This is a Gujarat Electricity Regulatory Commission instrument — styled on its opening page as a *draft* — that would replace the Commission's 2005 standards-of-performance regulations with a more granular regime for distribution licensees in Gujarat. It applies to every licensee engaged in electricity distribution in the State and to all consumers (p1), and comes into force on the date of publication in the Official Gazette (p1); the signing page carries the date 19/02/2022 (p32).
Chapters I–II set the title, extent and commencement, and define the vocabulary the rest of the document leans on — area of supply, rural and urban areas, and the four reliability indices CAIDI, MAIFI, SAIDI and SAIFI (p1–3).
Chapter III lays out a complaint-handling discipline: a consumer's right to a minimum standard of service, a mandatory "Manual of Practice for Handling Consumer Complaint / Consumer Charter" filed with the Commission for approval and published in English and Gujarati, guaranteed-standards publicity in January and July bills, registration of every complaint, a 24/7 toll-free call centre, unique complaint numbers, a common CRM system with auto-escalation, and monthly grievance redressal meetings at sub-division and circle level (p3–7).
Chapter IV is the operational core: guaranteed standards of performance expressed as maximum permissible times for raising demand notes, energising new/enhanced/shifted/converted connections, temporary connections, shifting of meters, lines and transformer structures, transfer of service connection, tariff reclassification, billing and metering complaints, reconnection after disconnection, restoration of supply by fault type, scheduled outages, and power-quality complaints such as neutral voltage and voltage variation (p7–14).
Chapter V turns to system-level performance: how the licensee must compute and disaggregate SAIFI/SAIDI/CAIDI/MAIFI, treat agricultural feeders separately, define momentary versus sustained events, automate feeder data capture, validate against DT and consumer meters, and leave base/target index values to a later Commission order. It also covers safety and earthing obligations, street-light and residual complaints, and harmonic monitoring against grid-connectivity limits (p14–20).
Chapter VI is the enforcement lever: compensation the licensee must pay automatically for a listed set of parameters, a claim-based route for the rest, eligibility conditions tied to bill-payment record and past theft/unauthorised-use findings, escalating amounts as a claim moves through representation and then the CGRF/Ombudsman, a bar on recovering compensation through the ARR, and a service-by-service compensation table (p20–29).
Chapter VII requires quarterly, half-yearly and annual reporting in the Appendix D formats to the Commission and the Ombudsman, publication of performance information, independent compliance checks, and a licensee-level Annual Review Committee. Chapter VIII repeals the 2005 regulations with savings, and provides for partial invalidity and force-majeure relaxation (p30–32). Appendices A–D and Performa SoP 001–019 supply the registers, the compensation claim form and the periodic reporting formats (p33–49).
Read with this
Voltaic holds no final regulation made from this draft.
Proposed changes (drafts with no final yet)
- Dated 19 Feb 2022Explanatory memorandum: Explanatory Memorandum for Draft Standard of Performance of Distribution Licensee Regulations, 2022
Voltaic last read GERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 23 Nov 2026. A document GERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.