This is the Kerala State Electricity Regulatory Commission's 2008 principal regulation on how distribution licensees must procure power from cogeneration plants (p1). It opens with a Statement of Objects and Reasons that grounds the regulation in the Electricity Act 2003 and in the National Tariff Policy's directions on non-conventional energy, and records that the Commission had earlier framed norms for small hydro and wind tariffs after a consultative paper and a public hearing (p1, p3).
The operative text has seven regulations. Regulation 1 names the regulation and applies it to distribution licensees in the State, extending it temporarily to the STU or any licensee engaged in bulk purchase and sale of electricity for the State as a whole; it takes effect from the date of Gazette notification (p1). Regulation 2 defines the Act, Buyer, cogeneration, Commission, distribution licensee, licensee, renewable sources and STU (p2). Regulation 3 is the purchase obligation: it sets out the renewable purchase percentage split between small hydro, wind and other sources including cogeneration, describes how the obligation applies to the STU or bulk-purchase licensee, requires Buyers to declare proposed purchases in ARR/ERC filings and to source within Kerala, sets a priority rule based on date of commercial operation, requires payment security, allows a triennial review of the quantum, and lets a generator sell elsewhere on payment default (p4). Regulation 4 gives mandatory open access to any licensee's transmission or distribution system for renewable generation (p4).
Regulation 5 is the tariff provision: the Commission determines cogeneration tariffs case by case, guided by CERC principles and the national policy and tariff policy, with an applicability period, and preserves PPAs approved before notification (p4–5). Regulations 6 and 7 reserve the Commission's power to review to remove difficulties and to amend the regulations (p5).
Annex I (p6–7) supplies the Commission's assumptions for estimating bagasse-based cogeneration tariffs — plant utilisation factor, capital cost, plant life, depreciation, O&M, interest and loan term, and return on equity — and concludes with a levelised tariff to be paid uniformly by licensees for ten years without escalation. The annex is where the Commission's methodology and its resulting tariff figure sit, while the regulations themselves only establish the framework.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of KSERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.