Wind and Solar Forecasting, Scheduling and Deviation Settlement Regulations, 2018

Sikkim State Electricity Regulatory Commission (Forecasting, Scheduling, Deviation Settlement and Related Matters of Wind and Solar Generation Sources) Regulations, 2018

RegulationDated 19 Apr 2018Published in the Gazette 3 May 2018No.18/SSERC/FSDS/2018 dated 19th April 2018

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on sserc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Sikkim State Electricity Regulatory Commission has issued a principal regulation under section 181 of the Electricity Act, 2003 to integrate wind and solar generation into the Sikkim grid through forecasting, scheduling and a state-level deviation-settlement mechanism (p1, p3–4). It applies to all wind and solar generators of installed capacity of 1 (one) Mega Watt and above, whether they sell to electricity supply or distribution companies, to third-party consumers through open access, or for captive consumption through open access, within or outside the State, including generators connected via pooling stations (p4).

Regulations 1–2 set commencement on Gazette publication and define the operative vocabulary: absolute error, available capacity, deviation, gaming, pool account, pooling station, QCA, State Entity, SLDC and 15-minute time-block (p1–3). Regulation 3 states the objective of large-scale grid integration while maintaining grid stability under the Grid Code, and fixes the applicability threshold (p3–4).

Regulation 4 is a Forecasting and Scheduling Code. It requires generators or their QCAs to provide technical, weather, telemetry and real-time data to SLDC; mandates day-ahead and week-ahead schedules in 15-minute blocks; allows schedule revisions on defined notice; and permits generators or QCAs either to adopt SLDC's forecast or to use their own schedule as the deviation reference. SLDC may engage forecasting agencies for grid-security forecasting, and a Detailed Procedure prepared by SLDC is to cover telemetry and formats (p4–5).

Regulation 5 creates the commercial and deviation settlement framework. Intra-state sales are paid on actual generation; inter-state transactions follow CERC regulations. Deviations from schedule are payable by the generator or QCA to the State DSM Pool in slabs based on absolute error in a 15-minute block (Table 1, p5). QCAs handle aggregation, commercial settlement and de-pooling to individual generators, and the State must maintain separate time-block-wise schedule, generation and deviation records (p5–6). Regulation 6 gives the Commission power to relax provisions after hearing and to issue directions to remove difficulties (p6).

Standard name
Forecasting, Scheduling and DSM for Wind and Solar
Primary topics
Scheduling and despatch, Deviation settlement (DSM), Energy accounting and settlement

Read with this

No other documents to read with it are on Voltaic.

Voltaic last read SSERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 21 Nov 2026. A document SSERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of SSERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.