Terms and Conditions for Determination of Tariff (Second Amendment) Regulations, 2024

Kerala State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) (Second Amendment) Regulations, 2024

AmendmentDated 27 Feb 2024No.3279 /Con. Engg/2023/ KSERC dated 27th February, 2024

Replaced by Multi Year Tariff Regulations, 2026

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Terms and Conditions for Determination of Tariff Regulations, 2021.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on dev.erckerala.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a one-clause amending regulation issued by the Kerala State Electricity Regulatory Commission on 27 February 2024 (p1). It rewrites Regulation 34(iv) of the KSERC (Terms and Conditions for Determination of Tariff) Regulations, 2021, which governs how the pension-liability bonds issued by KSEB Ltd to the Master Trust are treated in the licensee's Aggregate Revenue Requirement and truing up.

The notification first reproduces the draft text published on 6 August 2021, under which only interest on the Master Trust bonds was allowed in ARR and principal repayment was excluded (p1). It then reproduces the finalised 2021 text, which allowed both interest and principal to be reckoned in ARR and truing up after the stakeholder consultation and public hearing of 15.09.2021 (p1–2). It records that the Kerala High Court, by order dated 7 September 2023 in WP(C) No. 19205 of 2023, set aside Regulation 34(iv) to the extent it departed from the draft, for non-compliance with s.181(3) of the Electricity Act, 2003 and the Electricity (Procedures for Previous Publication) Rules, 2005, and that the clause consequently stood modified to allow only interest (p2).

Exercising the liberty granted by the same order, the Commission substitutes Regulation 34(iv) so that the amounts required for payment of both principal and interest on Master Trust bonds serviced by KSEB Ltd are reckoned for computation of ARR and for truing up of KSEB Ltd's accounts (p2). The Explanatory Memorandum (pp3–4) narrates the pension-liability background, the MYT order of 25.06.2022, KSEB Ltd's petition OP No. 18/2023, the writ petition, the re-notification of the draft Second Amendment on 01.12.2023, the hybrid hearing of 04.01.2024, and the decision to publish the approved amendment in the gazette.

It applies to KSEB Ltd and to the Commission's tariff-determination and truing-up exercises; it comes into force on gazette publication, a date not printed in the text (p1).

Standard name
Tariff Regulations
Primary topics
Tariff determination, ARR and true-up, Return, financing and working capital

Read with this

Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on dev.erckerala.org ↗

Report an issue with this document