedules for generating stations of generating company, distribution licensees and other entities and also drawal schedules for distribution licensees and other entities. The SLDC shall communicate the same to the generating stations and the beneficiaries.
The SLDC shall also communicate the final drawal schedule of power to the pumped storage hydro-generating station for its pumping operation and also confirm the schedule to the concerned source from where power will be drawn.
(xii) While finalizing the above daily generation schedules for the generating stations, the SLDC shall ensure that the same are on merit order basis as far as possible, operationally reasonable, particularly in terms of ramping / sliding rates and the ratio between minimum and maximum generation levels.
The SLDC shall also formulate the procedure for meeting contingencies both in the long run and in the short run, and detailed scheduling procedure in a surplus and shortage system in its monthly meeting with the licensees.
(xiii) The generating agencies connected to STS or agencies injecting power in State Grid shall inform any modification / changes to be made in station wise foreseen capabilities, if any, to the SLDC by 09.00 p.m. Beneficiaries may also inform any modification / change of their drawal/export, if any, to the SLDC by 09.00 PM.
(xiv) Based on the surplus, if any, the concerned beneficiaries may arrange for supply such surplus power through day ahead transaction under Open Access Regulations or any Inter-State supply. Such arrangement or the modification, if any, shall be intimated to the RLDC by the SLDC by 10.00 p.m. The SLDC shall receive the final 'drawal schedule' from the RLDC against ISGS share along with any Bilateral Exchange of Power, if any by 11.00 p.m.
(xv) The SLDC shall inform the final injection / drawal schedule for the next day to all concerned by 11.30 p.m.
(xvi) In the event of any contingency, during the course of the day of operation, the SLDC or any generating station of any generating company connected to the STS or any entity may revise its injection and drawal schedule and its foreseen capability, drawal/export, for the balance period of the day. The SLDC shall then revise the concerned 'drawal schedule' and 'dispatch schedule' in consultation with the concerned beneficiaries and issue the same. All such revisions shall be effective one hour after the first advice is received by the SLDC.
(xvii) While finalizing the drawal and injection schedules as above, the SLDC shall also check that the resulting power flows do not give rise to any transmission constraint. In case any impermissible constraint is foreseen, the SLDC shall moderate the schedules to the required extent, under intimation to the beneficiaries concerned. The revised schedule shall be made effective from the fourth time blocks counting the issuing time as the first time block. In case of any grid disturbance, the scheduled injection and scheduled drawal of all beneficiaries shall be deemed to have been revised to be equal to their actual injection / drawal for all the time blocks affected by grid disturbance.
(xviii) In the case of a forced outage of a unit, the SLDC shall revise the schedules on the basis of revised declared capacity. The revised declared capacity and the revised schedules shall become effective from the 4th time block, counting the time block in which the revision is advised by the generator to be the first one.
(xix) In the event of a bottleneck in evacuation of power due to any constraint, outage, failure or limitation in the STS, associated switchyard and sub-stations owned by the Licensees necessitating reduction in injection by any beneficiary, the SLDC shall revise the schedules which shall become effective from the 4th time block, counting the time block in which the bottleneck in evacuation of power has taken place to be the first one. Also, during the first, second and third time blocks of such an event, the scheduled injection shall be deemed to have been revised to be equal to actual injection, and the scheduled drawals / injection of the beneficiaries and all other entities on whom these Regulations is applicable, shall be deemed to have been revised to be equal to their actual drawals.
(xx) In the case of any grid disturbance, scheduled injection and scheduled drawal of the beneficiaries and all other entities on whom these Regulations are applicable, shall be deemed to have been revised to be equal to their actual injection / drawal for all the time blocks affected by the grid.
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 21/30
2/27/2017 disturbance. Certification of grid disturbance and its duration shall be done by the SLDC within 24 hours of the grid disturbance. The SLDC shall notify all the entities in the grid about the period of such grid disturbance and the effected portion of the grid system in detail.
If any running unit(s) of Bandel Thermal Power Station’s first four units, or of Santaldih Thermal Power Station goes / go out of operation from running condition at any block of time, then from the next block of time, the generation of such generating plants shall be considered as scheduled generation up to 6th block or till revised schedule is obtained, whichever is less, and the injection schedule by those generating stations shall be modified by SLDC accordingly.
Revision of declared capacity by the generation station(s) and requisition by beneficiary(ies) for the remaining period of the day or part of the day or injection / drawal of the entities as per agreement shall also be permitted with advance notice. Revised schedules/declared capacity or injection / drawal schedule in such cases shall become effective from the 6th time block, counting the time block in which the request for revision has been received in the SLDC to be the first one.
If, at any point of time, the S LDC observes that there is need for revision of the schedules in the interest of better system operation, it may do so on its own, and in such cases, the revised schedules shall become effective from the 4th time block, counting the time block in which the revised schedule is issued by the SLDC to be the first one.
For any revision of a scheduled injection, including post facto deemed revision, there shall be a corresponding revision of scheduled drawals of the beneficiaries. The SLDC shall issue final schedule of the day by 06.00 a.m. on next day for the purpose of UI calculation.
On completion of the operating day, by 24.00 hours, the schedule finally implemented during the day (taking into account all before-the-fact changes in dispatch schedule of generating stations and drawal schedule of the users) shall be issued by the SLDC. This schedule shall be the datum for commercial accounting. The average ex-bus capability for each of the generating stations connected with the STS shall also be worked out based on all before-the-fact advice to the SLDC.
While making or revising its declaration of capacity, the generator shall ensure that the declared capacity during peak hours is not less than that during other hours. However, exception to this may be allowed in case of tripping/re-synchronization of units as a result of forced outage of units. The peak-hours shall be as applicable for generating station as per Tariff Regulations.
The scheduled injection and actual injection for generation station shall be ex-bus generation at the generating station. For beneficiaries and all other entities on whom these Regulations are applicable, the scheduled and actual net drawals shall be at their respective receiving points as mentioned in the PPA.
For calculating the net drawal schedules of beneficiaries and all other entities on whom these Regulations are applicable, the applicable intra-State transmission losses shall be apportioned to their drawal schedules for the time being.
Provided that a refinement may be specified by the Commission in future depending on the preparedness of the SLDC.
Drawal / injection schedules issued/revised by the SLDC shall become effective from designated time block. Every endeavor shall be made by the SLDC to communicate the revision to the concerned entities unless there are extraordinary circumstances for only upon such communication the time block shall be reckoned to commence.
A procedure for recording the communication regarding changes to schedules duly taking into account the time factor shall be evolved by the STU.
Since variation of generation in purely run-of-river hydro generating stations may lead to spillage, these shall be treated as must run stations. The maximum available capacity in each time block, duly taking into account the over load capability, shall be equal to or greater than that required to make full use of the available water of that time block. The run-of-river hydro-generating station with pondage, storage type hydro-generating stations and pumped storage hydro-generating stations are designed to operate during peak hours to meet system peak demand. The maximum available capacity of a station declared for the day shall be equal to the installed capacity including overload capability, minus auxiliary consumption and transformation losses, corrected for the reservoir level. The SLDC shall ensure that generation schedules of such type of stations are prepared and the stations dispatched for optimum utilization of available hydro energy except in the event of specific system requirements/constraints.
The SLDC shall schedule and control the overall generation and injection of power in the STS in the specified manner after giving due preference to run-of-river hydro-generating station, canal based hydro-generating station, hydro generating station where water level is at peak reservoir level and inflow of water goes as a waste, and any other generating station where energy potential of the generating station, if unutilized, goes waste.
The SLDC shall properly document all above information i.e. station-wise foreseen ex-power plant capabilities advised by the generating stations, the drawal schedule indented by the beneficiaries, all schedules issued by the SLDC and all revisions / updating of the above.
The procedure for scheduling, carried out by SLDC shall be open to all entities for any checking / verification. In case any mistake / omission is detected, the SLDC shall forthwith make a complete check and rectify the same.
If required the SLDC may ask for the additional information besides those in Annexure – III & IV from respective persons concerned. In case of requirement of such additional information on regular basis, SLDC shall obtain prior approval from the Commission.
While availability declaration by the generating stations may be a resolution of one MW and one MWHr all entitlement requisitions and schedules shall be rounded off to the nearest decimal, to have a restriction of 0.1 MW.
Regarding VAR drawal / absorption from Inter-State Grid, the SLDC has to follow the Grid Code.
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
Untitled Document
(ii) All the distribution licensees, transmission licensees and the STU are expected to provide local VAR compensation such that they do not draw VARs from the grid. VAR compensation has to commence in the following order:
(iii) While tap changing on all 400/220 kV ICTs of CTU shall be done as per the instruction of the RLDC while tap changing of other ICTs shall be done as per the instructions of the S LDC.
(iv) The generating stations shall generate/absorb reactive power as per instructions of the SLDC, within the capability limits of the respective generating units. No payments shall be made to the generating companies for such VAR generation/absorption.
(v) The SLDC may direct a beneficiary to curtail its VAR drawal/injection in case security of the grid or safety of any equipment is endangered.
(vi) At interchange point the VAR drawal/injection shall be minimum when voltage at that point is below 97% or above 103%.
6.1 In pursuance to subsections (2), (4) and (5) of section 33 of the Act, every licensee, generating company, generating station, EHT S/S and any other entity connected with the operation of the State Grid shall comply with directions issued by the SLDC. If any dispute arises with reference to the safe, secure and integrated operation of the State grid or interpretation of clauses of State Grid Code, or in relation to any direction given by the SLDC, it shall be referred to the WBERC for decision. Pending decision of the Commission, the concerned party raising the dispute shall comply with direction of the SLDC. The WBERC, in turn, after due process may order the defaulting entity for compliance or otherwise. The noncompliance of the same may lead to penal action, which includes termination of connectivity agreement and delinking from the State Grid.
6.2 In the case of nonpayment of dues i.e. bills by any beneficiary, the affected entity shall report the matter to the SLDC. The SLDC shall verify the facts and take up the matter with the defaulting entity for paying up of the dues. In case of noncompliance by the defaulting entity, the WBERC shall be informed by the SLDC, whereupon the WBERC shall initiate necessary action.
6.3 Any entity that has been accused of noncompliance of any direction of any Appropriate Commission and has its connection disconnected with any grid by virtue of any order of the Appropriate Commission, shall not be allowed any connectivity with State Grid unless the original dispute is settled.
7.1 The summation of input meter readings at the connection points of the STS with generating stations, entities engaged in distribution of electricity and inter-connection points with the CTU and other entities gives the total flow into the STS. Similarly, the summation of export at the connection points of the STS with generating stations, entities engaged in distribution of electricity and inter connection points with the CTU and other entities gives the total outflow from the STS. The difference between the inflow and outflow is the transmission loss of the STS. As the connection points with distribution entity may be large in number, initially it may not be possible to apply the above principle to determine transmission loss. In such an event several load flow studies representing different load conditions covering at least three seasons and three hours of the day may be carried out to determine the transmission loss. The transmission losses determined either way shall be apportioned to the distribution entity consuming power and energy from the STS network and added to their metered drawal, to arrive at the billing figure.
7.2 Any variation between an actual injection or an actual drawal and the scheduled injection or the scheduled drawal shall be accounted for by SLDC as per Tariff Regulations. Weekly bills of variations shall be prepared and issued by the SLDC. These bills shall have high payment priority and the concerned entities shall make payment of the billed amount within 10 days of billing date. If the payments against the above bills are delayed, the defaulting entities shall have to pay simple interest @ 0.04% for each day of delay. The interest so collected shall be paid to the entities who were to receive the payment. In case of continued payment default, the matter should be brought to the notice of the WBERC by the SLDC.
7.3 Energy accounts shall be prepared by the SLDC on monthly basis and shall be issued to all concerned entities within 3 clear working days of the succeeding month.
7.4 All energy accounting calculations carried out by the SLDC shall be open to all users for any checking/verification. In case any mistake is detected, the SLDC shall make a complete check and rectify the mistake.
7.5 In matters concerning VAR drawal/absorption (its rate and payment) from inter-State grid, the SLDC has to follow Grid Code. VAR drawal/absorption and payment for the same shall be settled between a beneficiary and the pool account, or between the beneficiaries as applicable. The generating stations shall generate/absorb reactive power as per instruction of the SLDC, within the capability limits of the generating units. No payments shall be made to generating companies for the same.
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
2/27/2017 Untitled Document
If any difficulty arises in giving effect to any of the provisions of these Regulations, the Commission may, with reasons to be recorded in writing, direct the licensees, the consumers or the applicants for Open Access, by general or special order, for taking suitable action not inconsistent with the provisions of the Act, as may appear to be necessary for removing the difficulty.
The Commission may, at any point of time, at its sole discretion, vary, alter, modify, add or amend any provisions of these Regulations.
Nothing in these Regulations shall be deemed to limit or otherwise affect the inherent powers of the Commission to make such orders as may be necessary for meeting ends of justice or to prevent the abuse of the process of the Commission.
The West Bengal Electricity Regulatory Commission (West Bengal Electricity Grid Code) Regulations, 2006 issued under Notification No. 26/WBERC dated 12th January 2006 and published in the Kolkata Gazette, Extraordinary on 16th January 2006 is hereby repealed. Notwithstanding such repeal, anything done or any action already taken under the repealed Regulations, shall in so far as it is not inconsistent with the West Bengal Electricity Regulatory Commission (State Electricity Grid Code) Regulations, 2007, be deemed to have been done or taken under the corresponding provisions of the West Bengal Electricity Regulatory Commission (State Electricity Grid Code) Regulations, 2007.
[See Regulation 3.3]
Name of Power Station / SubStation owner:
Tel. Number:
Fax Number:
Permanent Address:
| Item of Plant / Apparatus | Responsibility for Safety | Control | Operation | Maintenance | Remarks |
|---|---|---|---|---|---|
| …kV Switchyard | All equipments including Bus bars | Feeders | Generating Units |
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 24/30
[See Regulation 3.6.5]
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
Untitled Document
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 26/30
2/27/2017 Untitled Document
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 27/30
2/27/2017 Untitled Document
Rated MVA, Voltage rating & vector group, Positive & zero sequence Impedance, Tap Changer (on / off load) and range, Transformer Grounding and X/R Ratio.
Line designation, Year of commissioning, Length of line (Km), Line capacity (Thermal & surge impedance), No. of circuits, Per unit circuit impedance on 100 MVA & admittance values (positive & zero sequence).
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 28/30
2/27/2017 Untitled Document
[See Regulation 5.3 (i), (iv), (ix)]
| Block No. | Time in injection by entity in MW | Proposed Injection by the entity from own availability for other entities* | Injection of power on behalf of other entities as per 5.3 (ix) | Total Injections (Outside own area of supply) |
|---|---|---|---|---|
| 1. | 00.00 hrs. to 00.15 hrs. | | | |
| 2. | 00.15 hrs. to 00.30 hrs. | | | |
| 3. | 00.30 hrs. to 00.45 hrs. | | | |
| 4. | 00.45 hrs. to 01.00 hrs. | | | |
| 5. | | | | |
| 96. | 23.45 hrs. to 24.00 hrs. | | | |
[See Regulation 5.3(iv), (vii), (ix)]
| Projected Drawal (MW) From | Projected Demand (MW) | Schedule of Drawal for Open Access Customer (OAC) | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Committed Inter-State | Electricity Trader | Restricted to, if any | |||||||||
| Block No. | Generating Company. | Distribution Licensees under sub-section (5) of section 64 | |||||||||
| (a) | (b) | (c) | (d) | (a + b + c + d) | (f) | (g) | Reasons of Restriction | (h) | (i) | (j) | (k) |
By Order of the Commission
Place: Kolkata
Dated: 04.04.2007 (K. L. Biswas)
Secretary of the Commission
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm
29/30
2/27/2017 Untitled Document
http://wberc.net/wberc/regulation/under_2003_Act/regulation34/regulation34_spl.htm 30/30