HERC · Haryana Electricity Regulatory Commission
Terms and Conditions of License for Deemed Licensee Regulations, 2020
Haryana Electricity Regulatory Commission (Terms and Conditions of License for Deemed Licensee) Regulations, 2020
RegulationDated 18 Sep 2020HERC/ 52 / 2020 dated 18th September, 2020
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is HERC's principal regulation laying down the terms and conditions of licence for "deemed licensees" — persons deemed to be licensees under section 14 of the Electricity Act 2003 — across Haryana. It was notified on 18 September 2020 as Regulation No. HERC/52/2020 and takes effect from the date of publication in the Haryana Government Gazette (p1); the Gazette date is not printed, though the signing block is dated 14.09.2020 (p7).
Part I (p1–2) sets the short title, commencement, whole-of-State extent and scope to deemed licensees under section 14, and defines the terms that carry the rest of the document: Deemed Licensee, Full, Partial and Embedded Open Access Consumer, Grid Code, IEGC and Load Despatch Centre, with residual definitions borrowed from the Act, the Grid Code and other HERC regulations.
Regulations 5–7 (p2–3) are general conditions: compliance with HERC regulations, codes, orders, guidelines, practice directions and with NLDC/RLDC/SLDC, CEA and other statutory directions; referral of licence disputes to the Commission; payment of fees under the 2005 Fee Regulations as amended, with the barring power under section 19 for non-payment; participation in standards-making; and liability under sections 142 and 146 for contravention.
Regulations 8–12 (p3–5) are technical and operational: annual ten-year load forecasting and cooperation with the STU; a transparent, economical power procurement obligation with a duty to arrange alternate or standby power (including standby arrangements with DHBVN/UHBVN and a fallback temporary tariff where the Commission has not determined standby charges); compliance with the State Grid Code, the Distribution Code (with possible relief by order) and operating standards; information-sharing and compliance with SLDC/STU directions; and a list of specific obligations — clearing dues before disconnection, ABT metering at interface points under the CEA Metering Regulations 2006, joint meter reading with DISCOMs/HVPN, reactive energy charges, settlement of transmission/open access/SLDC charges with HVPNL/DISCOMs, and SCADA telemetry.
Regulations 13–14 (p5–6) apply the 2004 Conditions of Licence for Distribution and Retail Supply Business to deemed distribution licensees, and classify a deemed licensee that consumes all the power it buys — with no other consumer — as an embedded or full open access consumer, liable for transmission/wheeling, cross-subsidy and additional surcharge, standby power charges, DSM 2019 imbalance charges, losses and RPO obligations.
Regulations 15–21 (p6–7) are the enabling and miscellaneous clauses: power to issue orders and directions, remove difficulties, relax provisions, decide interpretation finally, preserve inherent powers, conduct enquiries under the Conduct of Business Regulations 2004, and amend the regulations.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read HERC's website for final documents on 24 Nov 2026 (2 pages). A document HERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of HERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.