Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the HPERC's disposal order finalising the draft Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Sharing of Cost of Terminal Benefits of Personnel of the erstwhile HPSEB and Successor Entities) Regulations, 2015. It is the record of the consultation required before notification, not the regulations themselves.
The background (p1) sets out the trigger: the Himachal Pradesh Power Sector Reforms Transfer Scheme, 2010 (10 June 2010) transferred HPSEB's functions, assets and personnel to successor entities, protecting terminal benefits including pension and placing funding responsibility on HPSEB Ltd. and the State Government. Because no separate regulatory provision existed for recovering terminal-benefit cost from operation and maintenance expenses, the Commission proposed regulations under s.181(2)(zp) read with ss.61, 62 and 86 to recover past liabilities in a structured manner.
Pages 1–2 record the previous-publication steps: draft published in the Rajpatra on 7 February 2015, hosted on the Commission's website, public notice in The Tribune and Amar Ujala on 10 February 2015, with 30 days for objections, and circulation to stakeholders. Five stakeholders responded.
Pages 2–8 tabulate each objection against the Commission's view. The objections concern accounting for monthly pension contributions receivable from other entities, HPPTCL's and HPPCL's share, treatment of pension surcharge in the ARR, the quantum of liabilities transferred with assets, staffing and deputation, and whether the mechanism eases future liabilities. The Commission's recurring response is that the cost of terminal benefits is already provided for in HPSEBL's ARR, that the State Government's obligations under the Transfer Scheme remain unaffected, and that several points are not relevant to these regulations.
The order closes (p8) with a finding that regulations under s.181 may be framed prospectively and must be consistent with the Act, that the obligations cast on the State Government by the statutory transfer scheme are in no way affected or limited, and therefore that proposed sub-regulation (2) of regulation 1 requires amendment and provisions must be inserted preserving the State Government's Transfer Scheme obligations. The Commission directs that the draft amendment published be finalised and notified in the Official Gazette.
Read with this
The regulation
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.