This is KERC's principal regulation replacing its 2016 rooftop-solar framework with a wider 'Distributed Solar PV (DSPV)' regime covering grid-interactive solar plants up to 10 MW installed at consumer premises (p3–4). The Preamble explains the trigger: Karnataka had 21,961.67 MW of RE installed as of 31 March 2026 (57% of 38,196 MW), of which DSPV is about 899.53 MW; the 09.07.2025 order renamed SRTPV as DSPV, allowed facade panels and elevated ground structures, and introduced Virtual and Group Net Metering (p1–2). A draft was published on 6 June 2026, a public hearing held on 7 July 2026, with stakeholders asking for net metering for all categories up to a 3 GW State threshold and up to 1000 kW; the Commission adopted the 1000 kW net-metering cap (p2, p7).
The regulations define the metering mechanisms — net metering, net billing, gross metering, group net metering, virtual net metering and behind-the-meter — and set eligibility and minimum/maximum capacity limits for each (p3–9). Regulations 4.1.1–4.1.2 allow all consumer categories net metering from a 1 kW minimum up to the sanctioned load/contracted demand or 1000 kW, whichever is lower, and Regulation 3.6 makes this applicability and the capacity limits conditional on total installed DSPV plus VNM/GNM capacity staying below 3 GW. Energy accounting rules for each mechanism, including time-of-day set-off sequencing, monthly settlement of surplus, and the rates at which surplus from GNM and VNM is purchased, appear in Regulations 5.1–5.6 (p10–15).
Regulation 6 lets the Commission determine Grid Support Charges later; Regulation 7 preserves MNRE and State subsidies (p15). Regulations 8–11 cover hosting capacity and interconnection (including the 80% distribution-transformer limit for sub-150 kW plants), technical standards and safety, metering infrastructure (AMI, smart meters, CEA Metering Regulations 2006, interconnection point locations), and energy accounting during meter defects including a CUF-based estimate (p15–18).
Regulations 12–16 set the online application and commissioning timelines, the VNM/GNM SOP to be prepared by BESCOM, website disclosure duties, other provisions such as the DC-capacity tolerance, multiple units, shifting, deemed PPA approvals and termination, and the parameters for determining generic DSPV/Solar PV tariffs (p18–26). Regulations 17–25 cover RPO/RCO consumption obligations, REC eligibility, powers to issue directions, relax, amend and remove difficulties, dispute resolution, repeal and savings of the 2016 Regulations, and interpretation (p26–28).
Read with this
Earlier drafts
Voltaic last read KERC's website for final documents on 24 Nov 2026 (3 pages) and for drafts on 23 Nov 2026. A document KERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of KERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.