Terms and Conditions of Tariff Regulations, 2009 — Appendix-II: Timeline for completion of Projects

Timeline for completion of Projects

RegulationDate not stated

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is Appendix-II, "Timeline for completion of Projects", referred to by Regulation 15 of its parent instrument (the parent regulation itself is not reproduced here). It sets out how long a generating company or transmission licensee is allowed for project completion, counted from the date of investment approval by the Board or CCEA clearance, as applicable, to the date of commercial operation of a unit, block or transmission element (p1).

Part A covers thermal power projects. It gives separate completion schedules for coal/lignite plants by unit size and technology, and for combined-cycle gas plants by gas-turbine ISO rating, differentiating greenfield from extension projects and fixing the interval at which subsequent units or blocks may follow (p1–2).

Part B leaves hydro electric projects to the qualifying time schedule in the original concurrence issued by the Central Electricity Authority under section 8 of the Act, rather than prescribing its own periods (p3).

Part C sets qualifying time schedules for transmission works — lines and substations by voltage class, plus HVDC terminals — with different periods for plain, hilly, snowbound and very difficult terrain (p3–4). Two notes govern schemes that combine project types, where the longest activity governs, and lines crossing more than one terrain type, where a line-length weighted composite schedule applies (p4).

Standard name
Tariff Regulations

Read with this

No other documents to read with it are on Voltaic.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of CERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.