KSERC · Kerala State Electricity Regulatory Commission
Framework for Resource Adequacy Regulations, 2026
Kerala State Electricity Regulatory Commission (Framework for Resource Adequacy) Regulations, 2026
RegulationDated 11 Mar 2026No. 3476/Con(T2)/2026/KSERC dated 11th March, 2026
Summary
Summary written by software. Check the regulator's original before you rely on it.
KSERC Notification No. 3476/Con(T2)/2026/KSERC dated 11 March 2026 publishes the Kerala State Electricity Regulatory Commission (Framework for Resource Adequacy) Regulations, 2026, made under s.181 read with ss.61, 66 and 86 of the Electricity Act 2003 (p1–2). They extend to the whole State and take effect from Gazette notification (p2). The preamble and explanatory note (pp30–31) present them as Kerala's discharge of Rule 16(2) of the Centre's Electricity (Amendment) Rules 2022, following the June 2023 Resource Adequacy Guidelines and the Forum of Regulators' model regulations, and as the planning backbone for the State's stated goal of 100% renewable energy by 2040 (p1–2).
Chapter 1 sets objective, scope and definitions (pp2–5). The Regulations bind generating companies, distribution licensees, the SLDC, the STU and other grid-connected entities in Kerala, with a proviso exempting distribution licensees that procure bulk power only from a seller licensee from separate RA obligations, though they must still furnish data (p2–3). Definitions fix the long- and short-term planning horizons, capacity credit, planning reserve margin, reliability metrics and contract tenure bands (pp3–5). Chapter 2 lays out the four-step framework — demand assessment and forecasting, generation resource planning, procurement planning, and monitoring and compliance — and assigns LT-DRAP to the distribution licensee and ST-DRAP to the SLDC (pp5–6).
Chapter 3 governs demand assessment: category-wise and hourly/sub-hourly forecasting, permitted methods, scenario analysis, loss trajectory and derivation of peak demand, with forecasts to SLDC by 30 April and SLDC aggregation to CEA/NLDC/RLDC and the Commission by 31 May each year (pp6–9). Chapter 4 covers generation resource planning: data inputs, hourly chronological optimisation with stated constraints (resource adequacy requirement, portfolio balance, RE, conventional, RPO, storage, operating reserve, demand response, T&D), capacity-crediting methods and their application to RE, hydro, thermal and storage, the interface with CEA's LT-NRAP and NLDC's ST-NRAP, the annual vetting-and-approval chain, and the LOLP/NENS study used to arrive at optimal planning reserve margins (pp9–22).
Chapter 5 sets procurement planning — least-cost modelling, permitted procurement routes, indicative lead times, prior Commission approval of PPAs/PSAs and deviations under the 2021 Tariff Regulations (pp22–25). Chapters 6–8 cover quarterly compliance and non-compliance charges, data sharing, website disclosure, a dedicated RA cell, the annual milestone calendar, and the Commission's powers to direct, relax, amend and remove difficulties (pp25–29).
Read with this
Other copies of these documents (1)
- Dated 11 Mar 2026Framework for Resource Adequacy Regulations, 2026
Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of KSERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.