Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the first amendment (2024) to HERC's 2021 regulation on charging infrastructure and tariffs for electric vehicles. It was notified on 19 July 2024 under section 181 of the Electricity Act 2003 and applies across Haryana, coming into force on Gazette publication (p1).
Section 1 gives the short title, the Gazette-linked commencement and the territorial extent to the whole State of Haryana (p1). Sections 2 and 3 substitute Regulation 17(f) and Regulation 18(e) of the 2021 parent regulation with identical text: for HT connections to E-Vehicle charging stations with load up to 200 kW, the cost of the separate/dedicated transformer and allied equipment is to be borne out of the Discoms' CSR fund, and where that fund falls short the distribution licensee recovers the amount through its ARR/true-up petition (p1–2). Section 4 inserts a new clause 17(2) allowing HT metering to be provided by an outdoor CT/PT unit on an H-pole with the transformer placed at the nearest point outside an explosive zone — for fire-prone premises such as petrol pumps and gas agencies — with LT supply taken inside the charging station (p2).
The order is signed by the Deputy Secretary (Personnel) for the Secretary, HERC, dated 19 June 2024, a month before the notification date (p2).
Read with this
The regulation
Voltaic last read HERC's website for final documents on 24 Nov 2026 (2 pages). A document HERC issued after the page that lists it was read may not be held by Voltaic yet.