KSERC · Kerala State Electricity Regulatory Commission

Framework for Resource Adequacy Regulations, 2026

Kerala State Electricity Regulatory Commission (Framework for Resource Adequacy) Regulations, 2026

Regulation · Gazette copyDated 11 Mar 2026Published in the Gazette 12 Mar 2026No. 3476/Con(T2)/2026/KSERC dated 11th March, 2026

The Gazette copy of the Framework for Resource Adequacy Regulations, 2026.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on dev.erckerala.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Kerala State Electricity Regulatory Commission's principal regulation creating a Resource Adequacy (RA) planning framework for the State, notified as KSERC Notification No. 3476/Con(T2)/2026/KSERC dated 11 March 2026 and gazetted on 12 March 2026 (p1). It is made under s.181 read with ss.61, 66 and 86 of the Electricity Act 2003, to give effect to the Ministry of Power's Electricity (Amendment) Rules 2022 (Rule 16) and the 2023 national RA Guidelines and Forum of Regulators model regulations (p1–2, p30). It extends to the whole State and comes into force from the Gazette notification date (p2).

The regulation builds a four-step cycle — demand assessment and forecasting, generation resource planning, procurement planning, and monitoring and compliance (p3, p6). Chapter 3 (p7–10) assigns the distribution licensee responsibility for long-term and hourly/sub-hourly demand and energy forecasting by consumer category, lists permissible forecasting methodologies, the drivers to be modelled, loss trajectory and peak-demand derivation, and fixes the annual submission chain to SLDC and then to CEA/NLDC (p9). Chapter 4 (p10–23) is the analytical core: it lists the generation data inputs, the modelling constraints (PRM/RAR, portfolio balance, RE, conventional, RPO, storage, operating reserve, demand response, transmission constraints), the capacity-crediting methodologies for renewables, storage and hydro (top-demand-hours, top-net-load-hours, and ELCC approaches, pp13–15), and the Resource Adequacy Requirement, LOLP/NENS and optimal planning reserve margin process (p17–23).

Chapter 5 (p23–25) governs procurement: least-cost optimisation of the resource mix, the permissible contracting routes (own generation, s.62, s.63 bidding, storage, traders, DEEP/PUShP, capacity sharing), advance-procurement lead times by technology and tenure (p25), and mandatory Commission approval of all new tie-ups, PPAs and PSAs (p25). Chapter 6 (p26) sets quarterly compliance reporting and a case-by-case non-compliance charge. Chapter 7 (p26–29) assigns data-maintenance and sharing duties to the licensee, SLDC, STU, SRLDC and NLDC, requires website publication of procurement and merit-order-despatch data, mandates a multi-disciplinary RA cell in the licensee, and sets the annual calendar of RA milestones (p28–29). Chapter 8 (p29) gives the Commission powers to direct, relax, amend and remove difficulties. The Explanatory Note (p30–31) records the consultation history.

Standard name
Resource Adequacy Framework
Primary topics
Resource adequacy, Power procurement and PPAs, Energy storage deployment

Read with this

The regulation

Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on dev.erckerala.org ↗

Report an issue with this document