Standards of Performance of Distribution Licensees and Determination of Compensation Regulations, 2020

Haryana Electricity Regulatory Commission (Standards of Performance of Distribution Licensees and Determination of Compensation) Regulations, 2020

RegulationDated 24 Apr 2020HERC/50/ 2020 dated 24th April, 2020

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on herc.org.in ↗

Summary

Summary written by software, from pages 1 to 26 of 44. Check the regulator's original before you rely on it.

These are the HERC's 2020 Standards of Performance of Distribution Licensees and Determination of Compensation Regulations, issued on 24 April 2020 as Regulation No. HERC/50/2020 (p1). They apply to all distribution and retail supply licensees, including deemed licensees, and to consumers in Haryana, and come into force from the date of publication in the Official Gazette. The first two pages are a Statement of Objects and Reasons describing the 2004 standards, a 2007 amendment, the Forum of Regulators' 2018 power-quality report and two rounds of state consultation (p1-2).

Regulations 1-2 set title, commencement and scope and then define the technical vocabulary for performance and power quality, including designated customers, point of common coupling, harmonics, voltage dips/swells, flicker, unbalance, SAIDI/SAIFI and normal operating conditions (p2-7). Regulation 3 says the specified standards are minimum acceptable service standards and distinguishes Schedule-I guaranteed standards, breach of which attracts compensation, from Schedule-II overall standards, breach of which does not (p7-8). It also provides for officer fines for missed timelines, agriculture-connection targets and metering obligations (p7-8). Regulation 4 leaves new connections, load changes, shifting and category changes to the Electricity Supply Code, 2014 (p8).

The largest block, Regulation 5, sets power-quality standards for supply voltage variation, flicker, unbalance, dips, swells, voltage and current harmonics, short interruptions and sustained interruptions, with measurement, averaging and reporting rules and reliability indices for 11 kV and 33 kV feeders (p8-14). It then prescribes phased PQ-meter deployment, compliance reporting and audits, and an incentive/disincentive regime that is deferred in the first year and applies from the second year (p14-18).

Regulation 6 gives restoration timelines for fuse-off, line breakdowns, cable faults, transformer failures and major failures, and rules for scheduled outages, load shedding, disconnection and reconnection (p18-19). Regulations 7-10 cover metering checks and replacement, billing complaints, compliance with CGRF/Ombudsman orders, call-centre establishment and complaint handling (p20-22). Regulation 11 sets reliability-index calculation and reporting. Regulations 12-19 provide exemptions, compensation determination, information reporting, directions, relaxation, removal of difficulties, amendment, and repeal of the 2004 regulations with savings (p23-25). Schedule-I begins on p26 with the guaranteed standards and compensation payable.

Standard name
Standards of Performance, Power Quality
Primary topics
Standards of performance, Power quality, Conditions of supply

Read with this

Voltaic last read HERC's website for final documents on 24 Nov 2026 (2 pages). A document HERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of HERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on herc.org.in ↗

Report an issue with this document