Summary
Summary written by software, from pages 1 to 37 of 40. Check the regulator's original before you rely on it.
AERC's principal framework for setting renewable energy tariffs in Assam, notified 10 September 2012 and printed in the Assam Gazette Extraordinary of 7 November 2012 (p1). It is made under s.61 read with s.181(2)(zd) of the Electricity Act 2003 and is stated to be modelled on the CERC RE Tariff Regulations, 2012 (p2).
The first block (pp1–6) contains the short title, commencement, definitions and application. The regulations apply to *new* RE projects commissioned in Assam that sell to distribution licensees and whose tariff the Commission determines under s.62 read with s.86, subject to technology-wise eligibility criteria — new plant and machinery, size and fuel-use limits, and MNRE-approved technologies. Existing RE projects are expressly left to their own RE Tariff Orders (p5).
Chapter I (pp7–10) settles the ground rules: a five-year control period, tariff periods that differ by technology, project-specific tariff for listed project types, the petition procedure and forms for tariff determination, a single-part tariff structure (with a separate fuel-cost component for fuel-based technologies), levellised tariff design, and despatch treatment — most RE plants are 'must run', while larger biomass, cogeneration and solar plants follow the AERC Grid Code scheduling and despatch rules.
Chapter II (pp11–14) lays down the common financial principles applied across technologies: what capital cost includes, the debt-equity norm and its treatment for project-specific tariff, loan tenure and the interest-rate benchmark, depreciation method, return on equity, working-capital composition and interest rate, O&M escalation, rebates, late-payment surcharge, sharing of CDM proceeds, treatment of subsidies and incentives, and taxes as a pass-through.
Chapters III to X (pp15–34) are the technology chapters — wind, small hydro, Rankine-cycle biomass, non-fossil-fuel cogeneration, solar PV, solar thermal, biomass gasifier and biogas. Each follows a template: technology scope and qualifying criteria, a base capital cost for the first control year, a WPI-linked capital cost indexation formula with technology-specific weights, CUF or PLF norms, auxiliary consumption, station heat rate or specific fuel consumption, O&M expenses with escalation, and (for fuel-based technologies) fuel cost, calorific value, fuel price indexation and monitoring obligations.
Chapter XI (pp35–36) covers deviation from norms, the Commission's powers to relax, amend and remove difficulties, the overriding effect over the 2006 tariff regulations, and the repeal of Regulations 6 and 7 of the 2009 RE regulations with a savings clause. Petition forms are appended from p37.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read AERC's website for final documents on 30 Sep 2026. A document AERC issued after the page that lists it was read may not be held by Voltaic yet.