Skip to content

CSERC · Chhattisgarh State Electricity Regulatory Commission

Terms and Conditions for Determination of Tariff for Renewable Energy Sources Regulations, 2025

Chhattisgarh State Electricity Regulatory Commission (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025

RegulationDated 17 Dec 2025In force from 1 Apr 2025

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cserc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Chhattisgarh State Electricity Regulatory Commission (CSERC) makes these Regulations under s.61 and s.86 read with s.181 of the Electricity Act 2003 to fix the terms and conditions for determining tariff for renewable energy (RE) generating stations in the State that sell power to distribution licensees (p3). They come into force from 1 April 2025 and run for five years, and the Control Period is five years from the same date (p3, p10).

Regulations 1–4 set scope and eligibility: they apply to RE projects achieving COD between 1 April 2025 and 31 March 2030 that supply their entire output to State distribution licensees on a long-term basis, and they list eligibility criteria — new plant and machinery — for wind, hydro, non-fossil co-generation, solar PV/floating solar/solar thermal/rooftop, MSW and RDF, biogas, biomass gasifier, renewable hybrid and renewable-with-storage projects (p8–9). Existing projects with 20-year-plus PPAs and COD before 31 March 2025 stay under their earlier tariff orders, except that energy charges for fuel-based projects follow these Regulations (p8).

Chapter 1 (Reg. 5–12) covers general principles: control period, tariff period equal to useful life, which technologies get generic versus project-specific tariff, petition procedure and filing requirements, single-part tariff structure (two-part for fuel-based technologies), levelisation, and dispatch — all RE plants are treated as must-run, with limited exemptions from scheduling and deviation settlement (p10–15).

Chapter 2 (Reg. 13–24) sets financial principles: composition of capital cost, debt-equity, interest on loan, depreciation, return on equity, interest on working capital, O&M escalation, rebate, late payment surcharge, the ceiling-norm character of all norms, treatment of subsidy, and pass-through of statutory charges (p16–20).

Chapters 3–12 (Reg. 25–78) give technology-specific parameters for wind, small hydro, non-fossil co-generation, solar PV, solar thermal and floating solar, MSW and RDF, biogas, biomass gasifier, renewable hybrid and renewable-with-storage projects — each specifying how capital cost, CUF/PLF, auxiliary consumption, O&M and, where relevant, heat rate, calorific value and fuel cost are handled (p21–32).

Chapter 13 (Reg. 79–81) provides for deviation from norms and the Commission's powers to relax provisions and remove difficulties (p33). The annexed Forms 1.1–3.2 are petition templates for parameter assumptions, tariff-component computation and fuel-use reporting (p34–40).

Standard name
Renewable Energy Tariff Regulations
Primary topics
Tariff determination, Renewable energy tariff, Capital cost and investment

Read with this

No other documents to read with it are on Voltaic.

One more document belongs here and is not on Voltaic: a copy in another language.

Voltaic last read CSERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document CSERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of CSERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cserc.gov.in ↗

Report an issue with this document