OERC · Odisha Electricity Regulatory Commission
Odisha Grid Code Regulations, 2015
CodeDated 11 Aug 2015No. 967---Engg. 17/2005-(Vol. VIII) dated The 11th August, 2015
Summary
Summary written by software, from pages 1 to 34 of 122. Check the regulator's original before you rely on it.
The Odisha Grid Code (OGC) Regulations, 2015 is the State's grid code, notified by the Odisha Electricity Regulatory Commission on 11 August 2015 and coming into force on publication in the Official Gazette (p1). It repeals the Orissa Grid Code Regulations, 2006 (p1), extends to the whole State, and binds all Users connected to or using the State Transmission System, including the Transmission Licensee (p1). The Commission frames it as the boundary document between the Transmission Licensee/SLDC and other Users — laying down information requirements and operating procedures, while expressly not regulating the detailed design and operation of generators, power stations, suppliers and distribution systems (p2). It must stay consistent with CERC's Indian Electricity Grid Code, which prevails in case of inconsistency (pp2, 8).
Chapter 1 (pp2–22) is general: objectives and scope; interpretation; free governor mode of operation, effective from a date to be separately notified by CERC and exemptible only by CERC; reactive energy charge/payment as per Commission orders; exemptions from the Code only on prior petition to the Commission; confidentiality of User information held by STU/SLDC; dispute resolution by the Commission; State Government policy directives; the non-compliance ladder via the Grid Co-ordination Committee to the Commission; and the Section 1.19 definitions table (pp9–22).
Chapter 2 (pp23–26) restates the statutory roles of SLDC (apex body for integrated operation, scheduling and despatch, metering and data collection, State deviation/UI pool and reactive energy accounts, ancillary services, Sub-LDCs, and certification of transmission availability, PLF and hydro capacity index), the STU (planning and co-ordination, non-discriminatory open access, and operating the SLDC until a separate entity is notified), the Transmission Licensee and the Distribution Licensee (including a round-the-clock DSOCC).
Chapter 3 (pp27–33) is the Planning Code: planning philosophy and consultation with CEA/CTU/ERPC, planning criteria listing the contingency outages the system must withstand without load shedding or with rescheduling of generation, reactive compensation planning, standard and detailed planning data, implementation of the plan, a ten-year perspective plan with five-year demand forecasts, and the allocation of load-forecasting responsibility with annual submission deadlines and a ninety-day STU integration window.
Chapter 4 (p34 onward) opens the Connection Conditions — minimum technical and design criteria, compliance with CEA connectivity standards, site responsibility schedule and connection agreement — applicable to all new connections, with existing Users given two years from commencement to modify their systems (p34). The arrangement list at pp3–6 shows eleven further chapters covering the operating code, scheduling and despatch, monitoring of generation and drawl, cross-boundary safety, protection, metering and data acquisition, management of the OGC, data registration and miscellaneous provisions.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read OERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (9 pages) and for drafts on 21 Nov 2026. A document OERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of OERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.