PSERC · Punjab State Electricity Regulatory Commission
Punjab Framework for Resource Adequacy Regulations, 2024
Punjab State Electricity Regulatory Commission (Framework for Resource Adequacy) Regulations, 2024
RegulationDated 15 Mar 2024Published in the Gazette 15 Mar 2024PSERC/Secy/Regu: 187 dated The 15th March, 2024
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Punjab State Electricity Regulatory Commission made these regulations under s.181 read with ss.61, 66 and 86 of the Electricity Act 2003 and notified them on 15 March 2024 (p1). They replace the Commission's 2012 power purchase and procurement process regulations and set up Punjab's resource adequacy framework: a mechanism for assessing demand, planning generation and transmission resources, planning procurement, and monitoring compliance so that load is served reliably with an optimum generation mix (p1, p3). They come into force from the date of the Gazette notification and extend to the whole State of Punjab (p1).
Chapter 1 (pp1–3) gives the title, commencement and extent, the objective, the scope — generating companies, distribution licensees, SLDC, STU and other grid-connected entities and stakeholders in Punjab — and a definitions list built around capacity credit, expected/normalised energy not served, loss of load probability, net load, planning reserve margin and the three plan horizons. Chapter 2 (p3) describes the framework's four steps and fixes a ten-year planning period on an annual rolling basis. Chapter 3 (pp3–6) specifies how long-, medium- and short-term demand and energy forecasts are to be built: consumer-category energy forecasting with named candidate methodologies, statistical selection criteria, load-research refinement, addition of distribution and transmission losses, peak-demand derivation from load factors, and mandatory sensitivity scenarios; it then sets the annual submission chain from distribution licensee to SLDC to STU and on to CEA, NLDC and RLDC.
Chapter 4 (pp6–10) is the analytical core. It prescribes preparation of the generation resource map and the parameters to be recorded per plant, a net-load-based methodology for computing capacity credit factors (with separate treatment for RE, hydro and thermal), assessment of the planning reserve margin against reliability indices, and determination of the resource adequacy requirement and resource gap using scenarios. It governs the distribution licensee's LT-DRAP and the SLDC's ST-DRAP, positions CEA's LT-NRAP and NLDC's ST-NRAP as guidance, sets the required contracting tie-up for the first and second years, and prescribes a suggested split of resource adequacy requirement across long-, medium- and short-term contracts, with day-ahead market purchases excluded from that contribution.
Chapter 5 (pp10–12) covers procurement planning: optimal resource mix through least-cost modelling, procurement tenure and regional preference, capacity sharing, prior Commission approval of new capacity tie-ups and of long/medium-term PPAs and PSAs, and the limited circumstances in which additional or emergent short-term procurement may be made without prior approval. Chapter 6 (p12) makes resource adequacy compliance mandatory, with non-compliance charges to be determined by the Commission. Chapter 7 (pp12–13) sets the data maintenance and sharing protocol and the annual timelines for the national and state plans. Chapter 8 (pp13–14) provides for publication of the merit order dispatch stack, consultation with central and regional bodies, and the Commission's powers to issue orders and practice directions, relax provisions, remove difficulties and amend; it also repeals the 2012 regulations with a savings clause. Annexure-I (pp15–16) specifies the constraints the optimisation model must respect.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of PSERC's website on 26 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.