JSERC · Jharkhand State Electricity Regulatory Commission
Guidelines for Establishment of Forum for Redressal of Grievances of the Consumers, Electricity Ombudsman and Consumer Advocacy (First Amendment) Regulations, 2022
Jharkhand State Electricity Regulatory Commission (Guidelines for establishment of forum for redressal of Grievances of the Consumers Electricity Ombudsman and Consumer Advocacy) (First amendment), Regulations, 2022.
AmendmentDated 26 Aug 2022Published in the Gazette 29 Aug 2022No.88 dated 26 August, 2022
Amends the Consumer Grievance Redressal Forum, Electricity Ombudsman and Consumer Advocacy Regulations, 2020.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the First Amendment to JSERC's 2020 regulations that create the consumer grievance redressal machinery — the Consumer Grievance Redressal Forum, the Electricity Ombudsman and consumer advocacy. It is notification No.88 dated 26 August 2022, printed in the Jharkhand Gazette Extraordinary of 29 August 2022 (p1). The Commission says the 2020 principal regulations (notified 12 January 2021) contain ambiguities needing clarification, especially the essential requirements for the post of Electricity Ombudsman and for the Second Member of the Forum (p1).
Chapter I names the regulations, applies them to all distribution licensees in Jharkhand in their respective licensed areas, brings them into force on gazette publication, and defines 'Principal Regulations' (p2). Chapter II makes six substitutions in the principal regulations (p2–3): clause 4.1(b) is replaced with the qualification, experience and grade requirements for the Forum's Second Member, including an option to appoint a serving licensee officer who relinquishes his post and a bar on holding any other office of profit; clause 9(1) is corrected so its Explanation refers to clause 9(1) instead of clause 10(1); clause 11.4 is replaced to let the Forum order inspections or engage third parties, with the reasons to be recorded and costs normally borne by the licensee as a pass-through in tariff determination (advance deposit where the complainant requests the inspection); clause 11.7 restates the right of parties to appear in person or through an advocate; clause 16(2) sets out Ombudsman recruitment through public advertisement and three alternative eligibility tracks; and clause 16(6) provides for the Ombudsman's secretariat and office, funded by the Commission, with a technical officer taken on deputation (p3).
The instrument is short and operative-only. It is directed principally at distribution licensees and the redressal institutions they staff; no savings clause, transition period or repeal is stated.
Read with this
The regulation
Voltaic last read JSERC's website for final documents on 24 Nov 2026 (5 pages) and for drafts on 21 Nov 2026. A document JSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.