(1) Section 86(1)(e) of the Electricity Act, 2003 (hereinafter referred to as "the Act") assigns the following function to the State Electricity Regulatory Commission amongst others: "promote co-generation and generation of electricity from renewable sources of energy by providing suitable measures for connectivity with the grid and sale of electricity to any person, and also specify, for purchase of electricity from such sources, a percentage of the total consumption of electricity in the area of a distribution licensee."
(2) The National Electricity Policy notified by the Central Government has emphasized on the urgent need for tapping the untapped potential of energy from non-conventional and renewable energy sources. Even the Tariff Policy issued by the Central Government has provided a mechanism for promoting and harnessing renewable energy. Recognising higher costs of such sources, the Tariff Policy has mandated to provide preferential tariffs for renewable and non-conventional energy sources and guaranteed off-take of a defined percentage of power from such sources till they can compete with conventional sources.
(3) It is, therefore, clear from the above provisions that the function of the State Commission is to promote cogeneration and generation of electricity from renewable sources of energy not only through preferential tariffs but also by providing suitable measure which influence growth of renewable energy such as:
(4) In terms of clause (zd) of sub-section (2) of section 181 of the Act, the Commission has been vested with the powers to make regulations, by notification, on the terms and conditions of tariff under section 61. As per section 181(3) of the Act, the Commission is required to make previous publication before finalizing any regulation under the Act.
(5) In exercise of the powers vested under sections 61 and 181(2) of the Act and all other enabling powers and in compliance of the requirement under section 181(3) of the Act, the Uttarakhand Electricity Regulatory Commission (hereinafter referred to as the "Commission") had notified the UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) Regulations, 2010 on July 06, 2010 which amongst other terms and conditions also specified the preferential tariffs for plants based on renewable sources of generation along with the renewable purchase obligation (RPO) for the distribution licensee for FY 2010-11 to FY 2012-13. The Commission, subsequently, also issued the UERC (Compliance of Renewable Purchase Obligation) Regulations, 2010 which provided that if the Obligated Entity does not fulfill its commitment towards Renewable Purchase Obligation during any year it can be fulfilled by purchase of renewable energy certificates.
(6) Further, based on the difficulties expressed by UPCL and the developers of renewable energy based generating stations in interpreting, understanding and implementing certain provisions of UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) Regulations, 2010, the Commission had issued UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) Regulations, 2010, Removal of Difficulty (First) Order, 2010 on October 28, 2010.
The generators amongst other issues had raised the issue of deemed generation due to frequent tripping of the lines connecting the Generating station with the sub-station of distribution licensee, The Commission in the matter had held as under.
"Keeping in view the above concessions/relaxations allowed to RE based generating stations, the provisions of deemed generation has not been considered as necessary under the RE Regulations, 2010 in case of day to day tripping and outage of lines. However, in order to avoid bottling up of much needed generation due to inadequacy of the transmission and distribution system, the Commission is of the view that penal provisions are necessary so as to avoid such situations. This matter is under examination and the Commission shall take a final view on the same after discussions with UPCL and Developers."
(7) For the FY 2011-12, the RPO specified for non-solar sources for UPCL was 4.50% of the total energy purchased from all sources for the purpose of supply to its consumers within its area of supply. Against this, UPCL managed to procure only 4.10% thereby implying a deficit in meeting its RPO.
(8) The Commission was receiving continuous representations from the developers regarding frequent trippings and also voltage fluctuations in UPCL's system leading to generation loss. However, UPCL's approach was found to be lackadaisical in this regard. Proper upkeep of the distribution system to ensure maximum availability of generation was all the more crucial as it would have not only ensured additional generation to the State resorting to frequent over-drawals of power at costlier rates from the grid but would have also assisted UPCL to meet its RPO. Considering the same, the Commission decided to issue amendment to the UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) Regulations, 2010 to incorporate provisions relating to deemed generation. The Commission issued public notice on 24.03.2012 seeking comments/suggestions / objections of all the stakeholders on Draft UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating stations) (First Amendment) Regulations, 2012 (hereinafter referred to as the draft regulations). The Commission also held hearing in the matter on June 11, 2012 and June 22, 2012 for deliberations on the draft regulations. The Commission also held a meeting with MD, UPCL and ED (Commercial), UPCL on 30.07.2012 to seek their views in the matter.
(9) In all 6 comments were received on the draft Regulations from the generators as well as UPCL. The Commission considered the comments of the stakeholders on the draft regulations. The regulations have been finalized after detailed analysis and due consideration of the various issues raised by the stakeholders.
In the State of Uttarakhand, the small hydro projects are located at remote and hilly terrains, where bottlenecks related to inadequacy of the transmission and distribution system exists leading to frequent trippings, breakdowns of lines, voltage fluctuations occur leading to loss of generation. In comparison, other renewable sources are set up in plain areas close to the sub-station of UPCL where such problem may not be as persistent and as acute as that encountered for the SHP's. Further, at present only 3 Solar Generation Plants have been set up at Roorkee in the State of Uttarakhand with an installed capacity of about 5 MW and have been in operation for even less than a year. Hence, adequate data would not be available to examine the impact of the breakdowns, etc. for them. Thus, at present the Commission is only specifying the deemed generation conditions for small hydro projects. However, the Commission may consider the same for other renewable energy sources at a later stage on availability of sufficient data.
TRTQU , 01 , 2012 0 ( 10, 1934 H)
BTRQU ,01 , 2012 $0 ( 10, 1934 TH)
For 8 MW project, deemed generation based on actual CUF achieved during the year, actual number of month-wise outages/interruption in the system during the year is given as under:
| Month | Total actual generation achieved during the month (MU) | Total hours of outage/interruption in system during the month | Number of hours to be considered for deemed generation purposes | Deemed generation (MU) |
|---|---|---|---|---|
| April | 2.28 | 50 | 2 | 0.0068 |
| May | 2.59 | 52 | 4 | 0.0150 |
| June | 2.74 | 60 | 12 | 0.0498 |
| July | 2.95 | 75 | 27 | 0.1191 |
| August | 3.30 | 90 | 42 | 0.2119 |
| September | 3.14 | 80 | 32 | 0.1570 |
| October | 2.95 | 60 | 12 | 0.0518 |
| November | 2.57 | 0 | 0 | 0.0000 |
| December | 2.36 | 60 | 12 | 0.0414 |
| January | 2.12 | 46 | 0 | 0.0000 |
| February | 1.97 | 0 | 0 | 0.0000 |
| March | 2.12 | 42 | 0 | 0.0000 |
| Total | 31.07 | 0.6527 |
(1) Regarding the issue of voltage fluctuations raised by the generators, the Commission recognises that the problem of voltage fluctuations in UPCL's system is rampant which often causes generation loss. This issue was also discussed by the Commission during the meeting with senior officers of UPCL. They admitted that this problem exists because of the evacuation lines running for long distances, improper load management and also due to poor upkeep and maintenance of the equipments installed at the sub-stations. The Commission accepted the submission of UPCL, however, UPCL was instructed to maintain their equipments properly and also to ensure installation of capacitor banks at the sub-stations, wherever required, so as to ensure that voltage fluctuations does not lead to generation loss. It is the duty of UPCL to ensure that it gets maximum generation so as to meet its Renewable Purchase Obligation (RPO) specified by the Commission failing which it may be required to buy the Renewable Energy Certificates to meet the shortfall in complying with its RPO. Hence, the Commission feels it necessary to include loss of generation due to voltage fluctuation as deemed generation. However, keeping in view the existing system of UPCL, the Commission is of the view that it would be feasible to give UPCL reasonable time to upgrade/strengthen the system and also to install the capacitor banks at its sub-stations. The same was also agreed to by the officers of UPCL in the meeting with the Commission. Accordingly, the Commission has decided to enable the provision with regard to deemed generation on account of voltage fluctuations w.e.f. 01.04.2013.
(10, 1934)
(2) The Commission has, accordingly, decided to include the following in the amended Regulation:
"UPCL shall be required to maintain the voltages at the point of interconnection with the project within the limits stipulated hereunder, with reference to declared voltage:
With effect from 01.04.2013, any loss in generation due to variations in the voltage beyond the limits specified above shall be reckoned as deemed generation.
Provided that any loss in generation due to variation in voltage beyond the limits specified above, should be at least 25%."
Here, the generation loss of 25% has been provided, keeping in view that for a plant having 4 units, at least one unit should have tripped/stopped due to voltage fluctuations resulting in appreciable loss of generation due to voltage fluctuations.
For a plant running a load of 8 MW, the loss due to variation in voltage beyond the limits specified will be considered for deemed generation purposes only if the generation drops to 6 MW or below after voltage variations/fluctuations occurred.
(3) Further, the calculation of generation loss due to voltage fluctuations included in deemed generation would be carried out in the following manner:
"The generation loss towards the Deemed Generation (in MWh) in accordance with sub-Regulation (2) above, if any, during the month shall be considered as the summation of the product of number of hours the variations in voltage beyond the specified limit existed and the Generation lost (in MW) due to the variation in the voltage beyond the specified limit. The Generation lost (in MW) would be the difference between the following:
(The rationale behind taking generation after 90 minutes immediately after each fluctuation/variation in voltage was restored within the specified limit is that some of the generators submitted that it takes about 70-95 minutes after the grid is restored to bring back the machine to full load. The Commission understands that the meters installed at their stations are ABT Compliant meters which can be read through MRI's. Hence, the Commission has decided to consider the generation achieved after 90 minutes immediately after variation in voltage was restored within the specified limit as it would enable the generator to bring the plant to maximum possible load.)
The illustration given below would explain the computation of generation loss due to voltage fluctuations included in deemed generation.
BHYRUS T, 01 R, 2012
Deemed Generation (MWh) = [(ii(a)) X (v-ii(a)) + [ii(b) X (v-ii(b))} = 1/2 X (5.00-3.50) + 1/2 X (5.00-2.50) = 0.75 + 1.25 = 2.00 MWh
| (a) | (b) | (c) |
|---|---|---|
| Month | Total actual Saleable generation achieved during the month (MU) | Deemed generation (MWh) |
| April | 2.28 | 0 |
| May | 2.59 | 8 |
| June | 2.74 | 16 |
| July | 2.95 | 0 |
| August | 3.30 | 10 |
| September | 3.14 | 0 |
| October | 2.95 | 8 |
| November | 2.57 | 9 |
| December | 2.36 | 3 |
| January | 2.12 | 2 |
| February | 1.97 | 3 |
| March | 2.12 | 2 |
| Total | 31.07 | 61 |
for the deemed generation under the amended Regulation. Further, since the sum of actual annual saleable generation and total deemed generation of 31.7837 MU is more than the annual saleable energy of 31.22 MU at CUF of 45%, therefore, deemed generation of only 0.15 MU would be allowed in addition to the actual saleable energy of 31.07 MU equivalent to the specified ceiling of 45% CUF.
Further, it would also be relevant to mention that any charges paid by UPCL towards deemed generation shall not be allowed as an expense to be pass through in tariffs. Since, the deemed generation would be applicable therefore, UPCL will have to bear such charges.
In exercise of powers conferred under section 181 of the Electricity Act, 2003, and all other powers enabling it in this behalf, and after previous publication, the Uttarakhand Electricity Regulatory Commission hereby makes the following regulations to amend the Uttarakhand Electricity Regulatory Commission (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating stations) Regulations, 2010 (Principal Regulations), namely:
Provided that the following shall not count towards Deemed Generation:
With effect from 01.04.2013, any loss in generation due to variations in the voltage beyond the limits specified above shall be reckoned as deemed generation: Provided that any loss in generation due to variation in voltage beyond the limits specified above, should be at least 25%.
BTRRQUS T, 01 R, 2012 $0 (G 10, 1934 2 )
The period of outage/interruption on account of such factor(s) specified in sub-Regulation I and 2 above, shall be reconciled on monthly basis and the loss of generation at the Station towards Deemed Generation after accounting for the events specified under sub-Regulation (1) (i) & (ii) above, shall be computed on following considerations:--
The recovery on the above account shall be admissible if the actual energy generated during the year is less than the normative CUF of 45%, specified for recovery of fixed charges for small hydro projects. In case the sum of actual energy generated and the deemed generation during the year exceeds the normative CUF specified of 45%, then the deemed generation along with the actual energy generated will be allowed only up to the CUF of 45%.
The generation loss towards the Deemed Generation in accordance with sub-Regulation (1) above, if any, during the month shall be considered on the pro-rata basis on the number of hours lost based on the actual average generation achieved during that month divided by the total number of hours available during the month reduced by the number of hours outage/interruption occurred in the system.
The generation loss towards the Deemed Generation (in MWh) in accordance with sub-Regulation (2) above, if any, during the month shall be considered as the summation of the product of number of hours the variations in voltage beyond the specified limit existed and the Generation lost (in MW) due to the variation in the voltage beyond the specified limit. The Generation lost (in MW) would be the difference between the following:--
UPCL shall pay for the saleable deemed generation, on annual basis, for small hydro projects worked out on the basis of the deemed generation on the above lines, at the generic/project specific tariffs under the provisions of RE Regulations, as amended from time to time by the Commission. The settlement of payment towards deemed generation charges shall be carried out within 3 months of the completion of the financial year.
Any charges paid by UPCL towards deemed generation shall not be allowed as an expense to be passed through in tariffs. UPCL will have to bear such charges.
The deemed generation conditions stipulated above shall be applicable only on those small hydro projects who have signed a long term PPA with UPCL on the preferential tariffs specified in the Principal Regulations. Further, the deemed generation conditions shall be applicable only on the small hydro projects where the evacuation line is connected to 11 kV or higher voltage Grid Sub-station.
The deemed generation conditions as stipulated above shall come into effect from the date of publication of the amendment regulation in the Government Gazette.
By the order of the Commission,
Neeraj Sati, Secretary.
0 $035/581-1-2012/