Summary
Summary written by software. Check the regulator's original before you rely on it.
This is TSERC's principal regulation for bringing wind and solar generation on the Telangana state grid into a forecasting, scheduling and deviation-settlement discipline. It was issued on 30 May 2018 as No. TSERC/3/2018 and published in the Telangana Gazette on 31 May 2018 (p1). The opening pages explain the need: large solar and wind additions against the central target of 100 GW solar and 60 GW wind by 2022, while the CERC framework covers only stations connected to the central grid, leaving the state grid exposed (pp2–4). The Commission therefore adopts the Forum of Regulators' model regulation (p4–5).
Chapters 1–3 set commencement, a full definition set and applicability. The regulation binds all wind and solar generators on the intra-state transmission system, including those connected through pooling stations and selling power within or outside Telangana, but excludes rooftop solar and applies only where the combined capacity at a sub-station or pooling station — or of an individual generator elsewhere — is at least 5 MW (pp5, 10).
Chapter 4 is the operational core: day-ahead and week-ahead schedules in 15-minute blocks, one-and-a-half-hourly revisions with separate caps for wind and solar, the option of buying SLDC forecasting services, mandatory forecasting tools with a commissioning bar on new plants, and written-consent arrangements with QCAs (pp10–13). Chapters 5–7 cover metering, QCA eligibility (including the 51% appointment rule) and the QCA's role as a facilitator with no statutory status (pp13–15). Chapter 8 sets the deviation-charge slab table, review horizons and the anti-gaming procedure; Chapter 9 routes generators selling outside the State to the CERC DSM framework (pp16–19).
Chapters 10–20 give the implementation procedure, metering specifications, communication software, the deviation accounting arithmetic (state-level D minus pooled R, reallocated in proportion to deviation), settlement, payment security and de-pooling (pp19–23). Chapter 21 is a milestone timeline table — three months for tools and procedures, six months for commercial arrangements with a trial run of up to three months — followed by dispute resolution and the Commission's standard reservation-of-powers clauses (pp24–27).
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read TSERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document TSERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of TSERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.