Deviation Settlement Mechanism and Related Matters Regulations, 2018 — Draft
Telangana State Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) Regulations, 2018
Draft regulationDated 5 Jan 2019No.__/___/2018/TSERC- dated 05 January, 2019
Draft
A proposal, not law. Voltaic holds no final regulation made from this draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a draft Telangana State Electricity Regulatory Commission regulation to establish a state-level Deviation Settlement Mechanism (DSM) for grid discipline in intra-State electricity transactions. The preamble invokes the Electricity Act 2003 and the text is styled as a notification, but the notification number and Gazette date are left blank (p1). Regulations 1–3 set the short title, a split commencement—general provisions on Gazette notification, commercial arrangements and deviation charges/penalties six months later—and definitions and objective (pp1–4).
Regulation 4 limits application to short-, medium- and long-term open access transactions using intra-State transmission or distribution, including inter-State wheeling. It covers sellers connected to intra-State transmission (open access generators, captive generators other than in-situ captive, and all renewable generators except wind and solar) and buyers including distribution licensees, deemed distribution licensees and full open access consumers on intra-State transmission. Wind and solar are routed to the separate 2018 forecasting/scheduling/DSM regulation; partial open access consumers and all open access consumers on distribution networks are routed to the 2006 Interim Balancing and Settlement Code (p4).
Regulations 5–8 set duties and process: State entities must report contracts, follow the IEGC and State Grid Code, sign connection/open access agreements, install time-synchronised meters at defined intervals, and obey SLDC despatch instructions; SLDC must publish pool information (pp4–5). Regulation 6 lists the DSM design parameters—scheduling period, despatch principles, frequency operating range, deviation, weekly settlement, units for the State Deviation Pool Account, price vector, volume limits, and loss allocation—and ties the price vector to CERC DSM 2014 (pp5–7). Regulations 7–8 cover declaration/scheduling under the Grid Code and open access regulations and empower the Commission to inquire into gaming and disallow deviation charges (pp7–8).
Regulations 9–12 are the operative commercial core. Regulation 9 makes deviation charges payable/receivable for over/under-drawal and injection, adopts the CERC price vector and Annexure I, sets caps, dead bands, the zero-charge frequency, the ACP-linked band, and infirm-power treatment (pp8–9). Regulation 10 sets volume limits for buyers and sellers, additional deviation charges across frequency bands, and the periodic sign-change requirement, with Annexure II tables (pp9–12). Regulation 11 exempts infirm and start-up power from volume limits and additional charges for limited periods (p12). Regulation 12 requires SLDC to publish computation procedures and weekly deviation accounts, and preserves Section 142 action (pp12–13).
Regulations 13–17 cover settlement and governance: monthly State Energy Account, billing of open access consumers through distribution licensees, weekly deviation statements and the State Deviation Pool Account, payment timelines and interest, letter-of-credit security, and a State Power Committee within a fixed period after notification (pp13–16). Regulations 18–21 give the Commission powers to amend, remove difficulties, relax and issue directions (p16). Annexure I contains the price-vector table and the differentiated treatment for inter-State open access transactions of State entities (pp18–20); Annexure II contains additional-charge tables for buyers/sellers and for under-injection by coal/lignite/APM-gas stations (pp21–23); Annexure III illustrates the DSM price vector (p24). The document is signed by the Commission Secretary and dated 5 January 2019 at Hyderabad (p17).
Read with this
Voltaic holds no final regulation made from this draft.
Proposed changes (drafts with no final yet)
Voltaic last read TSERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document TSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.